Key takeaways
- Any new reactor in the U.S. needs an NRC license, and the licensing path adds years before construction starts.
- NRC site criteria cover seismology, geology, hydrology, population density and exclusion areas, which narrow where reactors can go.
- Emergency planning zones have historically extended about 10 miles around large reactors; rules for smaller reactors allow scaling, but outcomes are project-specific.
- Many reactor designs need substantial cooling water; some advanced designs need less, but that depends on the specific technology.
- Treat new nuclear as an option with uncertain timing, and pair it with a near-term grid or on-site power plan.
01Why data center developers look at nuclear
Nuclear generation offers large amounts of firm, low-carbon power with very high availability. That profile matches a data center’s round-the-clock load well. Developers look at it in three ways: taking power from an existing nuclear plant, locating near an existing plant site that may add units, or planning a campus around one or more future small modular reactors (SMRs) or other advanced reactors.
Each path has very different timing. Power from an existing plant is a contract and grid question, closer to the co-location arrangements in our guide to co-locating data centers with power plants. New reactors are a licensing, construction and supply chain question measured in years, and for first-of-a-kind designs the schedule is hard to predict.
02NRC licensing: what any new reactor goes through
Commercial nuclear reactors in the U.S. are licensed by the Nuclear Regulatory Commission (NRC). No reactor can be built or operated without its approval, and that approval covers both the design and the specific site. The main regulatory paths are well established:
- A two-step process under 10 CFR Part 50: a construction permit, followed later by an operating license.
- A combined construction and operating license under 10 CFR Part 52, which can reference a standard design the NRC has already approved and an approved early site permit.
- An early site permit, also under Part 52, which resolves site suitability questions in advance, before a specific reactor is chosen.
A new license application also triggers environmental review under NEPA, with the NRC as the lead federal agency. The NRC’s licensing framework has been the subject of ongoing modernization for advanced and smaller reactors, and the details may change over a project’s life. What does not change is that licensing is a multi-year process with public participation, and that the site itself is reviewed in depth.
03What makes a site suitable for a reactor
NRC reactor site criteria, found mainly in 10 CFR Part 100, look at the site’s physical characteristics and its surroundings. Those criteria rule out land that would be fine for a data center.
| Factor | What the reactor review looks at | Compared with a data center |
|---|---|---|
| Seismology and geology | Faulting, ground motion and foundation conditions, studied in depth | Far more detailed than a standard geotechnical review |
| Population | Exclusion area, low population zone and nearby population density | Data centers often favor proximity to metros; reactors are constrained by it |
| Hydrology and flooding | Flooding from rivers, storms, dam failure and other extreme events | Goes well beyond FEMA floodplain mapping |
| Nearby hazards | Industrial facilities, pipelines, airports and transportation routes | A gas pipeline that helps a data center can complicate a reactor |
| Meteorology | Dispersion, extreme winds and severe weather | Mostly a cooling and hazard issue for data centers |
| Cooling water | Reliable supply for normal and emergency cooling, depending on design | Can be much larger than data center water needs |
Our guide to slope, soils and geotechnical review covers the ordinary data center side. For a reactor, that work is a starting point at most.
04Emergency planning zones and land use
Licensed reactors have emergency planning zones (EPZs) around them. For large light-water reactors, the plume exposure pathway EPZ has historically extended about 10 miles from the plant, with an ingestion pathway zone of about 50 miles. Within these zones, operators, states and local governments maintain emergency plans, warning systems and protective action procedures.
For smaller and advanced reactors, NRC rules allow the plume exposure EPZ to be sized based on the facility’s potential consequences, which in some cases could shrink it to the site boundary. Whether a particular design at a particular site qualifies is decided case by case through licensing. It should not be assumed at the site selection stage.
- A data center inside a reactor’s EPZ is generally possible, but it becomes part of the emergency plan, with implications for staffing, access and evacuation.
- A reactor on the data center campus brings security perimeters, controlled areas and an exclusion area that must be under the licensee’s control.
- Local land use planning around the reactor may restrict some future development nearby.
05Cooling water, land and transmission
Most operating U.S. reactors are light-water designs that reject large amounts of heat, usually through cooling towers or once-through cooling from a river, lake or ocean. That is why many nuclear plants sit on major water bodies. Withdrawals and discharges need state water rights or permits and Clean Water Act authorizations, and thermal discharges face their own limits.
Some advanced and smaller designs use different coolants or air-cooled heat rejection and may need far less water. That depends entirely on the design and is still being demonstrated for many technologies. At the site stage, assume a reactor may need significant water unless the specific design says otherwise. Our guide to data center water requirements covers the data center’s own water needs, which come on top.
Land and transmission matter too. A reactor site needs room for the plant, its exclusion area, security, laydown during construction and switchyards. Even if the data center uses most of the output, a grid connection is normally needed for backup, for reactor startup and for periods when the reactor is offline for refueling or maintenance.
06Lead times and how to plan around them
New nuclear has long lead times: site characterization, licensing, environmental review, supply chain, construction and startup all add up. For advanced designs that need specialized fuel, fuel supply is another dependency. First-of-a-kind projects carry more schedule uncertainty than designs with an operating track record. No one can give a reliable date for a reactor that has not yet been licensed.
For a data center developer, the practical approach is to treat nuclear as one option in a phased power strategy:
- 01Secure a site with a credible near-term power path, from the grid, on-site generation or both.
- 02Check the land against basic reactor siting factors: geology, population, flooding, nearby hazards and water.
- 03Hold enough contiguous acreage, and enough distance to neighbors, to keep a future reactor possible.
- 04Favor sites near existing nuclear plants or with prior site characterization where available.
- 05Revisit the nuclear option as licensing progresses and specific designs mature.
When we screen land with nuclear in mind, we keep the two questions separate: can this site host a data center on a useful timeline, and does it keep a future reactor on the table? A site that only passes the second test is not yet a data center site.
Common questions
Can a data center be built next to a nuclear power plant?
Generally, yes, though it involves more than an ordinary site. The data center may sit within the plant’s emergency planning zone, which brings it into emergency planning, and it cannot intrude on the plant’s exclusion area or security perimeter. Taking power directly from the plant raises contract, grid and regulatory questions that vary by market. Land near plant sites is often limited by existing corridors and buffers.
How long does it take to build a small modular reactor for a data center?
There is no reliable general answer. A new reactor needs NRC licensing, environmental review, a supply chain and construction, and first-of-a-kind designs carry added schedule uncertainty. The full process is measured in years. That is why most data center developers treat SMRs as a long-horizon option and plan grid or on-site power for the campus’s early phases.
What is an emergency planning zone?
An emergency planning zone is the area around a licensed reactor where emergency plans and protective actions are prepared in advance. For large light-water reactors, the plume exposure zone has historically extended about 10 miles, with an ingestion pathway zone of about 50 miles. NRC rules allow smaller and advanced reactors to size the zone based on potential consequences, decided case by case in licensing.
Do small modular reactors need cooling water?
Many do. Reactors based on light-water technology reject substantial heat and often rely on cooling towers or water bodies, which require water rights and permits. Some advanced designs use other coolants or air-cooled heat rejection and may need far less water, but that depends on the specific design and is still being demonstrated for many technologies. Assume significant water need until a design shows otherwise.
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Related guides
More in Power & interconnection
- How Much Power Does a Data Center Need?
- Transmission Voltage and Data Centers: 69 kV to 765 kV
- Substation Proximity and Capacity for Data Center Sites
- How the Large-Load Utility Interconnection Process Works
- ISOs, RTOs and Utility Territories in Data Center Siting
- On-Site Generation and Bridge Power for Data Centers
- What Is Powered Land?
- Load Ramp Schedules: How to Phase Power for a Data Center Campus
- Redundant Utility Feeds and Dual Substations for Data Centers
- Large-Load Tariffs and Electric Service Agreements, Explained
- Behind-the-Meter vs. Front-of-the-Meter Power for Data Centers
- Transmission Upgrades for Data Centers: Who Pays for Them?
- Microgrids and Battery Storage at Data Center Sites
- Renewable Energy Procurement and How It Affects Data Center Siting
