Key takeaways
- GE Vernova reported a 116 GW gas power backlog at mid-2026, of which about 63 GW was paid slot reservations rather than firm orders.3
- Power transformers averaged 128 weeks and generator step-up units 144 weeks in Wood Mackenzie’s Q2 2025 survey, with some high-capacity units quoted at up to four years.24
- Large diesel generators are quoted at roughly 18–24 months, and switchgear, generator and cooling suppliers report long backlogs as data center orders absorb factory capacity.56
- Tariffs on steel, aluminum and copper add cost and uncertainty to imported electrical equipment, and the rules were rewritten again in April 2026.78
- Sites with an existing substation, spare interconnection or a credible path to smaller on-site generation gain value when long-lead equipment sets the schedule.
01Why the supply chain now shapes data center schedules
For most of the last decade, the long pole on a data center project was the utility: how long it took to study a new load and build the lines and substation to serve it. That is still true in many places, but a second clock now runs beside it. The equipment that turns a utility commitment into a working campus (transformers, breakers, switchgear, generators, chillers, and for on-site power, turbines or engines) has its own multi-year queue.
The International Energy Agency’s 2026 review of energy and AI says supply chains for gas turbines and transformers, as well as advanced chips and IT components, tightened over the past year, and that the volume of proposed data center projects is straining planning and grid connection processes.1 In practice, a project can have a signed electric service agreement and still miss its power date because the main power transformer will not ship in time.
This guide covers the equipment categories that most often set the critical path, what public sources report about each as of 2026, and how the constraints feed back into which sites are worth pursuing. For the transformer and switchgear detail on its own, see our guide to transformer and switchgear lead times.
02Gas turbines: the tightest constraint for on-site power
Gas turbines matter to data centers in two ways: utilities need them to build new generation for large loads, and developers want them for on-site or bridge power. Both groups are ordering from the same three heavy-duty manufacturers. Reporting on the IEA’s findings says orders for gas turbines to power data centers rose about 70% in 2025.9
GE Vernova reported a gas power backlog of 116 GW at the end of the second quarter of 2026, up from 100 GW a quarter earlier and 83 GW at the end of 2025. About 53 GW was firm equipment backlog and about 63 GW was slot reservations, in which customers pay to hold a future production slot.3 Siemens Energy reported a 69 GW gas turbine backlog with lead times of three years or more, and Mitsubishi Heavy Industries reported 35 GW of large-frame backlog, with recently booked orders scheduled for delivery between 2028 and 2030.10
Fig. 1Gas turbine backlogs, mid-2026
- GE Vernova gas power backlog, Q2 2026
- 116 GW
- of that total held as slot reservations
- 63 GW
- Siemens Energy gas turbine backlog
- 69 GW
- Mitsubishi Heavy large-frame backlog
- 35 GW
Wood Mackenzie has estimated global manufacturing capacity at roughly 60–70 GW a year against about 110 GW of orders, and lead times for new combined-cycle plants have been reported at around five years, up from about three and a half in 2023.10 The practical effect is that smaller machines are taking roles once reserved for large frames: aeroderivative turbines and reciprocating engines are moving from backup duty toward primary power at some hyperscale projects.11 Our comparison of gas turbines and reciprocating engines covers that trade-off.
03Transformers, switchgear and breakers
Every campus needs large transformers: the main power transformers in the utility or customer substation, and many smaller units that step medium voltage down inside the campus. Wood Mackenzie’s Q2 2025 survey put average lead times at 128 weeks for power transformers and 144 weeks for generator step-up units, while distribution transformer supply has improved.2 Its modeling points to supply deficits of about 30% for power transformers and 10% for distribution transformers in 2025.2
Demand is the driver. Wood Mackenzie reports that U.S. demand for generator step-up units rose 274% and for substation power transformers 116% since 2019, that imports supply roughly 80% of U.S. power transformers, and that some high-capacity units are quoted at up to four years.4 It also projects U.S. data center capacity rising to about 110 GW by 2030 from around 24 GW, which keeps pressure on the highest-voltage equipment classes.4
Switchgear and circuit breakers are the next bottleneck. Reuters reported that utilities are scrambling to lock in equipment as data center demand strains supplies, with analysts expecting breakers and switchgear to face larger deficits.12 Lead times quoted for medium-voltage switchgear built to data center specifications vary widely by manufacturer and configuration, so written quotes for the exact specification are the only reliable number.
04Generators, cooling plant and chips
Backup generators
Large diesel generator sets remain the default backup for most campuses. A September 2026 trade analysis, citing manufacturer order books, put lead times at roughly 18–24 months for units above 2.5 MW; treat that as an estimate rather than a published manufacturer figure.5 Cummins reported record Power Systems revenue of $2.3 billion for the second quarter, citing strong demand for data center backup power, a multiyear agreement with a hyperscaler covering several gigawatts of future generator demand, and capacity limits on larger generator configurations through 2026.6
Chillers and cooling equipment
Cooling manufacturers are reporting order books that outpace shipments. Vertiv’s backlog roughly doubled over 2025 to about $15 billion.13 Trane Technologies acquired Stellar Energy, which brought about $1 billion of backlog and modular chiller products aimed at data centers.14 For sites, the shift toward liquid cooling and modular, factory-built cooling plant can shorten field construction but ties the schedule to a factory slot.
GPUs and IT equipment
Chips are a different kind of constraint. They do not sit on the site’s critical path the way a transformer does, but they set how fast buyers want capacity and where they will pay for speed. Coverage of the IEA’s 2026 findings notes a shortage of high-bandwidth memory used in AI accelerators that is expected to last through at least the end of 2027.15 When accelerators are scarce and expensive, an idle powered building is costly, which pushes buyers toward sites that can energize on a firm date.
05Tariffs and equipment costs
Much of the electrical equipment a campus needs is imported or built from imported metals, so trade policy moves both cost and timing. A 50% Section 232 tariff on copper took effect on August 1, 2025, and steel and aluminum tariffs were raised to 50% in 2025 and extended to many derivative products.7 Copper is central to transformer windings, switchgear, busway and cable, and steel and aluminum run through enclosures, racks and cooling equipment.7
An April 2026 proclamation restructured the metals tariffs again. For goods entered on or after April 6, 2026, duties apply to the full customs value of covered products, including derivatives, at tiered rates that depend on metal content, and hundreds of low-metal products were removed from scope.8 Rates, product coverage and expiration dates have shifted several times since early 2025, so a project budget should be checked line by line with a customs broker or trade counsel rather than built on a single headline rate.
06Lead times at a glance
The figure below summarizes reported lead times for the long-lead categories discussed above. Ranges reflect averages and upper quotes from different sources and dates, so they are a planning frame, not a quote.
Fig. 2Reported lead times for long-lead equipment
- Diesel gensets above 2.5 MW18–24
- Power transformers128 weeks avg. to 4 years
- Generator step-up units144 weeks avg. to 4 years
- Heavy-duty gas turbines3 years or more
Two cautions apply. Averages hide the specialized units that data centers often need, such as high-capacity transformers and data center specification switchgear. And a quoted lead time usually starts when the order is released with approved drawings, so engineering, submittals and approvals add time before the factory clock starts. Our guide to the energization timeline shows where these fit.
The categories also interact. A campus waiting on a main power transformer gains little from early generator delivery, and on-site generation that arrives before its switchgear cannot carry load. The useful exercise is to list every long-lead item for the first phase, attach a realistic order date and delivery window to each, and find the latest one. That item, not the average, sets the earliest credible date to energize.
07How equipment constraints change site selection
Equipment scarcity changes which sites rise to the top of a shortlist. When every new substation and generator needs a multi-year factory slot, a site that avoids some of that equipment, or already has it, is worth more.
Fig. 3Equipment exposure vs. power path
Best position
Existing substation or spare interconnection; ready sooner.
Order early
Good utility path but new substation gear on order.
Low priority
Little to build, but the grid cannot serve the load.
Hardest case
New grid assets and new generation both required.
Less ← Long-lead equipment needed → More
- Existing infrastructure counts. Retired plant sites, existing substations and powered land can reuse transformers, switchyards and interconnection rights. See surplus interconnection and retired plant sites.
- On-site power depends on equipment you can actually get. Heavy-duty turbines are booked years out, so plans increasingly rely on engines, aeroderivatives or phased generation.11 Our guide to on-site generation and bridge power covers the options.
- Phasing helps. A ramp schedule that starts with the load existing equipment can serve buys time for later units.
- Buyers with slot reservations move faster. Large developers and hyperscalers that pre-order equipment can match a site to equipment they already hold.3
For a landowner or early-stage developer, the useful questions are what equipment the site needs that does not exist today, who will own and order it, and whether the utility’s schedule assumes equipment already on order. If you want an outside view of a parcel, you can get a site reviewed.
Common questions
How long does it take to get a power transformer for a data center?
Wood Mackenzie’s Q2 2025 survey put the average lead time for power transformers at 128 weeks, or roughly two and a half years, and generator step-up units at 144 weeks.2 Some high-capacity units have been quoted at up to four years.4 Confirm current lead times with the utility and manufacturers for the specific rating you need.
Why are gas turbines so hard to get for data centers?
Utilities and data center developers are ordering from the same few heavy-duty manufacturers, whose production capacity is below current orders.10 GE Vernova reported a 116 GW gas power backlog at mid-2026, and Siemens Energy reported lead times of three years or more.310 Many projects are turning to smaller turbines and reciprocating engines instead.11
Do GPU shortages affect where data centers are built?
Indirectly. Chips do not set a site’s energization date, but scarce, expensive accelerators raise the cost of a powered building that sits idle, so buyers favor sites that can energize on a firm date. Coverage of the IEA’s 2026 findings points to a high-bandwidth memory shortage expected to persist through at least 2027.15
How do tariffs affect data center equipment costs?
Section 232 tariffs on copper, steel and aluminum raise the cost of transformers, switchgear, cable, enclosures and cooling equipment that use those metals.7 The tariffs were restructured again in April 2026, so check current rates and product classifications with a customs broker before budgeting.8
What kind of site is most resilient to equipment shortages?
Sites that need less new long-lead equipment: those near an existing substation with spare capacity, on a retired plant with reusable interconnection, or with a phased load that existing infrastructure can serve first. These sites still need equipment, but less of it sits on the critical path.
Notes
- 1.International Energy Agency, “Data centre electricity use surged in 2025, even with tightening bottlenecks driving a scramble for solutions,” 2026. iea.org
- 2.Power Magazine, “Transformers in 2026: Shortage, Scramble or Self-Inflicted Crisis?,” 2026. powermag.com
- 3.Utility Dive, “GE Vernova gas turbine backlog climbs to 116 GW,” 2026. utilitydive.com
- 4.pv magazine USA, “U.S. transformer market faces severe supply constraints as lead times extend to four years,” 2026. pv-magazine-usa.com
- 5.Datacentres.com, “Diesel, duty cycles and dollars: inside the $2.8M per MW backup power stack,” 2026. datacentres.com
- 6.Nasdaq, “Cummins Q2 Earnings Call Highlights,” 2026. nasdaq.com
- 7.Center for Strategic and International Studies, “The Impact of Tariffs on the AI Data Center Buildout: Balancing Supply Chain Security and AI Infrastructure Leadership,” n.d. csis.org
- 8.White & Case, “United States modifies steel, aluminum, and copper Section 232 tariffs,” 2026. whitecase.com
- 9.Eco-Business, “AI’s energy appetite is outpacing deployment of AI-based climate solutions: IEA,” n.d. eco-business.com
- 10.OilPrice.com, “The Gas Turbine Shortage Just Became AI’s Biggest Constraint,” 2026. oilprice.com
- 11.Power Engineering, “Data center power crunch lifts engines, aeroderivatives into larger role,” n.d. power-eng.com
- 12.Reuters (via American Journal of Transportation), “US power companies scramble to secure equipment as surging data center demand strains supplies,” 2026. ajot.com
- 13.Nasdaq, “Vertiv’s $15 Billion Backlog Is the Loudest AI Signal in 2026,” 2026. nasdaq.com
- 14.Trane Technologies, “Trane Technologies Wolfe Conference Transcript,” 2026. s2.q4cdn.com
- 15.Lightwave, “AI drives data center power investment surge says International Energy Agency,” n.d. lightwaveonline.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Related guides
More in Markets & economics
- Major U.S. Data Center Markets: Inventory, Absorption and Power
- Emerging Data Center Markets in the U.S.: Where Growth Is Moving and Why
- U.S. Data Center Electricity Demand Forecasts: LBNL, EPRI and Grid Operators
- Data Center Vacancy, Absorption and Pricing Trends in North America
- The Northern Virginia Data Center Market: History, Power Limits and Land Prices
- How Data Center Deals Are Structured: Shells, Build-to-Suits, Leases and JVs
- Who Finances Data Centers? REITs, Private Equity, Infrastructure Funds and Debt
- The Economic Impact of Data Centers on Communities: Taxes, Jobs and the Evidence
- Do Data Centers Raise Electricity Bills? Cost Shifting, Large-Load Tariffs and the Studies
- How Hyperscalers Choose Data Center Sites: Power First
