Key takeaways
- Co-location ranges from fully islanded campuses to grid-connected configurations where the load sits behind the plant’s meter.
- The plant’s outages, remaining life and fuel or water supply become the data center’s risks; even nuclear units shut down for refueling every 18 to 24 months.4
- The Talen and Amazon deal at Susquehanna moved from behind-the-meter to a grid-connected, front-of-the-meter structure after FERC rejected an expanded interconnection agreement.56
- In PJM, FERC’s December 2025 order directed new transmission services for co-located load, and a June 2026 order required further changes;12 in ERCOT, SB 6 sets a review path for pairing large loads with existing generation.3
- Land next to a plant is often limited by buffers, existing easements and the plant owner’s own expansion plans.
01What does co-location with a power plant mean?
The idea is simple. A power plant already has generation, a transmission interconnection, a switchyard and usually water and fuel infrastructure. Put a data center next to it, and the campus can draw power without waiting for new transmission to be built across many miles.
In practice, co-location covers several different arrangements with different technical, commercial and regulatory consequences. The first task in evaluating a co-location opportunity is to pin down which one is actually on the table. The best-known U.S. example shows how much the label can shift: Amazon’s campus next to Talen’s Susquehanna nuclear plant in Pennsylvania began as a 300 MW behind-the-meter arrangement and is being converted to a grid-connected supply deal.56
02The main co-location configurations
| Configuration | How power flows | Grid role | Main tradeoff |
|---|---|---|---|
| Islanded, fully behind the meter | Plant serves the data center only, with no grid connection for the load | None, or the plant leaves the grid | Full exposure to plant outages; needs on-site redundancy |
| Grid-connected co-location | Load sits behind the plant’s meter; plant remains connected to the grid | Backup supply and a path for excess output | Regulatory and cost-allocation questions about grid use |
| Adjacent front-of-the-meter service | Load takes standard utility service from a nearby substation, often the plant’s switchyard | Full; the load is an ordinary grid customer | Behaves like any large-load request, but close to strong infrastructure |
| New generation built for the campus | New plant sized to the data center on shared or adjacent land | Varies by design | Longest lead time; full control of design and fuel |
The configurations are not equally available everywhere. In vertically integrated states the local utility often owns or controls both the plant and the retail service, which shapes what is possible. In restructured markets with independent generators, a direct deal with a plant owner is more common, but the grid operator and state regulators still have a say. Our guide to behind-the-meter vs. front-of-the-meter power explains the metering distinction in more depth.
New generation built for a campus is no longer hypothetical. At the former Homer City coal plant in Pennsylvania, developers plan up to 4.5 GW of gas-fired generation to serve a data center campus on the retired plant’s site.7 At the end of March 2026 the developer said the first vertical steel was going up, with about 3,700 MW of the initial output intended for data centers and the remainder for the grid.8 Many deals look more like the Microsoft and Constellation agreement tied to restarting the Crane unit (formerly Three Mile Island Unit 1): a long-term purchase of a plant’s output delivered over the grid, not a load on the plant site.9
Fig. 1Homer City: new generation built for a campus
- Planned gas-fired generation
- 4.5 GW
- Initial output intended for data centers
- ~3,700 MW
- Former coal plant site
- 3,200 acres
03What to check about the plant
A co-located campus inherits the plant’s strengths and weaknesses. Diligence on the plant is as important as diligence on the land.
- Availability and outages. Every plant has planned maintenance and unplanned outages. U.S. nuclear units typically refuel every 18 to 24 months, often in spring or fall, with outages lasting roughly a month on average in recent years; thermal plants have periodic major overhauls.4 Know how the campus is served during each.
- Unit configuration. A plant with several units can keep serving part of a load when one unit is down. A single-unit plant cannot.
- Remaining life and retirement plans. A plant that may retire within the data center’s planning horizon is a poor anchor unless replacement generation is part of the plan.
- Fuel and water. Gas supply firmness, coal or fuel logistics, and cooling water rights all carry over to the data center’s reliability.
- Environmental permits. Changes in how a plant operates, such as higher run hours, can trigger air permit review.
- Ownership and contracts. Existing offtake contracts, capacity obligations and lender consents can limit how much output is available to a new load.
Outage timing can also shape how a deal is restructured. Talen planned to reconfigure the Susquehanna campus from behind-the-meter to front-of-the-meter service during a scheduled spring 2026 refueling outage, continuing to serve the existing 300 MW arrangement until then.6 Confirm the current structure before relying on it as a precedent.
04What to check about the land
Plant sites are often large, but much of the acreage is spoken for. Switchyards, transmission corridors, fuel handling areas, ash or water ponds, buffer zones and land the owner holds for future units can all reduce what is available. Nuclear sites add security perimeters and exclusion areas, which our guide to nuclear and SMR siting covers. Adjacent land is a common answer: Amazon’s proposed campus in Somervell County, Texas, would sit on Vistra property next to the Comanche Peak nuclear plant, subject to final lease terms, with a tax abatement application describing up to 18 buildings on about 435 acres.10
- Confirm the boundary of the parcel offered and whether it is owned, leased or subject to the plant’s easements.
- Map transmission rights-of-way, pipelines and water lines that cross or border the land.
- Review environmental history, particularly at older thermal plants with ash or fuel storage. A Phase I ESA is a baseline, and retired or active plant land often needs more.
- Check zoning. Plant land may be zoned for utility or heavy industrial use that does or does not allow a data center.
- Look at access, flood exposure and room for the data center’s own substation, generators and cooling equipment.
Retired plant sites are a related but different opportunity. They may offer an existing interconnection and industrial zoning without the live-plant constraints, which our guides to repurposing industrial and power plant sites and surplus interconnection and retired plant sites explore.
05How regulators and grid operators view co-located load
Regulatory treatment is the least settled part of co-location, though it moved quickly in 2025. Several questions come up repeatedly:
- Whether a grid-connected co-located load is using, and should pay for, transmission service and other grid costs.
- How removing a plant’s output from the market affects resource adequacy and reliability for other customers.
- Whether the arrangement is a retail sale subject to state utility law, and who has the right to serve that load.
- What interconnection and metering changes are needed at the plant, and whether they trigger new studies.
- How the load must behave during grid emergencies, and whether it can be curtailed.
PJM and FERC
The Susquehanna case brought these questions to FERC. PJM asked FERC to approve an amended interconnection agreement that would have raised the co-located load from 300 MW to 480 MW; Exelon and AEP protested, arguing the arrangement could let the data center avoid up to $140 million a year in transmission costs, and FERC rejected the amendment.116 After a February 2025 show-cause proceeding, FERC found on December 18, 2025, that PJM’s tariff lacked clear rules for co-located load.1 It set a paper hearing on three new transmission services as alternatives to network integration service: interim non-firm service, firm contract demand service and non-firm contract demand service.112 FERC also found PJM’s behind-the-meter generation rules no longer just and reasonable and directed revisions with a transition for some existing customers.1 On June 18, 2026, FERC ruled on PJM’s compliance filing: it kept the three-service structure, found PJM’s proposed design of the firm and non-firm contract demand services not flexible enough, and required further tariff revisions.2 The same day it issued show-cause orders requiring all six RTOs and ISOs to justify or reform their rules for interconnecting large loads.13 Check the dockets for the current outcome. Our guide to PJM site selection covers the wider market.
Fig. 2Susquehanna co-location, 2024 to 2026
- 01
Behind-the-meter start
Campus served by up to 300 MW under the original agreement.
- 02
Expansion request
PJM files to raise the co-located load to 480 MW.
- 03
FERC rejects
Protests over transmission cost shifts; amendment blocked.
- 04
Restructured deal
June 2025: 1,920 MW front-of-the-meter supply through 2042.
- 05
Reconfiguration
Planned for the spring 2026 refueling outage.
ERCOT and Texas SB 6
Texas took a statutory route. Senate Bill 6, signed in June 2025, requires notice to ERCOT before an existing generation resource enters a net metering arrangement with a new co-located large load; ERCOT studies the effect on generation available to the grid, and the PUCT may approve, deny or condition the arrangement.314 By May 2026 the PUCT had approved two such arrangements, one pairing a data center with a wind farm and one with a gas plant, on conditions that include being able to curtail within 30 minutes in an ERCOT emergency.15 The law also covers loads of 75 MW or more and lets ERCOT direct large loads with backup generation to deploy it or curtail in an emergency.16 Our guide to Texas Senate Bill 6 covers the PUCT rulemakings.
Fig. 3SB 6 review of co-location with an existing plant
- 01
Notice to ERCOT
Before the net metering arrangement takes effect.
- 02
ERCOT study
Effect on generation available to the grid.
- 03
PUCT decision
Approve, deny or set reliability conditions.
State utility commissions, other grid operators and NERC reliability standards can also touch these questions. A co-location plan should be reviewed with regulatory counsel in the specific market before the deal terms are fixed, and revisited as rules change during development.
06When co-location makes sense
Co-location tends to fit when the plant has multiple units and a long remaining life, the land is genuinely available and buildable, and a grid backup path exists or can be arranged. It fits less well when the plant is near retirement, the site is boxed in, or the regulatory treatment in that market is unclear and the project cannot absorb a change.
It also helps to compare co-location against a standard large-load request at the same location. Sometimes the plant’s switchyard makes ordinary front-of-the-meter service fast and simple, and the extra complexity of a behind-the-meter deal is not worth it. Susquehanna is an example: the parties concluded that a grid-connected retail structure, with the plant owner acting as the licensed retail supplier and the local utility delivering power, did not need FERC approval.65 Energy developers weighing these options can start with our guide for energy developers.
- 01Pin down the configuration and whether the load will be behind or in front of the plant’s meter.
- 02Get the plant’s outage history, unit count, retirement outlook and fuel and water arrangements.
- 03Map what land is actually available after switchyards, corridors, buffers and future units.
- 04Identify which regulator and rules apply: the new PJM services as FERC finalizes them, SB 6 in ERCOT, or state law elsewhere.
- 05Price the grid backup path for the hours the plant is down.
When a plant-adjacent site is screened, both paths should be evaluated side by side. If you are weighing one, you can get a site reviewed.
Common questions
What is a co-located data center at a power plant?
It is a data center placed on or next to a power plant so it can take power directly from the plant, either fully separated from the grid or behind the plant’s meter while the plant stays grid-connected. The goal is faster access to large blocks of power using generation and switchyard equipment that already exist, rather than waiting for new transmission to reach a distant site.
Does a co-located data center still need a grid connection?
Usually, yes. Every power plant has maintenance periods and unplanned outages, and nuclear units shut down for refueling every 18 to 24 months.4 Most co-located campuses rely on a grid connection, other units at the plant or on-site generation and storage to cover those hours. A fully islanded design is possible but needs substantial on-site redundancy, which adds cost and land.
Is co-locating with a power plant regulated?
Yes, though how depends on the market. In PJM, FERC’s December 2025 order directed new transmission services for co-located load and changes to behind-the-meter generation rules, and FERC required further revisions in June 2026.12 In ERCOT, SB 6 requires ERCOT study and PUCT approval for net metering arrangements between existing plants and new large loads.3 Review the specific configuration with regulatory counsel early.
What happened with the Amazon and Talen Susquehanna deal?
FERC rejected an amended interconnection agreement that would have expanded the behind-the-meter load at Susquehanna from 300 MW to 480 MW.11 In June 2025, Talen and Amazon restructured the arrangement as a front-of-the-meter supply deal of up to 1,920 MW running through 2042, with power delivered over the grid by the local utility.56
What are the risks of co-locating with a power plant?
The main risks are dependence on one plant’s availability, its remaining life and retirement plans, its fuel and water supply, and changes in regulatory treatment. Land constraints are common too, since switchyards, corridors, buffers and future units take much of a plant site. Contract terms with the plant owner, including what happens during outages, deserve as much attention as the land.
Notes
- 1.Beveridge & Diamond, “FERC Orders PJM to Create Clear Rules for Co-Located Data Centers and Large Loads,” 2025. bdlaw.com
- 2.PJM Interconnection, “Co-Located Load and Large Load Show Cause Orders (stakeholder presentation),” 2026. pjm.com
- 3.Baker Botts, “Texas Senate Bill 6: Understanding the Impacts to Large Loads and Co-Located Generation,” 2025. bakerbotts.com
- 4.U.S. Energy Information Administration, “U.S. summer nuclear outages rose in 2023, returning to 2021 levels,” 2023. eia.gov
- 5.The Register, “Amazon has changed its nuclear deal in Pennsylvania to bypass grumpy regulators,” 2025. theregister.com
- 6.POWER Magazine, “Talen, Amazon Launch $18B Nuclear PPA: A Grid-Connected IPP Model for the Data Center Era,” 2025. powermag.com
- 7.Data Center Dynamics, “Homer City and Kiewit unveil plans for 4.5GW natural gas-powered AI data center in Pennsylvania,” 2025. datacenterdynamics.com
- 8.Axios Pittsburgh, “Homer City power plant, the grid and data centers in Pennsylvania,” 2026. axios.com
- 9.Converge Digest, “Microsoft taps Three Mile Island nuclear power for data centers,” 2024. convergedigest.com
- 10.Data Center Dynamics, “Amazon looks to build large-scale data center campus next to nuclear plant in Texas,” n.d. datacenterdynamics.com
- 11.Renewable Energy World, “Exelon and AEP protest interconnection agreement for Amazon data center at Susquehanna nuclear plant,” 2024. renewableenergyworld.com
- 12.Foley & Lardner, “FERC Opens New Paths for Co-Located Loads in PJM: What Data Center and Power Generation Developers Need to Know,” 2025. foley.com
- 13.Foley & Lardner, “FERC Issues Six Tailored “Show Cause” Orders to Accelerate Large Load Interconnection,” 2026. foley.com
- 14.Bracewell, “Texas Senate Bill 6 Ushers in Major Overhaul of Large Load Interconnection and Grid Access Rules,” 2025. bracewell.com
- 15.ERCOT, “Trending Topic: Grid Reliability, Data Centers and Net Metering Arrangements,” 2026. ercot.com
- 16.Utility Dive, “Texas law gives grid operator power to disconnect data centers during crisis,” 2025. utilitydive.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Power & interconnection
- How Much Power Does a Data Center Need?
- Transmission Voltage and Data Centers: 69 kV to 765 kV
- Substation Proximity and Capacity for Data Center Sites
- How the Large-Load Utility Interconnection Process Works
- Power Timelines: Why “When” Matters as Much as “Where”
- ISOs, RTOs and Utility Territories in Data Center Siting
- On-Site Generation and Bridge Power for Data Centers
- What Is Powered Land?
- Load Ramp Schedules: How to Phase Power for a Data Center Campus
- Redundant Utility Feeds and Dual Substations for Data Centers
- Large-Load Tariffs and Electric Service Agreements, Explained
- Transmission Upgrades for Data Centers: Who Pays for Them?
- Microgrids and Battery Storage at Data Center Sites
- Renewable Energy Procurement and How It Affects Data Center Siting
- What Is a Utility Load Study for a Data Center?
- Firm vs. Interruptible Electric Service for Data Centers
- Flexible Data Center Loads and Demand Response
- PJM Capacity Prices and Data Center Load Growth
- Contribution in Aid of Construction (CIAC) and Line Extensions for Data Centers
- Transformer and Switchgear Lead Times for Data Centers
- Substation Configurations for Data Center Campuses: Ring Bus, Breaker-and-a-Half and Double Bus
- Electricity Rates and Power Costs for Data Center Sites
- Power Purchase Agreements for Data Centers: Physical, Virtual and Sleeved
- 24/7 Carbon-Free Energy and Hourly Matching for Data Centers
- Gas Turbines vs. Reciprocating Engines for Data Center On-Site Power
- Fuel Cells for Data Center Power: How They Work and Where They Fit
- NERC Reliability Standards and Large Data Center Loads: Ride-Through, Load Loss and Registration
- From Signed Agreement to Energization: The Data Center Power Timeline
- Hydropower and Data Center Siting: Public Power, Allocations and Drought Risk
- Geothermal Power for Data Centers: Enhanced Geothermal, Clean Tariffs and Siting in the West
Guide 15 of 35 in Power & interconnection · all 242 guides · glossary · calculators
