Key takeaways
- The RTO-wide clearing price went from $28.92 to $269.92 per MW-day in one auction, then hit the cap three times in a row.61
- The 2028/2029 auction cleared at the $325 cap and would have cleared near $555 without it.1
- The collar runs through the 2029/2030 auction; after that, pricing depends on rules not yet written.4
- PJM forecasts summer peak near 222,000 MW by 2036, though stricter vetting of large loads trimmed the near-term outlook.7
- A data center’s capacity bill follows its load during five summer peak hours, so the operating profile matters.8
- PJM’s reliability backstop for new capacity was suspended by FERC in September 2026 pending fixes to cost allocation.910
01What PJM’s capacity market does
PJM runs a forward capacity market, the Reliability Pricing Model, that pays generators, storage and demand response to be available during peak conditions. The main event is the Base Residual Auction (BRA), which procures capacity for a delivery year that runs from June through May. The auction sets a clearing price in dollars per MW-day, and load-serving entities pass those costs to customers.1
Capacity is separate from energy. A data center pays for energy on every megawatt-hour it uses, and separately pays a capacity charge based on its share of the system peak. For a large, flat load running near full output during summer peaks, capacity can be a material share of the delivered power cost. Our guide to electricity rates for data centers covers the other bill components, and PJM data center site selection covers the regional market structure.
The auction is also a resource adequacy signal. When it clears short of the reliability requirement, that tells utilities and regulators the region does not have enough committed supply for forecast peak load, which shapes how quickly they are willing to connect new large loads.
02Auction results, 2024/2025 to 2028/2029
The 2025/2026 auction, held in 2024, cleared at a record $269.92 per MW-day across most of the footprint, up from $28.92 the year before.6 Two zones with large data center concentrations cleared higher still: Baltimore Gas and Electric at $466.35 and Dominion at $444.26, reflecting limited supply inside those zones and transmission limits on imports.6
Fig. 1PJM RTO capacity clearing price by delivery year
- 2024/2025$28.92
- 2025/2026$269.92
- 2026/2027 (cap)$329.17
- 2027/2028 (cap)$333.44
- 2028/2029 (cap)$325.00
$ per MW-day
The next three auctions all hit the cap: $329.17 for 2026/2027 and $333.44 for 2027/2028.2 The 2027/2028 auction fell 6,623 MW short of the reliability requirement, the first time the RTO as a whole came up short, and PJM said peak load for that year was forecast about 5,250 MW higher than in the forecast used for the 2026/2027 auction, with nearly 5,100 MW of the increase from data centers.11
The 2028/2029 auction, announced July 14, 2026, cleared at the $325 cap across the entire footprint. It procured 138,318 MW of generation and demand response, plus 10,864 MW under Fixed Resource Requirement plans, for 149,182 MW in total, and still fell 6,831 MW short. Total procurement cost was $16.4 billion, and PJM estimated the uncapped price at $554.72 per MW-day.112
Fig. 22028/2029 Base Residual Auction
- Clearing price, at the cap
- $325/MW-day
- Estimated price without the collar
- $554.72
- Shortfall vs. reliability requirement
- 6,831 MW
- Total procurement cost
- $16.4 billion
03The price cap and floor, and when they end
The cap is not a market outcome. After the 2025/2026 price spike, PJM filed in February 2025 to lower the cap from roughly $500 to about $325 per MW-day, with a floor near $175, for the 2026/2027 and 2027/2028 auctions.4 PJM proposed an extension in February 2026, and FERC accepted it in April 2026 for the 2028/2029 auction and the 2029/2030 auction that closes on December 15, 2026, with a cap near $325 and a floor near $175 per MW-day, both adjusted annually for the accreditation of PJM’s reference resource.4
For a site underwriting a 15- or 20-year load, that leaves a gap. The collar covers delivery through May 2030. After that, absent another extension or market redesign, PJM’s uncapped estimate of $554.72 per MW-day for 2028/2029 is a reasonable stress case for what tight supply could produce, though new generation, demand response or rule changes could pull prices down.1 Treat capacity cost beyond 2030 as a range, not a number.
05PJM’s response: large-load rules and the backstop procurement
In January 2026, after the Critical Issue Fast Path process on large loads, the PJM Board issued a decision covering load forecasting, bring-your-own new generation arrangements, expedited interconnection for new supply, and a reliability backstop procurement. It defined large load additions as 50 MW or more at a single point of interconnection.5
The Board has also sought FERC approval for curtailing new data center loads that do not bring their own capacity during capacity shortages.14 For siting, that means a project’s power position in PJM increasingly depends on whether it brings or contracts for new supply, accepts some interruptibility, or does neither. Our guides to flexible data center loads and on-site generation and bridge power cover the first two paths.
The backstop procurement was meant to fill the roughly 6.8 GW shortfall from the 2028/2029 auction.10 On September 29, 2026, FERC accepted parts of PJM’s filing but found deficiencies in cost allocation, transmission-owner exit rules and collateral requirements, suspended those provisions through February 28, 2027, and set a paper hearing.9 PJM delayed the auction, which had been set to begin September 30, and had not set a new timeline as of early October 2026.10
06What capacity prices mean for a data center’s costs
A customer’s capacity obligation in PJM is its peak load contribution: its average load during the five highest summer system peak hours, which must fall on separate days between June and September. That figure, adjusted by zonal and system scaling factors, sets the customer’s capacity obligation for the following delivery year, and the utility or supplier bills it against the zonal capacity rate.8 A data center running near full load in July and August will carry close to its full demand as its contribution.
Fig. 3How a capacity price reaches a data center bill
- 01
Base Residual Auction
Sets $/MW-day for the delivery year.
- 02
Zonal rate
Utility applies zone and system scaling factors.
- 03
Five summer peaks
Customer load measured in the 5CP hours.
- 04
Peak load contribution
Average of those five hours, in MW.
- 05
Capacity charge
Contribution × rate over the delivery year.
| Price ($/MW-day) | Per MW-year | 100 MW per year |
|---|---|---|
| $28.92 (2024/2025)6 | about $10,600 | about $1.1 million |
| $325 (2028/2029 cap)1 | about $118,600 | about $11.9 million |
| $554.72 (2028/2029 uncapped)1 | about $202,500 | about $20.2 million |
Two site-level consequences follow. First, zones matter: constrained zones such as BGE and Dominion have cleared well above the RTO price when import limits bind, so a parcel’s transmission zone belongs in the screen.6 See Northern Virginia and Maryland. Second, the ability to reduce load in the five peak hours, through on-site generation, storage or workload shifting, has direct value under the current tariff.8
The table leaves out zonal scaling factors, which move the effective rate up or down, and any hedge in a retail supply contract. PJM notes that load hedged through self-supply or bilateral contracts is not directly exposed to auction clearing prices, so the contract structure decides how much of a price swing reaches the operator.1
07What to check for a PJM site
- 01Identify the transmission zone and its recent zonal clearing prices, not just the RTO price.6
- 02Check whether the serving utility procures capacity through a Fixed Resource Requirement plan instead of the auction.1
- 03Model capacity cost at the cap through May 2030 and at uncapped levels after that.41
- 04Ask the utility how its large-load tariff handles capacity, collateral and minimum bills, and whether new loads must bring supply.5
- 05Track the backstop procurement and how your state assigns its costs to new large loads.910
- 06Estimate your peak load contribution and what it would take to reduce load in the five summer peak hours.8
- 07Compare against other markets with different structures, such as ERCOT under Texas Senate Bill 6.
Confirm current terms with the utility, your retail supplier and regulatory counsel before relying on any capacity forecast. If you want an independent view of a PJM parcel’s power position, you can get a site reviewed.
Common questions
What is the PJM capacity price for 2028/2029?
The 2028/2029 Base Residual Auction cleared at $325 per MW-day across the whole PJM footprint, which is the cap under the FERC-approved price collar.1 PJM estimated the price would have been $554.72 without the cap.1
Why did PJM capacity prices go up so much?
Tighter supply, higher forecast demand and market rule changes pushed the 2025/2026 price to $269.92 from $28.92.6 Since then, load forecasts driven largely by data centers have kept the auction short of its reliability target.131
Do data centers pay PJM capacity costs?
Yes, through their utility or retail supplier, based on their peak load contribution during five summer peak hours.8 The market monitor argues data center growth also raises the price that every other customer pays.3
When does the PJM capacity price cap expire?
The collar FERC accepted in April 2026 covers the 2028/2029 and 2029/2030 auctions, which means delivery through May 2030.4 Rules for later auctions were not settled as of October 2026.
Notes
- 1.PJM Interconnection, “PJM Capacity Auction Procures 138,318 MW of Generation Resources,” 2026. pjm.com
- 2.PJM Interconnection, “Review of 2027/2028 Base Residual Auction Results (Markets and Reliability Committee presentation),” 2025. pjm.com
- 3.Utility Dive, “Data centers drove $6.3B in PJM capacity auction costs: market monitor,” 2026. utilitydive.com
- 4.PJM Inside Lines, “FERC Approves Capacity Auction Price Collar to Next Two Capacity Auctions,” 2026. insidelines.pjm.com
- 5.PJM Interconnection, “PJM Board Letter re Results of the CIFP Process: Large Load Additions,” 2026. pjm.com
- 6.S&P Global Market Intelligence, “PJM capacity auction clears at record price of $269.92/MW-day across footprint,” 2024. spglobal.com
- 7.PJM Interconnection, “PJM 2026 Long-Term Load Forecast (Load Analysis Subcommittee presentation),” 2026. pjm.com
- 8.PJM Interconnection, “PLC and NSPL Education (Markets and Reliability Committee presentation),” 2013. ftp.pjm.com
- 9.Federal Energy Regulatory Commission, “Order on PJM reliability backstop procurement, Docket No. ER26-3380-000,” 2026. pjm.com
- 10.Utility Dive, “PJM delays backstop procurement,” 2026. utilitydive.com
- 11.PJM Interconnection, “PJM Auction Procures 134,479 MW of Generation Resources,” 2025. pjm.com
- 12.PJM Interconnection, “2028/2029 Base Residual Auction Results Report,” 2026. pjm.com
- 13.Utility Dive, “Data centers were 40% of PJM capacity costs in last auction: market monitor,” 2025. utilitydive.com
- 14.T&D World, “PJM Board Seeks FERC Approval on Data Center Curtailments Amid Grid Capacity Concerns,” 2026. tdworld.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Related guides
More in Power & interconnection
- How Much Power Does a Data Center Need?
- Transmission Voltage and Data Centers: 69 kV to 765 kV
- Substation Proximity and Capacity for Data Center Sites
- How the Large-Load Utility Interconnection Process Works
- Power Timelines: Why “When” Matters as Much as “Where”
- ISOs, RTOs and Utility Territories in Data Center Siting
- On-Site Generation and Bridge Power for Data Centers
- What Is Powered Land?
- Load Ramp Schedules: How to Phase Power for a Data Center Campus
- Redundant Utility Feeds and Dual Substations for Data Centers
- Behind-the-Meter vs. Front-of-the-Meter Power for Data Centers
- Transmission Upgrades for Data Centers: Who Pays for Them?
- Microgrids and Battery Storage at Data Center Sites
- Co-Locating Data Centers With Power Plants
- Nuclear and Small Modular Reactors: Siting Considerations for Data Centers
- Renewable Energy Procurement and How It Affects Data Center Siting
- What Is a Utility Load Study for a Data Center?
- Firm vs. Interruptible Electric Service for Data Centers
- Texas Senate Bill 6: What It Means for Data Centers and Large Loads
- Contribution in Aid of Construction (CIAC) and Line Extensions for Data Centers
- Transformer and Switchgear Lead Times for Data Centers
- Substation Configurations for Data Center Campuses: Ring Bus, Breaker-and-a-Half and Double Bus
- Power Purchase Agreements for Data Centers: Physical, Virtual and Sleeved
- 24/7 Carbon-Free Energy and Hourly Matching for Data Centers
- Gas Turbines vs. Reciprocating Engines for Data Center On-Site Power
- Fuel Cells for Data Center Power: How They Work and Where They Fit
- NERC Reliability Standards and Large Data Center Loads: Ride-Through, Load Loss and Registration
- From Signed Agreement to Energization: The Data Center Power Timeline
- Hydropower and Data Center Siting: Public Power, Allocations and Drought Risk
- Geothermal Power for Data Centers: Enhanced Geothermal, Clean Tariffs and Siting in the West
- Surplus Interconnection Service and Retired Power Plant Sites: How Existing Grid Rights Get Reused
