BlackForge Data Centers

Power & interconnection

Surplus Interconnection Service and Retired Power Plant Sites: How Existing Grid Rights Get Reused

Surplus interconnection service, created by FERC Order No. 845 in 2018, lets a generator owner add new resources that use the unused part of an existing interconnection without joining the back of the queue,12 and generator replacement rules in MISO, SPP and PJM let a retiring plant hand its interconnection rights to a new resource.34 Both paths can cut years off the generator side of a project when the median queue wait now exceeds four years, but they carry generator injection rights, not load service, so a data center at a retiring plant still needs its own arrangement with the utility and grid operator.56

Last reviewed · 10 min read · BlackForge Data Centers

Key takeaways

  • Surplus interconnection service uses capacity that an existing interconnection agreement already allows but the plant does not use, without raising the total injection limit at the point of interconnection.71
  • Generator replacement lets an owner retire a unit and keep its interconnection rights for a new resource; MISO’s process was approved in 2019 and SPP’s in 2020.38
  • In PJM, Capacity Interconnection Rights end one year after deactivation unless a replacement request is filed, and a faster replacement process took effect on January 30, 2026.94
  • FERC’s December 2025 PJM co-location order directed PJM to make surplus interconnection service available to new generators serving co-located load.6
  • Retirement dates are less predictable than they were: only 2.6 GW of coal capacity retired in 2025 against 8.5 GW planned, partly because of DOE emergency orders.10

01What surplus interconnection service is

Every large generator connected to a transmission system has an interconnection agreement that sets how much power it may inject at a defined point. FERC Order No. 845, issued in April 2018, required transmission providers to add a service to their tariffs called surplus interconnection service: the unused portion of the interconnection service granted under an existing agreement, used in a way that does not increase the total service at the point of interconnection.17

The reason surplus exists is how plants are studied. A new generator is studied and connected as if it will run at full output all the time, yet solar, wind and peaking units often produce well below nameplate.1 The wires, breakers and switchyard built for that worst case sit partly idle. A battery added beside a solar farm, or new generation added at a gas peaker, can fill that space without the transmission provider having to plan for more total injection.

Order No. 845 told transmission providers that their tariffs must do four things for this service:2

  • Provide an expedited process outside the normal interconnection queue, so the added resource does not need its own queue position.
  • Let affiliates of the original interconnection customer use the surplus for another generating facility.
  • Allow transfer of surplus that the original customer or its affiliates do not intend to use.
  • Specify the reliability studies and approvals the request must pass.

The same rule let customers request interconnection service below their facility’s full capacity, which matters for hybrid sites where some output is meant to stay on site.1 Transmission providers filed compliance tariffs in 2019, so the exact study steps differ by region.7 For the general mechanics of grid studies, see interconnection studies.

02Generator replacement: keeping the connection when a plant retires

Surplus service adds to a plant that keeps running. Generator replacement deals with a plant that is closing. Without a replacement path, an owner generally goes through the grid operator’s retirement process, may have to give up the interconnection rights tied to the old unit, and must file a fresh request for any new plant at the site, which then waits in a standard queue that can take two to four or more years depending on the region.3

Replacement procedures change that. As one FERC commissioner described them, they allow owners of an existing generating facility to keep the interconnection rights associated with it even after retiring it and replacing it with a new facility.11 MISO’s procedure was approved in 2019 and SPP followed with a similar one in 2020; a 2023 utility presentation to PJM stakeholders lists FERC acceptance of SPP’s revisions on June 30, 2020, alongside similar approvals for MISO, PacifiCorp and Arizona Public Service.38

The rules are not uncontroversial. The same commissioner asked whether they risk an undue preference for owners of existing plants over new market entrants competing for scarce grid capacity, and urged a broader review before more such procedures are approved.11 For a site buyer, the practical point is that replacement rights belong to the generator owner and follow the owner’s plans, not the land.

The process can also serve a restart. In 2025 FERC granted NextEra a waiver of parts of MISO’s tariff so the retired Duane Arnold nuclear plant in Iowa could use the generator replacement process for its recommissioning, with a commercial operation date extended to December 31, 2029.12 Our guide to nuclear and SMR siting covers restarts more broadly.

Fig. 1Three ways to reuse an existing grid connection

Plant keeps running

Surplus interconnection

  • Adds a resource behind an existing agreement
  • No increase in total injection at the POI
  • Expedited, outside the normal queue
  • Owner or affiliate first; unused surplus can transfer

Plant retires

Generator replacement

  • New resource inherits the retiring unit’s rights
  • Usually capped at the old unit’s capacity
  • Strict filing windows tied to retirement
  • Rights stay with the generator owner

Default path

New queue request

  • Any site, any size the system can take
  • Full cluster or serial studies
  • Median of more than four years to operation
  • Network upgrade costs assigned through studies
General patterns; eligibility, studies and timing are set by each region’s tariff. Queue median from LBNL.25

03How PJM handles retiring plants and co-located load

PJM deserves a close look because its rules for both retiring plants and co-located load changed in 2025 and 2026 (see data center site selection in PJM). Under PJM’s rules, the Capacity Interconnection Rights of a deactivated capacity resource terminate one year from the deactivation date unless the holder has submitted a completed interconnection request in that time, and an owner can associate those rights with a new resource’s application.9

On January 29, 2026, FERC accepted a separate, serial replacement generation process in PJM, effective January 30, 2026.4 A replacement qualifies if it connects at the same substation, at the same voltage, and does not exceed the deactivating unit’s maximum output. FERC had rejected an earlier version in August 2025 over concerns that it allowed open-ended extensions of commercial operation dates, and PJM refiled on October 31, 2025. FERC said the accepted process makes efficient use of existing infrastructure and reduces study timelines and costs.4

Fig. 2PJM replacement generation path, simplified

  1. 01

    Deactivation notice

    Owner tells PJM the existing unit will retire.

  2. 02

    Replacement request

    Filed within the window, or rights end after one year.

  3. 03

    Eligibility check

    Same substation, same voltage, no more than old output.

  4. 04

    Expedited study

    Separate serial study instead of the full cycle.

  5. 05

    New resource online

    Inherits the retiring unit’s capacity rights.

Simplified from the process FERC accepted in January 2026; confirm current manual and tariff terms with PJM.94

The co-location side moved at the same time. On December 18, 2025, FERC found PJM’s tariff unjust and unreasonable for lacking clear terms for generators serving co-located load, and directed PJM to make surplus interconnection service available to new generators that serve co-located load, along with provisional interconnection service and interconnection below nameplate capacity.6 On April 16, 2026, FERC accepted PJM’s compliance revisions clarifying interconnection pathways but rejected changes to the required definition of co-located load and ordered a further filing.13 The configurations themselves are covered in co-locating data centers with power plants.

FERC then went further: on June 18, 2026 it issued show-cause orders directing each of the six FERC-jurisdictional RTOs and ISOs, PJM included, to justify or reform their procedures for interconnecting large and co-located loads, with responses due in August 2026.14 The rules in MISO and SPP may therefore change through late 2026 and beyond.

04Injection rights are not load service

The most common misunderstanding about retired plant sites is that the plant’s interconnection can simply be pointed at a data center. Surplus interconnection service and generator replacement are generator processes. They carry the right to inject power at a point on the grid, and the studies behind them test what happens when power flows out of the site. A data center draws power in, often at a steadier and higher level than the old plant ever exported.

That leaves three broad options at a retiring plant site:

  1. 01Grid-served load. The data center takes service from the local utility like any other large customer, through the large-load interconnection process. The old switchyard may shorten the build, but the load study is new.
  2. 02New generation plus co-located load. The owner uses replacement or surplus rights for new generation and serves the campus from it, which in PJM now runs through the pathways the December 2025 order required.613
  3. 03Fully separate supply. The campus is islanded from the grid, which avoids load interconnection but leaves the site without grid backup. See behind-the-meter vs. front-of-the-meter.

The second option is why these rules matter for data centers. A generator that keeps its rights at a retiring plant can rebuild faster than a new plant elsewhere, and a campus beside it can take power behind the same connection. The trade is dependence on one plant owner, one set of tariff rules and studies that are still being worked out.

05Where the retiring plants are, and why timing is uncertain

The supply of sites depends on retirements, and retirements have slowed. U.S. power companies retired 2.6 GW of coal capacity at four plants in 2025, the least since 2010, after planning to retire 8.5 GW; 4.8 GW was pushed to later years and two plants totaling 1.1 GW cancelled retirement plans.10 For 2026, 6.4 GW of coal capacity was scheduled to retire, though EIA noted that renewed or new emergency orders could change that.10

Fig. 3Coal retirements, planned vs. actual

coal retirements planned for 2025
8.5 GW
coal capacity actually retired in 2025
2.6 GW
coal retirements scheduled for 2026
6.4 GW
held open by DOE orders, March 2026
4.4 GW+
EIA data on U.S. coal capacity; DOE order figure from POWER’s March 2026 tracker.1015

Much of the delay comes from Section 202(c) of the Federal Power Act. DOE orders under it last up to 90 days but can be reissued, as happened at J.H. Campbell in Michigan.10 Campbell’s original retirement date was May 31, 2025, and by March 2026 it was operating under a third extension; POWER counted at least 4.4 GW of coal capacity held open by such orders at that time.15 A plant under an emergency order is neither retired nor available for replacement on the owner’s schedule, which can stall any project that depends on its rights.

Where retirement does happen, the existing grid ties are the draw. The Homer City plant in western Pennsylvania shut in 2023 after 54 years, and its new owners announced a $10 billion campus with seven gas turbines generating up to 4.5 GW for on-site data centers, citing transmission lines to the mid-Atlantic and New York grids, substations and water already in place.16 They targeted power as early as 2027.16 The physical side of these sites (coal ash, demolition, water permits) is covered in repurposing power plant and industrial sites and brownfield cleanup and liability protections.

The value of skipping the queue is real. LBNL found that the median time from interconnection request to commercial operation rose from under two years for projects built in 2000–2007 to more than four years for those built in 2018–2024, and that only 13% of capacity requested from 2000 to 2019 had reached operation by the end of 2024.5 Our guide to power timelines and interconnection queues puts those numbers in context.

06What to check at a retiring plant site

A retiring plant can be one of the fastest routes to large power, or a site whose best asset belongs to someone else. Before relying on its interconnection, work through these questions with the plant owner, the transmission provider and the ISO or RTO:

  • What interconnection agreement covers the plant, and how many MW of injection does it allow? Ask for the agreement, not a summary.
  • Has a deactivation notice been filed, and when does the replacement window close? In PJM, rights lapse one year after deactivation without a request.9
  • Is the plant subject to a DOE 202(c) order or a reliability-must-run arrangement that could delay retirement?15
  • Would a replacement meet the region’s eligibility tests, such as PJM’s same-substation and same-voltage rule?4
  • How much of the existing connection is unused today, and could surplus service add generation for a co-located campus?6
  • Separately, what would load service from the utility require, and on what schedule?

Fig. 4Sample interconnection screen of a retiring plant

Illustrative
  • PassGenerator agreementExisting agreement for 600 MW of injection at a 345 kV switchyard.
  • WatchReplacement windowDeactivation filed; replacement request due in eight months.
  • WatchRetirement certaintyOwner reports a possible federal order to keep units online.
  • PassOwner cooperationOwner plans new gas units and wants a co-located load.
  • FailLoad serviceUtility says a grid-served load needs new 345 kV upgrades.
Illustrative sample. Not a real site; actual results depend on the agreements and studies.

Energy developers weighing these options from the generation side can start with our guide for energy developers. If you hold land at or near a retiring plant and want to know what its connection can realistically support, get a site reviewed.

Common questions

What is surplus interconnection service?

It is the unused part of the interconnection service granted to an existing generator, made available for new resources without increasing total injection at the point of interconnection.7 FERC Order No. 845 required transmission providers to offer it through an expedited process outside the normal queue.2

Can a data center use a retired power plant’s interconnection?

Not directly. Generator interconnection rights cover injecting power, while a data center needs load service, so the campus either takes utility service or is served by new generation that uses the plant’s rights.6 In PJM, the December 2025 co-location order set up pathways for new generators serving co-located load.6

How long do interconnection rights last after a plant retires?

It depends on the region. In PJM, Capacity Interconnection Rights terminate one year after deactivation unless a completed interconnection request has been filed in that time.9 MISO and SPP have their own replacement procedures with their own deadlines.8

Why are some coal plants not retiring on schedule?

Some owners delayed plans on their own, and DOE used emergency orders under Section 202(c) of the Federal Power Act to keep others running.10 Those orders last up to 90 days but can be reissued, as at J.H. Campbell in Michigan.10

Does generator replacement favor incumbent plant owners?

Critics argue it can. A FERC commissioner has questioned whether these procedures give owners of existing plants an undue preference for interconnection capacity over new entrants.11 Supporters point to faster timelines and lower study costs from reusing existing infrastructure.4

Notes

  1. 1.Norton Rose Fulbright, “Big changes in how new power projects connect to the grid,” 2018. nortonrosefulbright.com
  2. 2.Orrick, “FERC Order No. 845 Reforms Generator Interconnection Process, Advances Energy Storage,” 2018. orrick.com
  3. 3.Bloomberg Law, “It’s Time to Improve Generator Replacement Procedures and Rules,” n.d. news.bloomberglaw.com
  4. 4.Troutman Energy Report, “FERC Accepts PJM’s Replacement Generation Interconnection Process,” 2026. troutmanenergyreport.com
  5. 5.Lawrence Berkeley National Laboratory, “Queued Up: 2025 Edition, Characteristics of Power Plants Seeking Transmission Interconnection As of the End of 2024,” 2025. emp.lbl.gov
  6. 6.Akin Gump, “FERC Clears the Way for Co-Location,” 2025. akingump.com
  7. 7.Federal Energy Regulatory Commission, “Florida Power & Light Company, Order on Compliance Filing (Order Nos. 845 and 845-A), Docket No. ER19-1938-000,” 2020. ferc.gov
  8. 8.PJM Interconnection (AEP presentation to the Interconnection Process Subcommittee), “PJM IPS Transfer of CIRs Education: MISO, SPP, PacifiCorp, PJM,” 2023. pjm.com
  9. 9.PJM Interconnection, “CIR Transfer Problem Statement,” 2023. pjm.com
  10. 10.U.S. Energy Information Administration (via CleanTechnica), “U.S. Coal-Fired Generating Capacity Retired in 2025 Was the Least in 15 Years,” 2026. cleantechnica.com
  11. 11.Federal Energy Regulatory Commission, “Commissioner Clements Concurrence Regarding Duke Energy Carolinas, LLC,” n.d. ferc.gov
  12. 12.Troutman Energy Report, “NextEra Receives FERC Waiver to Facilitate Nuclear Plant Restart in Iowa,” 2025. troutmanenergyreport.com
  13. 13.Van Ness Feldman, “FERC Provides Further Guidance on Co-Located Load Interconnection,” 2026. vnf.com
  14. 14.Foley & Lardner, “FERC Issues Six Tailored “Show Cause” Orders to Accelerate Large Load Interconnection,” 2026. foley.com
  15. 15.POWER Magazine, “DOE Has Issued More Than 40 Section 202(c) Emergency Orders Since May 2025. Here’s an Updated Log,” 2026. powermag.com
  16. 16.Associated Press (via ABC News), “Pennsylvania’s largest coal-fired power plant, now retired, to become gas-powered data center campus,” 2025. abcnews.go.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Related guides

More in Power & interconnection