BlackForge Data Centers

Power & interconnection

PJM Capacity Prices and Data Center Load Growth

PJM capacity prices rose from $28.92 per MW-day for 2024/2025 to the regulated cap in each of the last three auctions, most recently $325 per MW-day for 2028/2029, with supply still about 6.8 GW short of the reliability requirement.12 The independent market monitor attributes a large share of that increase to existing and forecast data center load.3 For a site, the result is a capacity charge of roughly $119,000 per MW-year at the cap, a policy push to make new large loads bring or pay for their own supply, and real uncertainty once the price collar ends.45

Last reviewed · 8 min read · BlackForge Data Centers

Key takeaways

  • The RTO-wide clearing price went from $28.92 to $269.92 per MW-day in one auction, then hit the cap three times in a row.61
  • The 2028/2029 auction cleared at the $325 cap and would have cleared near $555 without it.1
  • The collar runs through the 2029/2030 auction; after that, pricing depends on rules not yet written.4
  • PJM forecasts summer peak near 222,000 MW by 2036, though stricter vetting of large loads trimmed the near-term outlook.7
  • A data center’s capacity bill follows its load during five summer peak hours, so the operating profile matters.8
  • PJM’s reliability backstop for new capacity was suspended by FERC in September 2026 pending fixes to cost allocation.910

01What PJM’s capacity market does

PJM runs a forward capacity market, the Reliability Pricing Model, that pays generators, storage and demand response to be available during peak conditions. The main event is the Base Residual Auction (BRA), which procures capacity for a delivery year that runs from June through May. The auction sets a clearing price in dollars per MW-day, and load-serving entities pass those costs to customers.1

Capacity is separate from energy. A data center pays for energy on every megawatt-hour it uses, and separately pays a capacity charge based on its share of the system peak. For a large, flat load running near full output during summer peaks, capacity can be a material share of the delivered power cost. Our guide to electricity rates for data centers covers the other bill components, and PJM data center site selection covers the regional market structure.

The auction is also a resource adequacy signal. When it clears short of the reliability requirement, that tells utilities and regulators the region does not have enough committed supply for forecast peak load, which shapes how quickly they are willing to connect new large loads.

02Auction results, 2024/2025 to 2028/2029

The 2025/2026 auction, held in 2024, cleared at a record $269.92 per MW-day across most of the footprint, up from $28.92 the year before.6 Two zones with large data center concentrations cleared higher still: Baltimore Gas and Electric at $466.35 and Dominion at $444.26, reflecting limited supply inside those zones and transmission limits on imports.6

Fig. 1PJM RTO capacity clearing price by delivery year

  • 2024/2025$28.92
  • 2025/2026$269.92
  • 2026/2027 (cap)$329.17
  • 2027/2028 (cap)$333.44
  • 2028/2029 (cap)$325.00

$ per MW-day

Base Residual Auction RTO prices.62 The last three cleared at the cap set by the price collar.1

The next three auctions all hit the cap: $329.17 for 2026/2027 and $333.44 for 2027/2028.2 The 2027/2028 auction fell 6,623 MW short of the reliability requirement, the first time the RTO as a whole came up short, and PJM said peak load for that year was forecast about 5,250 MW higher than in the forecast used for the 2026/2027 auction, with nearly 5,100 MW of the increase from data centers.11

The 2028/2029 auction, announced July 14, 2026, cleared at the $325 cap across the entire footprint. It procured 138,318 MW of generation and demand response, plus 10,864 MW under Fixed Resource Requirement plans, for 149,182 MW in total, and still fell 6,831 MW short. Total procurement cost was $16.4 billion, and PJM estimated the uncapped price at $554.72 per MW-day.112

Fig. 22028/2029 Base Residual Auction

Clearing price, at the cap
$325/MW-day
Estimated price without the collar
$554.72
Shortfall vs. reliability requirement
6,831 MW
Total procurement cost
$16.4 billion
Results for the delivery year starting June 2028, from PJM’s July 2026 release and results report.112

03The price cap and floor, and when they end

The cap is not a market outcome. After the 2025/2026 price spike, PJM filed in February 2025 to lower the cap from roughly $500 to about $325 per MW-day, with a floor near $175, for the 2026/2027 and 2027/2028 auctions.4 PJM proposed an extension in February 2026, and FERC accepted it in April 2026 for the 2028/2029 auction and the 2029/2030 auction that closes on December 15, 2026, with a cap near $325 and a floor near $175 per MW-day, both adjusted annually for the accreditation of PJM’s reference resource.4

For a site underwriting a 15- or 20-year load, that leaves a gap. The collar covers delivery through May 2030. After that, absent another extension or market redesign, PJM’s uncapped estimate of $554.72 per MW-day for 2028/2029 is a reasonable stress case for what tight supply could produce, though new generation, demand response or rule changes could pull prices down.1 Treat capacity cost beyond 2030 as a range, not a number.

04How much of the increase comes from data centers

PJM’s independent market monitor, Monitoring Analytics, has repeatedly tied the price increases to data center load. It attributed $6.5 billion, or 40%, of the $16.4 billion 2027/2028 cost to data center load.13 For 2028/2029, its president attributed about $6.3 billion, or 38%, of $16.4 billion in charges to data centers.3 Across the last four base auctions, he put data-center-driven capacity charges at $29.4 billion, about 46% of the $63.6 billion total.3 The monitor had not yet published the analysis behind those figures when they were reported.3

The load forecast is the hinge. PJM’s 2026 long-term forecast projects summer peak of about 222,000 MW in 2036, a 10-year increase of nearly 66,000 MW, or 3.6% per year.7 It lowered near-term peaks through 2032 partly because of stricter vetting of requested large-load adjustments.7 Because the BRA buys capacity against forecast load, speculative data center requests that never get built still raise prices for everyone, which is why utilities now ask for more commitment up front. See large-load tariffs and service agreements.

05PJM’s response: large-load rules and the backstop procurement

In January 2026, after the Critical Issue Fast Path process on large loads, the PJM Board issued a decision covering load forecasting, bring-your-own new generation arrangements, expedited interconnection for new supply, and a reliability backstop procurement. It defined large load additions as 50 MW or more at a single point of interconnection.5

The Board has also sought FERC approval for curtailing new data center loads that do not bring their own capacity during capacity shortages.14 For siting, that means a project’s power position in PJM increasingly depends on whether it brings or contracts for new supply, accepts some interruptibility, or does neither. Our guides to flexible data center loads and on-site generation and bridge power cover the first two paths.

The backstop procurement was meant to fill the roughly 6.8 GW shortfall from the 2028/2029 auction.10 On September 29, 2026, FERC accepted parts of PJM’s filing but found deficiencies in cost allocation, transmission-owner exit rules and collateral requirements, suspended those provisions through February 28, 2027, and set a paper hearing.9 PJM delayed the auction, which had been set to begin September 30, and had not set a new timeline as of early October 2026.10

06What capacity prices mean for a data center’s costs

A customer’s capacity obligation in PJM is its peak load contribution: its average load during the five highest summer system peak hours, which must fall on separate days between June and September. That figure, adjusted by zonal and system scaling factors, sets the customer’s capacity obligation for the following delivery year, and the utility or supplier bills it against the zonal capacity rate.8 A data center running near full load in July and August will carry close to its full demand as its contribution.

Fig. 3How a capacity price reaches a data center bill

  1. 01

    Base Residual Auction

    Sets $/MW-day for the delivery year.

  2. 02

    Zonal rate

    Utility applies zone and system scaling factors.

  3. 03

    Five summer peaks

    Customer load measured in the 5CP hours.

  4. 04

    Peak load contribution

    Average of those five hours, in MW.

  5. 05

    Capacity charge

    Contribution × rate over the delivery year.

Simplified; scaling factors and retail pass-through differ by utility zone and supply contract.8
Illustrative annual capacity cost for a 100 MW peak load contribution (no scaling factors)
Price ($/MW-day)Per MW-year100 MW per year
$28.92 (2024/2025)6about $10,600about $1.1 million
$325 (2028/2029 cap)1about $118,600about $11.9 million
$554.72 (2028/2029 uncapped)1about $202,500about $20.2 million

Two site-level consequences follow. First, zones matter: constrained zones such as BGE and Dominion have cleared well above the RTO price when import limits bind, so a parcel’s transmission zone belongs in the screen.6 See Northern Virginia and Maryland. Second, the ability to reduce load in the five peak hours, through on-site generation, storage or workload shifting, has direct value under the current tariff.8

The table leaves out zonal scaling factors, which move the effective rate up or down, and any hedge in a retail supply contract. PJM notes that load hedged through self-supply or bilateral contracts is not directly exposed to auction clearing prices, so the contract structure decides how much of a price swing reaches the operator.1

07What to check for a PJM site

  1. 01Identify the transmission zone and its recent zonal clearing prices, not just the RTO price.6
  2. 02Check whether the serving utility procures capacity through a Fixed Resource Requirement plan instead of the auction.1
  3. 03Model capacity cost at the cap through May 2030 and at uncapped levels after that.41
  4. 04Ask the utility how its large-load tariff handles capacity, collateral and minimum bills, and whether new loads must bring supply.5
  5. 05Track the backstop procurement and how your state assigns its costs to new large loads.910
  6. 06Estimate your peak load contribution and what it would take to reduce load in the five summer peak hours.8
  7. 07Compare against other markets with different structures, such as ERCOT under Texas Senate Bill 6.

Confirm current terms with the utility, your retail supplier and regulatory counsel before relying on any capacity forecast. If you want an independent view of a PJM parcel’s power position, you can get a site reviewed.

Common questions

What is the PJM capacity price for 2028/2029?

The 2028/2029 Base Residual Auction cleared at $325 per MW-day across the whole PJM footprint, which is the cap under the FERC-approved price collar.1 PJM estimated the price would have been $554.72 without the cap.1

Why did PJM capacity prices go up so much?

Tighter supply, higher forecast demand and market rule changes pushed the 2025/2026 price to $269.92 from $28.92.6 Since then, load forecasts driven largely by data centers have kept the auction short of its reliability target.131

Do data centers pay PJM capacity costs?

Yes, through their utility or retail supplier, based on their peak load contribution during five summer peak hours.8 The market monitor argues data center growth also raises the price that every other customer pays.3

When does the PJM capacity price cap expire?

The collar FERC accepted in April 2026 covers the 2028/2029 and 2029/2030 auctions, which means delivery through May 2030.4 Rules for later auctions were not settled as of October 2026.

What is PJM’s reliability backstop auction?

It is a one-time procurement meant to add new capacity to cover the shortfall in the 2028/2029 auction.10 FERC suspended key provisions in September 2026 over cost allocation and collateral concerns, and PJM delayed the auction.910

Notes

  1. 1.PJM Interconnection, “PJM Capacity Auction Procures 138,318 MW of Generation Resources,” 2026. pjm.com
  2. 2.PJM Interconnection, “Review of 2027/2028 Base Residual Auction Results (Markets and Reliability Committee presentation),” 2025. pjm.com
  3. 3.Utility Dive, “Data centers drove $6.3B in PJM capacity auction costs: market monitor,” 2026. utilitydive.com
  4. 4.PJM Inside Lines, “FERC Approves Capacity Auction Price Collar to Next Two Capacity Auctions,” 2026. insidelines.pjm.com
  5. 5.PJM Interconnection, “PJM Board Letter re Results of the CIFP Process: Large Load Additions,” 2026. pjm.com
  6. 6.S&P Global Market Intelligence, “PJM capacity auction clears at record price of $269.92/MW-day across footprint,” 2024. spglobal.com
  7. 7.PJM Interconnection, “PJM 2026 Long-Term Load Forecast (Load Analysis Subcommittee presentation),” 2026. pjm.com
  8. 8.PJM Interconnection, “PLC and NSPL Education (Markets and Reliability Committee presentation),” 2013. ftp.pjm.com
  9. 9.Federal Energy Regulatory Commission, “Order on PJM reliability backstop procurement, Docket No. ER26-3380-000,” 2026. pjm.com
  10. 10.Utility Dive, “PJM delays backstop procurement,” 2026. utilitydive.com
  11. 11.PJM Interconnection, “PJM Auction Procures 134,479 MW of Generation Resources,” 2025. pjm.com
  12. 12.PJM Interconnection, “2028/2029 Base Residual Auction Results Report,” 2026. pjm.com
  13. 13.Utility Dive, “Data centers were 40% of PJM capacity costs in last auction: market monitor,” 2025. utilitydive.com
  14. 14.T&D World, “PJM Board Seeks FERC Approval on Data Center Curtailments Amid Grid Capacity Concerns,” 2026. tdworld.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Related guides

More in Power & interconnection