A BlackForge Ventures company
BlackForge Data Centers

Grid regions

Data Center Site Selection in PJM

PJM runs the grid and wholesale market for more than 67 million people in 13 states and the District of Columbia, and it holds some of the largest data center markets in the country, so power availability and capacity cost, not demand, are usually the deciding factors there.1 Its 2028/2029 capacity auction cleared at the price cap and still fell 6,831 MW short of the reliability requirement, and PJM spent 2026 writing new rules for how large loads connect.23 A site selector in PJM should check the specific transmission zone, the local utility’s large-load process, state retail rules and local land-use attitudes, because all four vary widely across the footprint.

Last reviewed · 9 min read · BlackForge Data Centers

Key takeaways

  • PJM covers all or parts of 13 states and D.C., from the Mid-Atlantic coast into the Midwest, with about 88,000 miles of transmission.14
  • Capacity is expensive and short: the 2028/2029 auction cleared at the $325/MW-day cap, and the market monitor attributed about $6.3 billion of its $16.4 billion value to data center load.25
  • PJM forecasts summer peak load rising about 66,000 MW over ten years, driven mainly by data centers, with growth very uneven by zone.67
  • New large loads face new terms: PJM’s Board has backed a bring-your-own-generation path, a “connect and manage” option with curtailment, and a reliability backstop procurement.89
  • State retail rules differ: some PJM states allow retail choice, others keep vertically integrated utilities.
Public data · Power trackerLarge-load power tracker39 utilities and their data center power rules, from public filings.

01The PJM footprint and how it is organized

PJM operates the transmission grid and wholesale electricity market for all or parts of Delaware, Illinois, Indiana, Kentucky, Maryland, Michigan, New Jersey, North Carolina, Ohio, Pennsylvania, Tennessee, Virginia and West Virginia, plus the District of Columbia, serving more than 67 million people.1 PJM listed 88,417 miles of bulk transmission lines at the end of 2025.4 It is part of the Eastern Interconnection and is regulated by FERC.

PJM does not own transmission lines or serve retail customers. Its footprint is divided into transmission zones, each tied to one or more transmission owners. Within those zones, retail service comes from investor-owned utilities, cooperatives and municipal utilities. For a data center, the identity of the local transmission owner and retail provider matters as much as the fact that the site is “in PJM.” Our guide to ISO and RTO markets explains these roles; the state guides for Virginia, Ohio and Pennsylvania go deeper.

Fig. 1Who decides what for a large load in PJM

  1. 01FERCApproves PJM’s tariff, market rules and transmission service terms
  2. 02PJMWholesale markets, load forecast and regional transmission planning
  3. 03Transmission ownerStudies the request and builds local lines and substations
  4. 04State commission and utilityRetail tariffs, large-load contracts and collateral
  5. 05Data centerApplies for service, commits to load ramp and pays its share
Simplified. PJM can plan and price, but it relies on the load-serving entity for any curtailment of a specific retail customer.8

02Market structure and retail service

PJM’s states took different paths on electricity restructuring. Some allow retail choice, where customers buy energy from competitive suppliers while the local utility delivers it. Others keep vertically integrated utilities that own generation and sell bundled service under state-regulated rates. A few have mixed arrangements by utility type. Our comparison of regulated utility vs. competitive market sites explains the difference.

How service tends to work for a large load in PJM
ElementWho usually handles itWhat it means for a site
Wholesale market and dispatchPJMEnergy and capacity prices are set regionally, with zonal differences
Regional transmission planningPJM with transmission ownersLarge loads enter the load forecast and can drive upgrades
Customer connection and substationLocal transmission owner or utilityStudy scope, cost responsibility and timeline vary by owner
Retail service termsUtility under state regulationLarge-load tariffs, contracts and collateral vary by state and utility
Energy supplyCompetitive supplier or utility, depending on stateProcurement options depend on the state’s retail rules

03Resource adequacy and capacity prices

PJM runs a centralized forward capacity market. Generators and other resources commit to be available years ahead, and load-serving entities pay for that capacity. States, meanwhile, set their own policies on generation mix, retirements and procurement. Together these decide whether the region has enough supply for its peak.

The margin has tightened sharply. In the 2028/2029 Base Residual Auction, held in July 2026, PJM procured 138,318 MW at the FERC-approved price cap of $325 per MW-day, and was still 6,831 MW short of the reliability requirement even after counting Fixed Resource Requirement capacity.2 PJM noted that the $16.4 billion auction value is not the same as the cost to load, because some load is hedged through self-supply or bilateral contracts.2 PJM’s independent market monitor estimated that data centers accounted for about $6.3 billion, or 38%, of that value, and about $29.4 billion across the last four base auctions.5

Fig. 2PJM’s 2028/2029 capacity auction

clearing price, at the cap
$325/MW-day
capacity and demand response procured
138,318 MW
short of the reliability requirement
6,831 MW
of $16.4B attributed to data centers
~$6.3B
Results released July 2026; the data center share is the market monitor’s estimate, not PJM’s.25

For a data center, this has two effects. First, capacity costs flow into the price of power, and large, steady loads pay them on every megawatt of peak demand. Second, a short supply margin makes utilities and PJM more cautious about how fast new large loads connect, and more interested in loads that bring their own supply or accept curtailment. Neither is a reason to avoid PJM, but both belong in the site comparison. Our guide to PJM capacity prices and data centers goes deeper.

04How much load PJM expects

PJM’s 2026 long-term load forecast projects summer peak demand of about 222,000 MW in 2036, nearly 66,000 MW above current levels, and more than 253,000 MW by 2046.6 Over 15 years, the forecast rises about 85,000 MW, to more than 241,000 MW; the system’s record summer peak, set in 2006, is 166,929 MW.10

The near-term numbers came down slightly from the 2025 forecast. PJM attributed that partly to tighter vetting of large-load requests, counting projects with firm commitments and screening out duplicate requests from developers shopping several sites,7 and partly to updated economic and electric vehicle assumptions.6 Growth is also very uneven. Ten-year growth rates by zone ranged from 0.2% to 6.4% a year, with a median of 1.6%.7 For a site selector, that spread is the point.

Fig. 3PJM summer peak: record vs. 2026 forecast

  • Record peak (2006)166,929 MW
  • Forecast, 2036~222,000 MW
  • Forecast, 15 years out~241,000 MW
  • Forecast, 2046~253,000 MW

MW

Record peak and forecast summer peaks from PJM’s 2026 long-term load forecast; forecasts are revised every year.610

05How large-load interconnection works in PJM

Loads do not go through PJM’s generator interconnection queue. A data center applies to its local utility or transmission owner, which studies the request against its own system and coordinates with PJM on regional effects. Large loads are reflected in PJM’s load forecast, and the regional transmission planning process can identify upgrades needed to serve them. See the large-load interconnection process.

  • The transmission owner sets the study steps, deposits and timelines for its zone, so two sites in neighboring zones can face very different processes. Dominion Energy, for example, reports about 70 GW of large-load requests in its Virginia queue, with about 25 GW assigned dates through 2031.11
  • Upgrades may be local, such as a new substation or line tap, or regional; cost responsibility depends on the upgrade type and applicable tariffs. See transmission upgrades and cost allocation.
  • Utilities increasingly ask for firm ramp schedules and financial commitments before committing capacity.

New rules for large loads in 2026

After a fast-tracked stakeholder process failed to reach consensus on any of 12 proposals, PJM’s Board issued its own package in January 2026 and described some measures as interim, until supply and reserve margins recover.3 PJM’s January 2026 filing at FERC listed a voluntary bring-your-own-new-generation path with an expedited interconnection track, a reliability backstop procurement, and a “connect and manage” option under which new large loads that do not bring generation could be curtailed before pre-emergency demand response.8

In July 2026 the Board went further. It projected new large-load demand rising about 70 GW by 2038, noted about 15 GW of generation retirements since 2022, concluded that a voluntary framework would not close the near-term shortfall, and directed filings for a reliability backstop procurement and for large-load curtailment.9 Ohio’s commission has urged FERC to keep new obligations focused on data centers rather than manufacturers and other large customers.12 These filings were still pending at FERC as of this review; confirm current rules with the utility and PJM.

Co-location rules are changing too. In December 2025, FERC found PJM’s tariff lacked clear terms for co-located load and directed new transmission service options, including an interim, non-firm network service subject to curtailment and firm and non-firm contract demand services.13 See co-locating data centers with power plants.

06Typical constraints across the footprint

Constraints differ from zone to zone, but several themes recur.

  • Transmission congestion. Zones with established data center clusters can face long timelines and large upgrades for new requests.
  • Generation retirements. PJM’s Board cited about 15 GW of retirements since 2022.9 Where older plants retire, local transmission may need reinforcement, which can delay new large loads nearby or, in some cases, free up a connection point. See surplus interconnection and retired plant sites.
  • Terrain and geology. Parts of the Appalachian region have steep slopes and karst, which affect grading and foundations.
  • Mineral rights. Much of the footprint overlies coal, oil and gas resources, so severed mineral estates are common. See mineral rights and easements.
  • Flood and storm exposure. River valleys and coastal areas need site-by-site checks.
  • Local restrictions. Loudoun County, Virginia, ended by-right approval of data centers in March 2025, so new projects there need a special exception with public hearings.14 Maryland and Ohio were among the states with the most active opposition groups in early 2026.15

07Land, water, fiber and climate

Fiber is a strength in much of PJM. The Mid-Atlantic hosts some of the densest data center fiber in the country, and long-haul routes cross the footprint along interstate corridors. Outlying zones can still be thin on diverse routes, so fiber should be checked for each site.

Water is generally more available than in the arid West, but local supply, treatment capacity and discharge permits still vary. Summers in the southern and coastal parts of the footprint are hot and humid, which affects cooling design and PUE. Northern and higher-elevation areas are cooler. Land prices and tract sizes vary from dense suburban markets to large rural parcels in the interior. For fiber, count the carriers with routes in reach of the site and confirm that two of them follow physically separate paths. For water, ask the provider early about peak-day capacity and discharge limits, since a closed-loop or air-cooled design can shrink the request.

08What to check for a site in PJM

  1. 01Identify the transmission zone, transmission owner and retail utility that would serve the site.
  2. 02Learn the utility’s large-load process: study steps, deposits, required commitments and typical timelines.
  3. 03Map nearby substations and lines, and ask what other large loads are pending on them.
  4. 04Ask how PJM’s 2026 large-load measures would apply: whether the project would need to bring generation, accept curtailment, or both.
  5. 05Check the state’s retail rules, how energy supply would be procured, and how capacity costs would reach the bill.
  6. 06Review local zoning, recent data center decisions and any restrictions in the jurisdiction.
  7. 07Screen for slope, karst, flood exposure and severed mineral rights, and confirm fiber routes, carriers and diversity.

When we screen sites in PJM, we compare them zone by zone. Sites a few miles apart can sit behind different substations with very different outlooks. If you have a tract in the footprint, you can get a site reviewed.

CalculatorIT load to grid demand →CalculatorCooling water use →

Common questions

What states are in PJM?

PJM covers all or parts of Delaware, Illinois, Indiana, Kentucky, Maryland, Michigan, New Jersey, North Carolina, Ohio, Pennsylvania, Tennessee, Virginia and West Virginia, plus the District of Columbia. In several of them, only part of the state is in PJM. For a specific site, confirm which utility and transmission zone serve it.

Does a data center go through the PJM interconnection queue?

Not in the way a generator does. A data center applies for service to its local utility or transmission owner, which studies the request and coordinates with PJM; PJM folds large loads into its forecast and regional planning. On-site generation may need its own interconnection, and PJM’s 2026 proposals add an expedited track for loads that bring new generation.8

Why is power hard to get for data centers in parts of PJM?

Some zones host very large concentrations of data centers, and the local transmission system has to serve them alongside homes and businesses; Dominion alone reports about 70 GW of large-load requests.11 At the same time, retirements and load growth have left the region short of its capacity target.29 Outlying zones may have more room, which is why searches in PJM increasingly look beyond the established clusters.

Does PJM have a capacity market?

Yes. PJM runs a centralized forward capacity market, and load-serving entities pay for the capacity it procures. The 2028/2029 auction cleared at the $325/MW-day cap, about $118,625 per MW-year.2 Capacity costs reach large customers through utility rates or retail supply contracts, depending on the state, so they belong in any total power cost comparison.

Notes

  1. 1.PJM Interconnection, “PJM Releases 2025 Annual Report, ‘Meeting Each Moment’,” 2026. insidelines.pjm.com
  2. 2.PJM Interconnection, “PJM Capacity Auction Procures 138,318 MW of Generation Resources,” 2026. pjm.com
  3. 3.PJM Interconnection, “PJM Board Letter re Results of the CIFP Process: Large Load Additions,” 2026. pjm.com
  4. 4.PJM Interconnection, “PJM by the Numbers,” 2026. services.pjm.com
  5. 5.Industrial Info Resources, “Report: Data Centers Create About US$6.3 Billion in Electric Costs for PJM Customers,” 2026. industrialinfo.com
  6. 6.American Public Power Association, “PJM’s updated 20-year forecast continues to see significant long-term load growth, slightly decreases,” 2026. publicpower.org
  7. 7.Altoona Mirror, “Power load growth forecast drops slightly,” 2026. altoonamirror.com
  8. 8.PJM Interconnection, “Filing in FERC Docket No. EL25-49-000,” 2026. pjm.com
  9. 9.PJM Interconnection, “Board Decisional Letter on Critical Issue Fast Path,” 2026. pjm.com
  10. 10.PJM Interconnection, “PJM’s Updated 20-Year Forecast Continues To See Significant Long-Term Load Growth,” 2026. insidelines.pjm.com
  11. 11.Data Center Dynamics, “Dominion files large load connection queue plan with state regulators,” 2026. datacenterdynamics.com
  12. 12.Public Utilities Commission of Ohio, “PUCO urges FERC to require PJM to focus on data centers and leave traditional manufacturers alone,” n.d. content.govdelivery.com
  13. 13.K&L Gates, “FERC Orders PJM to Reform Tariff for Co-Located Generation and Load,” 2026. klgates.com
  14. 14.McGuireWoods, “Loudoun County Eliminates By-Right Use for Data Centers, Increasing Development Hurdles,” 2025. mcguirewoods.com
  15. 15.Data Center Watch, “Q1 2026: Data Center Watch Report,” 2026. datacenterwatch.org

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Terms in this guide

Related guides

More in Grid regions

Guide 1 of 9 in Grid regions · all 242 guides · glossary · calculators