Key takeaways
- Every new U.S. reactor needs NRC approval of both the design and the site, through Part 50, Part 52 or, since 2026, the optional Part 53 framework.3
- Executive Order 14300 (May 2025) directs the NRC to decide new reactor applications within 18 months; the Clinch River permit review took 14 months, helped by an existing early site permit.41
- Reactor sites need an exclusion area, a low population zone and a population center distance of at least 1⅓ times the distance to the low population zone’s outer edge, which keeps reactors away from dense metros.5
- Large reactors plan around a 10-mile plume exposure zone; a rule effective December 2023 lets SMRs and advanced reactors size that zone by potential consequences, in some cases to the site boundary.6
- Nuclear plants with cooling towers typically consume about 600–800 gallons of water per MWh, so plan for water unless a specific design shows otherwise.7
- Tech companies have signed for gigawatts of future nuclear (Meta for up to 6.6 GW in January 2026), but most new reactor capacity is targeted for the 2030s.8
01Why data center developers look at nuclear
Nuclear generation offers large amounts of firm, low-carbon power with very high availability, which suits a data center’s round-the-clock load. Developers look at it in three ways: taking power from an existing plant, locating near a plant site that may add units, or planning a campus around future small modular reactors (SMRs) or other advanced reactors.
The largest buyers are signing for all three. In January 2026 Meta announced agreements that could bring up to 6.6 GW of nuclear capacity online by 2035: 20-year purchase agreements with Vistra for 2,176 MW from the operating Perry and Davis-Besse plants in Ohio plus uprates, rights to up to eight TerraPower Natrium units, and a new Oklo campus in Pike County, Ohio.89 Google and Kairos Power agreed on a fleet of advanced reactors totaling 500 MW by 2035, with the first unit targeted for 2030.10 Amazon invested in X-energy with a goal of more than 5 GW of its SMRs online by 2039, starting with four reactors totaling about 320 MW with Energy Northwest in Washington.11
Fig. 1Meta’s January 2026 nuclear agreements
- potential capacity by 2035
- 6.6 GW
- from operating Vistra plants
- 2,176 MW
- of uprates at Vistra plants
- 433 MW
- TerraPower Natrium units
- Up to 8
Each path has different timing. Power from an existing plant is a contract and grid question, closer to the arrangements in our guide to co-locating data centers with power plants. New reactors are a licensing, construction and supply chain question measured in years, and for first-of-a-kind designs the schedule is hard to predict.
02NRC licensing: what any new reactor goes through
Commercial reactors in the U.S. are licensed by the Nuclear Regulatory Commission (NRC). No reactor can be built or operated without its approval, which covers both the design and the specific site. There are now three main paths:
- A two-step process under 10 CFR Part 50: a construction permit, then an operating license. TVA’s Clinch River Unit 1 is at this stage; TVA must apply for an operating license once construction is complete.1
- A combined construction and operating license under 10 CFR Part 52, which can reference a design the NRC has already certified and an early site permit that resolves site questions before a reactor is chosen.
- An optional, risk-informed and performance-based framework under the new 10 CFR Part 53, affirmed by the Commission on March 25, 2026. It is technology-neutral, giving non-light-water designs a path that does not depend on exemptions from rules written for large water-cooled plants.2
Fig. 2NRC licensing paths for a new reactor
Two-step
Part 50
- Construction permit first
- Separate operating license later
- Path used for Clinch River Unit 1
- Site reviewed with the permit
Combined
Part 52
- One license to build and operate
- Can reference a certified design
- Can reference an early site permit
- More review up front
New, optional
Part 53
- Risk-informed, performance-based
- Technology-neutral
- Built with advanced designs in mind
- Alternative to Parts 50 and 52
Federal policy is pushing for speed. Executive Order 14300, signed May 23, 2025, directs the NRC to decide applications to build and operate a new reactor within 18 months and to finish a wholesale revision of its regulations within 18 months of the order.4 In March 2026, NRC officials said they were on track for the November 2026 rulemaking deadline.12 A license application also triggers environmental review under NEPA, and licensing still involves public participation and an in-depth site review.
03What makes a site suitable for a reactor
NRC reactor site criteria, found mainly in 10 CFR Part 100, look at the site and its surroundings. Every site needs an exclusion area and a surrounding low population zone, sized by analyzing radiation doses at their boundaries after a postulated accident.514 The nearest population center must be at least 1⅓ times as far from the reactor as the outer edge of the low population zone, judged by where people actually live rather than by political boundaries.5 Those criteria exclude a lot of land that would be fine for a data center.
| Factor | What the reactor review looks at | Compared with a data center |
|---|---|---|
| Seismology and geology | Faulting, ground motion and foundation conditions, studied in depth | Far more detailed than a standard geotechnical review |
| Population | Exclusion area, low population zone and population center distance | Data centers often favor proximity to metros; reactors are constrained by it |
| Hydrology and flooding | Flooding from rivers, storms, dam failure and other extreme events | Goes well beyond FEMA floodplain mapping |
| Nearby hazards | Industrial facilities, pipelines, airports and transportation routes | A gas pipeline that helps a data center can complicate a reactor |
| Meteorology | Dispersion, extreme winds and severe weather | Mostly a cooling and hazard issue for data centers |
| Cooling water | Reliable supply for normal and emergency cooling, depending on design | Can be much larger than data center water needs |
Multi-unit campuses have to account for every reactor: under the older Part 100 criteria, for example, these areas are sized for each independent reactor and the combined envelope becomes the boundary.14 TVA plans as many as four SMRs at Clinch River.1 Our guides to slope, soils and geotechnical review and seismic risk cover the ordinary data center side; for a reactor, that work is a starting point at most.
04Emergency planning zones and land use
Licensed reactors have emergency planning zones (EPZs) around them. For large light-water reactors, the plume exposure pathway EPZ has been about 10 miles from the plant, with an ingestion pathway zone of about 50 miles.6 Within these zones, operators, states and local governments maintain emergency plans, warning systems and protective action procedures.
An NRC rule effective December 18, 2023 gives SMRs and other new technologies a performance-based alternative. Instead of a fixed radius, the plume exposure EPZ covers the area where a release could expose the public to more than 10 millisieverts over 96 hours, based on accident likelihood, source term, timing and meteorology. If that area stays inside the site boundary, local responders do not have to take part in radiological drills and exercises.6 The rule also requires a hazard analysis for any facility contiguous to or near the reactor, which matters for a campus planned beside one.15
Whether a design and site qualify for a site-boundary EPZ is decided in licensing, so don’t assume it at site selection.
- A data center inside a reactor’s EPZ is generally possible, but it becomes part of the emergency plan, with implications for staffing, access and evacuation.
- A reactor on the campus brings security perimeters, controlled areas and an exclusion area that shape the campus layout.
- Local land use planning around the reactor may restrict some future development nearby.
05Cooling water, land and transmission
Most operating U.S. reactors are light-water designs that reject large amounts of heat through cooling towers or once-through cooling from a river, lake or ocean, which is why many nuclear plants sit on major water bodies. Once-through systems withdraw far more water than cooling towers, but towers consume more of what they take, mostly through evaporation.7 Withdrawals and discharges need state water rights or permits and Clean Water Act authorizations, and thermal discharges face their own limits.
Fig. 3Nuclear plant water use by cooling type
- Once-through, withdrawal25,000–60,000
- Once-through, consumption100–400
- Cooling towers, withdrawal800–2,600
- Cooling towers, consumption600–800
Some advanced designs use other coolants or air-cooled heat rejection and may need far less water, but that depends on the design and is still being demonstrated for many technologies. Until a specific design says otherwise, assume significant water. Our guides to water rights and groundwater permits and data center water requirements cover the permits and the data center’s own needs, which come on top.
Land and transmission matter too. A reactor site needs room for the plant, its exclusion area, security, construction laydown and switchyards. Even if the data center takes most of the output, a grid connection is normally needed for backup, for reactor startup and for refueling or maintenance outages.
06Lead times and how to plan around them
New nuclear has long lead times: site characterization, licensing, environmental review, supply chain, construction and startup all add up, and advanced designs that need specialized fuel add a fuel supply dependency. First-of-a-kind projects carry more schedule risk than designs with an operating record. Even Clinch River, now holding a construction permit, still has to be built and then licensed to operate.1 The data center deals above reflect this, with delivery targets running from 2030 to 2039.1011
For a data center developer, the practical approach is to treat nuclear as one option in a phased power strategy:
- 01Secure a site with a credible near-term power path from the grid, on-site generation or both; our guide to grid power vs. on-site generation covers the trade-offs.
- 02Check the land against basic reactor siting factors: geology, population distances, flooding, nearby hazards and water.
- 03Hold enough contiguous acreage, and enough distance to neighbors, to keep a future reactor and its exclusion area possible.
- 04Favor sites near existing nuclear plants, or with an early site permit or prior site characterization.
- 05Revisit the nuclear option as licensing progresses and specific designs mature.
When we screen land with nuclear in mind, we keep two questions separate: can this site host a data center on a useful timeline, and does it keep a future reactor on the table? A site that passes only the second test is not yet a data center site. To check a tract against both, get a site reviewed.
Common questions
Can a data center be built next to a nuclear power plant?
Generally, yes. The data center may sit within the plant’s emergency planning zone, which brings it into emergency planning, and it has to work around the exclusion area that every reactor site must have.5 Taking power directly from the plant raises contract, grid and regulatory questions that vary by market, and land near plant sites is often limited by existing corridors and buffers.
How long does it take to build a small modular reactor for a data center?
There is no reliable general answer. The NRC reviewed TVA’s Clinch River construction permit application in 14 months, but construction and an operating license still lie ahead.1 Announced data center deals target first power in 2030 or later.10 That is why most developers treat SMRs as a long-horizon option and plan grid or on-site power for early phases.
What is an emergency planning zone?
It is the area around a licensed reactor where emergency plans and protective actions are prepared in advance. For large light-water reactors, the plume exposure zone has been about 10 miles. Since December 2023, SMRs and advanced reactors can size it by potential consequences, in some cases within the site boundary.6
Do small modular reactors need cooling water?
Many do. Nuclear plants with cooling towers typically consume about 600–800 gallons per MWh.7 Some advanced designs use other coolants or air cooling and may need far less water, but that is design-specific and still being demonstrated.
What is NRC Part 53?
Part 53 is an optional, risk-informed and performance-based licensing framework for commercial reactors that the NRC finalized in March 2026.2 It is technology-neutral, so developers of non-light-water designs can use it instead of seeking exemptions from rules written for large light-water plants. Parts 50 and 52 remain available.
Notes
- 1.World Nuclear News, “First construction permit issued for BWRX-300 SMR in the US,” 2026. world-nuclear-news.org
- 2.American Nuclear Society, “NRC unveils Part 53 final rule,” 2026. ans.org
- 3.Beveridge & Diamond, “NRC Finalizes New Optional Licensing Framework for Advanced Reactors,” 2026. bdlaw.com
- 4.Executive Office of the President (Daily Compilation of Presidential Documents), “Executive Order 14300: Ordering the Reform of the Nuclear Regulatory Commission,” 2025. govinfo.gov
- 5.Federal-Regs.com (Code of Federal Regulations text), “10 CFR 100.21, Non-seismic siting criteria,” 2026. federal-regs.com
- 6.Morgan Lewis, “NRC Provides Emergency Preparedness Flexibility for SMRs and Advanced Reactors,” 2023. morganlewis.com
- 7.Union of Concerned Scientists, “How it Works: Water for Power Plant Cooling,” n.d. ucs.org
- 8.World Nuclear News, “Meta announces ‘landmark’ agreements for new nuclear,” 2026. world-nuclear-news.org
- 9.Vistra, “Vistra and Meta Announce Agreements to Support Nuclear Plants in PJM and Add New Nuclear Generation to the Grid,” 2026. investor.vistracorp.com
- 10.Kairos Power, “Google and Kairos Power Partner to Deploy 500 MW of Clean Electricity Generation,” 2024. kairospower.com
- 11.World Nuclear News, “Amazon invests in X-energy, unveils SMR project plans,” 2024. world-nuclear-news.org
- 12.American Nuclear Society, “NRC provides timeline update on rules, meeting EO deadline,” 2026. ans.org
- 13.GE Vernova, “NRC issues first US construction permit for BWRX-300 small modular reactor at TVA Clinch River,” 2026. gevernova.com
- 14.Legal Information Institute, Cornell Law School, “10 CFR § 100.11, Determination of exclusion area, low population zone, and population center distance,” n.d. law.cornell.edu
- 15.U.S. Nuclear Regulatory Commission, “Emergency Preparedness (advanced reactor rulemaking),” n.d. ww2.nrc.gov
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Power & interconnection
- How Much Power Does a Data Center Need?
- Transmission Voltage and Data Centers: 69 kV to 765 kV
- Substation Proximity and Capacity for Data Center Sites
- How the Large-Load Utility Interconnection Process Works
- ISOs, RTOs and Utility Territories in Data Center Siting
- On-Site Generation and Bridge Power for Data Centers
- What Is Powered Land?
- Load Ramp Schedules: How to Phase Power for a Data Center Campus
- Redundant Utility Feeds and Dual Substations for Data Centers
- Large-Load Tariffs and Electric Service Agreements, Explained
- Behind-the-Meter vs. Front-of-the-Meter Power for Data Centers
- Transmission Upgrades for Data Centers: Who Pays for Them?
- Microgrids and Battery Storage at Data Center Sites
- Renewable Energy Procurement and How It Affects Data Center Siting
- What Is a Utility Load Study for a Data Center?
- Firm vs. Interruptible Electric Service for Data Centers
- Flexible Data Center Loads and Demand Response
- Texas Senate Bill 6: What It Means for Data Centers and Large Loads
- PJM Capacity Prices and Data Center Load Growth
- Contribution in Aid of Construction (CIAC) and Line Extensions for Data Centers
- Transformer and Switchgear Lead Times for Data Centers
- Substation Configurations for Data Center Campuses: Ring Bus, Breaker-and-a-Half and Double Bus
- Electricity Rates and Power Costs for Data Center Sites
- Power Purchase Agreements for Data Centers: Physical, Virtual and Sleeved
- 24/7 Carbon-Free Energy and Hourly Matching for Data Centers
- Gas Turbines vs. Reciprocating Engines for Data Center On-Site Power
- Fuel Cells for Data Center Power: How They Work and Where They Fit
- NERC Reliability Standards and Large Data Center Loads: Ride-Through, Load Loss and Registration
- From Signed Agreement to Energization: The Data Center Power Timeline
- Hydropower and Data Center Siting: Public Power, Allocations and Drought Risk
- Geothermal Power for Data Centers: Enhanced Geothermal, Clean Tariffs and Siting in the West
- Surplus Interconnection Service and Retired Power Plant Sites: How Existing Grid Rights Get Reused
Guide 16 of 35 in Power & interconnection · all 242 guides · glossary · calculators
