Key takeaways
- The grid connection is often the main asset; confirm who owns the switchyard and what interconnection rights survive retirement.
- Generator interconnection rights and load service are different things; a data center needs load service from the utility unless it is paired with on-site generation.9
- In PJM, a replacement generator must request service within one year of the old unit’s deactivation to reuse its rights through the expedited process.7
- Coal ash ponds and landfills carry federal groundwater monitoring and post-closure care obligations and can remove large areas from use.1011
- Demolition, asbestos and PCB abatement and old foundations add cost and time before any pad is ready.14
01Why developers look at retired plants and industrial sites
Large power plants and heavy industrial facilities were built where the grid, water and transportation could support them. When they close, they leave behind exactly the things a data center campus struggles to find: high-voltage connections, cooling water, heavy-haul roads or rail, industrial zoning and hundreds of acres held in one ownership. A Pacific Northwest National Laboratory pamphlet on coal plant reuse notes that retired and retiring coal plants often have this kind of electrical infrastructure in place, while new large loads can face multi-year delays to reach the grid.1
The best-known example is the former Homer City Generating Station in western Pennsylvania, the state’s largest coal plant until it shut in 2023 after 54 years. Its owners plan a gas-powered data center campus of more than 3,200 acres with up to 4.5 GW of on-site generation, and much of the critical infrastructure, including transmission lines to the PJM and New York grids, substations and water access, was already in place.2 Trade press describes the value of that existing transmission as hard to overstate.3
These sites also tend to have local support. A closing plant takes jobs and tax base with it, and a data center can replace some of that tax base. A Columbia University capstone study found that coal-plant conversions work best when they combine strong grid connectivity, supportive policy, a viable business model and alignment with community needs.4 The general trade-offs between previously developed and raw land are covered in greenfield vs. brownfield sites.
Supply is not as large as it once looked. Of about 8.5 GW of coal capacity scheduled to retire in 2025, only 2.6 GW actually closed, the least since 2010; 4.8 GW was delayed and two plants cancelled retirement plans.5 Federal emergency orders under Section 202(c) of the Federal Power Act have also kept some plants running past planned retirement dates.5
Fig. 1U.S. coal retirements in 2025
- scheduled to retire in 2025
- 8.5 GW
- actually retired, least since 2010
- 2.6 GW
- retirement delayed
- 4.8 GW
- retirement cancelled
- 1.1 GW
02Common types of sites and what each tends to offer
| Former use | Typical strengths | Typical issues |
|---|---|---|
| Coal-fired power plant | Transmission switchyard, large acreage, water intake, rail | Coal ash ponds and landfills, asbestos, large demolition scope |
| Gas-fired power plant | Switchyard, gas supply, smaller footprint | Plant may still be operating or only partly retired; gas and water permits |
| Paper or pulp mill | Large water and wastewater systems, industrial power service | Sludge lagoons, chemical storage, riverfront floodplain |
| Steel, aluminum or smelting | Very large historical loads, substations, industrial zoning | Slag, metals contamination, deep foundations |
| Large manufacturing or assembly plant | Big flat pads, roads, sometimes existing buildings | Solvents, vapor intrusion, building reuse limits |
| Mine or quarry | Remote acreage, sometimes power service | Unstable ground, reclamation obligations, mineral leases |
| Crypto mining facility | Energized substation, recent service agreement | Light buildings, limited cooling and redundancy |
Former uses also shape what lies underground. Plants that handled solvents, fuels or metals tend to leave plumes that move with groundwater. Power plants tend to leave large ash deposits and buried pipelines. EPA’s list of common brownfield contaminants, including lead, asbestos, PCBs, petroleum, PFAS and arsenic, maps closely onto these industries.6 Knowing the industrial process helps focus sampling. Former crypto mining sites are a newer category with a different profile, covered in converting bitcoin mining sites to AI data centers.
03The grid connection: what transfers and what does not
A retired generating station usually sits beside a switchyard connected to the transmission network. PNNL describes the resulting point of interconnection as both physical infrastructure and the rights to use it, and expects reuse to be faster and cheaper than building a new one, though a study and some upgrades may still be required.1 That connection is the headline asset, and it is easy to overvalue. Several questions need answers:
- Who owns the switchyard? Often the transmission owner or utility owns part or all of it, not the plant owner selling the land.
- What happens to the generator’s interconnection rights at retirement? In PJM, a replacement resource at the same substation and voltage, no larger than the retiring unit, can use an expedited process if it applies within one year of deactivation; it generally must be in service within about three years and pays for all required network upgrades.7 Other markets have their own rules.
- Can unused capacity be shared? FERC Order No. 845 required transmission providers to let new generation use surplus interconnection service at an existing point of interconnection without a full queue study, and FERC expanded PJM’s version in 2025.8
- Is the site getting load service or generator service? A data center is a load. It needs an agreement with the serving utility under its large-load process, separate from any generator rights. See the large-load interconnection process.
- What did retirement do to the grid? Removing a plant can change power flows and reliability needs nearby. The grid operator may require upgrades before the area can absorb a large new load.
- Is the plant actually retiring? Some units are kept online for reliability, sometimes under federal emergency orders that can be renewed.
Fig. 2Reusing a retiring unit’s rights in PJM
- 01
Deactivation
Existing unit retires; its capacity rights start a one-year clock.
- 02
Request
Replacement request filed within one year of deactivation.
- 03
Eligibility
Same substation and voltage; output no larger than the old unit.
- 04
Expedited study
Runs outside and in parallel to the regular cycle process.
- 05
In service
Generally within about three years; owner pays all upgrades.
Some developers pair a new campus with new or remaining generation on the same site, as Homer City plans.2 In December 2025, FERC directed PJM to revise its tariff to make surplus interconnection service available to new generation serving co-located load and to create new transmission services for co-located arrangements.9 Metering, market rules and regulatory treatment are covered in co-locating data centers with power plants and surplus interconnection at retired plant sites.
04Legacy environmental issues
Older industrial and power sites carry a predictable set of environmental issues. Each can take land out of use or add obligations that run with the property.
- Coal combustion residuals: ash ponds and landfills are regulated under federal rules issued under the Resource Conservation and Recovery Act. A 2024 rule extended requirements to inactive impoundments at inactive plants and to previously unregulated CCR management units.10 Units closed with waste in place carry groundwater monitoring, corrective action and post-closure care obligations.11
- Shifting deadlines: EPA extended several legacy-unit compliance deadlines in 2025 and proposed further amendments in 2026, including changes to how earlier closures are treated, so check the current rule before relying on any date.1112
- Asbestos and lead paint in boilers, piping and buildings, which require inspection and abatement before demolition.14
- PCBs in older transformers, capacitors and hydraulic systems.6
- Fuel oil and chemical tanks, above and below ground, with related soil and groundwater impacts.
- Solvent and metals contamination at manufacturing sites, including vapor intrusion risk for occupied buildings.
- Permits that remain open: groundwater monitoring, stormwater and wastewater permits, and environmental covenants recorded against the land.
An ASTM E1527-21 Phase I Environmental Site Assessment is the starting point, along with a review of regulator files. Most of these sites need Phase II sampling and a clear plan for which areas will be remediated, capped or avoided. The site plan should treat closed ash units and capped areas as fixed constraints from day one. Liability tools are covered in brownfield cleanup programs and liability protections.
Fig. 3From fence line to developable acres
Illustrative- Acres inside the fence900
- Ash ponds and landfill-210
- Switchyard and corridors-45
- Riverfront floodplain-120
- Easements and covenants-60
- Buffers and stormwater-75
- Developable acres390
acres
05Water, rail and other reusable infrastructure
Steam plants and mills used large amounts of water, so many have river or lake intakes, wells and discharge outfalls. A data center usually needs far less water than a steam plant, which can make the existing systems attractive. Reuse is not automatic. Cooling water intakes are regulated under Section 316(b) of the Clean Water Act; EPA’s 2014 rule for existing facilities applies to those that withdraw at least 2 million gallons per day and use at least 25% of it for cooling, with requirements written into NPDES permits.13 Discharge permits are written for a specific operation, and water rights in prior-appropriation states may be tied to a particular use. Changing the use typically needs approval from the state agency; see water rights and groundwater permits.
Rail spurs, heavy-haul roads and large laydown areas help with transformer and generator deliveries. Gas laterals matter too where on-site generation is planned; Homer City’s developers received a state grant to extend a gas line to the property.2 Existing buildings rarely fit modern data hall design, but office buildings, warehouses and shops can sometimes serve construction or support functions while demolition proceeds elsewhere.
06Demolition and site preparation
Clearing a large plant is a project of its own. Boilers, turbines, stacks, cooling towers, coal handling systems and deep foundations all have to come out or be designed around. At Homer City, the owners demolished three cooling towers and four smokestacks before redevelopment began.2 Abatement comes first, then demolition, then removal or documentation of what stays buried. Under the federal asbestos NESHAP, a thorough inspection for asbestos is required before demolition, and the state or local agency must be notified at least 10 working days before demolition starts, whether or not asbestos was found.14 Scrap value can offset some cost, but schedules run long, and a buyer should know whether the seller or the buyer is responsible for each step.
- Agree on the demolition scope and the condition the land will be in at closing.
- Get records of buried utilities, foundations, tunnels and fill.
- Run geotechnical work after demolition where old structures may have altered the ground.
- Check whether stacks or cooling towers stay standing during construction, since tall structures affect crane and FAA planning.
- Confirm the asbestos survey and demolition notice requirements with the state or local air agency, which may add its own rules.
07Title, easements and contracts tied to the old use
Industrial and utility land often carries decades of recorded documents: transmission and pipeline easements, rail agreements, water rights filings, mineral reservations, environmental covenants and agreements with the utility or neighbors. Some will help the new use, and some will block parts of the site. A full title review and an ALTA/NSPS survey are standard, and our guide to title review and ALTA surveys explains what to look for.
When we evaluate a retired plant, we map the switchyard, ash units, easements and environmental controls together. The developable area is what remains outside all of them, and it is often smaller than the fence line suggests. If you hold or are weighing a former plant or mill, you can get a site reviewed.
Common questions
Can a data center use a retired power plant’s grid connection?
Sometimes, but not automatically. The data center needs load service from the utility under its large-load process, which is separate from the generator’s interconnection rights. The existing point of interconnection can make service faster or cheaper than at a new site, but a study and upgrades may still be needed, and the utility and grid operator must confirm capacity and who owns the equipment.1 Rules on reusing a retiring generator’s rights vary by market; PJM’s process has a one-year window after deactivation.7
Can you build on top of a closed coal ash pond?
Generally not for buildings or heavy equipment. Ash units closed with waste in place carry groundwater monitoring and post-closure care obligations under federal rules, and the material is usually not suitable for foundations.11 Some closed areas may be usable for low-impact purposes, depending on the regulator. Most data center site plans treat closed ash units as unbuildable.
Why are retired industrial sites attractive for data centers?
They often have what new campuses need and struggle to get: high-voltage power connections, water supply and discharge, heavy-haul roads or rail, industrial zoning, large acreage in one ownership and local officials who want the land back in use.4 In exchange, they bring contamination, demolition and legacy permit obligations that have to be resolved before construction.
Who pays for demolition and cleanup when buying a former plant site?
It is negotiated. Some sellers demolish and remediate before closing, some sell as-is at a lower price, and many split responsibility through purchase agreement terms, escrows, indemnities and environmental insurance. Regulatory obligations such as ash unit post-closure care often stay with the original owner, but that depends on the permits and the agreement.10 Legal and environmental advisers should structure it.
Are many coal plants still coming available?
Fewer than planned, for now. In 2025 only 2.6 GW of a scheduled 8.5 GW of coal capacity retired, and federal emergency orders have kept some plants online.5 Retirement schedules can change quickly, so confirm a plant’s status with its owner and the grid operator before counting on the site.
Notes
- 1.Pacific Northwest National Laboratory, “Redeveloping Coal Power Plants: Data Centers,” 2024. pnnl.gov
- 2.ABC News (Associated Press), “Pennsylvania’s Largest Coal-Fired Power Plant, Now Retired, to Become Gas-Powered Data Center Campus,” 2025. abcnews.go.com
- 3.Data Center Frontier, “From Coal to Compute: How Pennsylvania Is Rebuilding Power for AI Data Centers,” n.d. datacenterfrontier.com
- 4.Columbia University School of International and Public Affairs, “From Soot to Servers: Paving the Way for Digital Age by Using US Coal Power Plant Brownfields,” n.d. sipa.columbia.edu
- 5.U.S. Energy Information Administration, “U.S. Coal-Fired Generating Capacity Retired in 2025 Was the Least in 15 Years,” 2026. eia.gov
- 6.U.S. Environmental Protection Agency, “Environmental Contamination Brownfield Sites,” n.d. epa.gov
- 7.Troutman Pepper Locke, “FERC Accepts PJM’s Replacement Generation Interconnection Process,” 2026. troutmanenergyreport.com
- 8.McGuireWoods, “FERC Approves Expansion of PJM’s Surplus Interconnection Service to Address Near-Term Resource Adequacy Concerns,” 2025. mcguirewoods.com
- 9.Sheppard Mullin, “FERC Directs Revisions to Enable Co-Located Load Data Centers and Generation,” 2025. sheppard.com
- 10.U.S. Environmental Protection Agency, “Legacy CCR Surface Impoundments and CCR Management Units Final Rule,” 2024. epa.gov
- 11.U.S. Environmental Protection Agency, “Webinar Slides: 2026 CCR Amendments Proposal,” 2026. epa.gov
- 12.J. J. Keller, “EPA Offers CCR Facilities Delayed Reporting Option and Extends Compliance Deadlines,” 2025. jjkellercompliancenetwork.com
- 13.WilmerHale, “EPA Final 316(b) Rule Establishes Standards for Cooling Water Intake Structures at Existing Facilities,” 2014. wilmerhale.com
- 14.West Virginia Department of Environmental Protection, “Asbestos Removal and Demolition,” n.d. dep.wv.gov
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Land & site fundamentals
- How Much Land Does a Data Center Need?
- Data Center Site Selection Criteria: The Complete Checklist
- Parcel Assembly for Data Center Campuses
- Gross vs. Buildable Acreage: How Much of a Site You Can Use
- Site Shape, Access and Frontage for Data Centers
- Can My Land Host a Data Center? A Landowner’s Guide
- Mineral Rights and Easements: How They Affect Data Center Land
- Title Review and ALTA Surveys for Data Center Land
- Can Farmland Be Converted to a Data Center?
- Data Center Land Option Agreements: Key Terms for Landowners
- Ground Leases for Data Centers: Terms, Rent, Financing and Reversion
- What Drives Data Center Land Value? Power, Timing, Entitlements and Size
- Topographic Surveys and LiDAR for Data Center Site Selection
- Heavy-Haul Routes and Construction Access for Data Centers
- Certified Sites and Shovel-Ready Programs: What They Mean for Data Centers
- Eminent Domain and Transmission Line Easements: A Landowner’s Guide
- How Data Centers Are Taxed: Property Taxes, Abatements and PILOTs
- Federal Land for AI Data Centers: DOE Sites, BLM and Military Bases
- Conservation Easements and Deed Restrictions on Data Center Land
- Subdivision, Platting and Lot Consolidation for Data Center Sites
- Agricultural Tax Status and Rollback Taxes When Farmland Is Developed
Guide 8 of 23 in Land & site fundamentals · all 242 guides · glossary · calculators