Key takeaways
- Load interconnection has mostly been a utility and state matter, but in June 2026 FERC opened proceedings on large loads of about 50 MW and up connecting above 69 kV in all six FERC-jurisdictional RTO and ISO regions.2
- The typical path is inquiry, formal request, a series of increasingly detailed studies, agreements, construction and staged energization.1
- Utilities want a specific site, a credible ramp and proof the project is real; Texas law now requires site control and a study fee of at least $100,000 for loads of 75 MW or more.4
- Expect minimum-demand charges, collateral, long terms and exit fees: an August 2026 LBNL analysis of 55 large-load tariffs found 39 approved and 13 pending.3
- Flexibility can speed things up. A Duke study estimated 76 GW of new load could fit on existing systems if curtailed just 0.25% of the time.5
01How load interconnection differs from generator interconnection
People often borrow the vocabulary of generator interconnection when talking about data centers. The two processes have been different. Generator interconnection to the transmission grid is governed by FERC-approved procedures and, in ISO and RTO regions, run by the grid operator through formal queues. Load interconnection has usually been a retail service matter: the local utility, and in some cases a separate transmission owner, studies and serves the load under rules overseen by the state utility commission.
That line is shifting. In October 2025 the Department of Energy used its authority under the DOE Organization Act to ask FERC to consider rules for loads above 20 MW connecting directly to transmission, including assigning network upgrade costs to those customers, and sought final action by April 30, 2026.67 Rather than issue one national rule, FERC on June 18, 2026 issued show cause orders to PJM, MISO, SPP, CAISO, ISO New England and NYISO, preliminarily finding their tariffs may be unjust and unreasonable because they lack adequate provisions for large loads, which the orders define using thresholds of 50 MW and 69 kV. Each grid operator had 60 days to respond in its own proceeding.2
For a developer, the practical result as of October 2026 is a two-layer process in many regions: the utility’s retail process plus a grid operator process that is still being settled. Our guide to ISOs, RTOs and utility territories explains who does what, and NERC reliability and large loads covers the reliability side. Either way, ask early for the utility’s written process.
02The typical steps, from inquiry to energization
- 01Informal inquiry. The developer describes a site, a load size and a target date. The utility offers high-level feedback, often starting with whether distribution can serve it at all.
- 02Formal load request. A written application with site location, load ramp, power quality needs, redundancy and schedule, often with a study fee or deposit.1
- 03Feasibility study. A preliminary look at whether existing facilities can serve the load and what broad upgrades might be required.
- 04System impact study. Detailed power-flow, contingency and stability analysis of the load’s effect on the transmission system, sometimes coordinated with the ISO or RTO.
- 05Facilities study. Engineering design and cost estimates for the specific substation, line and network upgrades.
- 06Agreements. Engineering and construction agreements, an electric service agreement, and any contribution or security arrangements.
- 07Design, procurement and construction. Utility and customer facilities are built, often with long-lead equipment ordered well ahead.
- 08Energization and ramp. Service begins, usually at a fraction of full load, and increases on the agreed ramp schedule.
Fig. 1From load request to energization
- 01
Request
Site, peak MW, ramp, fee or deposit.
- 02
Feasibility
Preliminary, non-binding screen.
- 03
System impact
Load flow, short circuit, stability.
- 04
Facilities study
Design and cost of specific upgrades.
- 05
Agreements
Service terms, security, cost sharing.
- 06
Build and energize
Construction, then a staged ramp.
RMI describes the core of the process as three increasingly detailed studies that determine the transmission upgrades needed and their cost.1 Utilities name and combine these steps differently. Some merge the studies; others add a pre-application stage or study requests in groups. The Energy Systems Integration Group has recommended moving to cluster studies as large-load request volumes grow.8 Texas has gone that way: in June 2026 the PUCT approved a “Batch Zero” framework that studies loads of 75 MW or more in batches.9 The sequence still moves from rough to specific, with commitments rising at each step. Our guide to utility load studies explains what each study tests.
03What the utility will ask you for
| Item | Why the utility needs it |
|---|---|
| Site location and site control | Studies are location-specific; Texas law now requires site control for large loads4 |
| Peak demand in MW and MVA, by year | Sets the ramp the system must serve |
| Load profile and power factor | Affects voltage, losses and equipment sizing |
| Load behavior (ramp rates, swings, ride-through) | Fast-changing or tripping loads can affect grid stability |
| Redundancy needs (one or two sources) | Drives substation and line configuration |
| Target energization dates | Determines whether upgrades can be built in time |
| On-site generation or storage plans | Changes how the load interacts with the grid |
| Financial capability | Supports cost responsibility and security requirements |
Load behavior now gets real scrutiny. In July 2024 a fault on a 230 kV line in the Eastern Interconnection led customer protection systems to disconnect about 1,500 MW of data center load across 60 load points and 25 substations as facilities moved to backup power; NERC’s incident review found that no utility equipment tripped the load and warned that the grid has been planned around large generation losses, not simultaneous load losses.10 Expect questions about ride-through settings and dynamic models.
Expect the utility to ask for more detail as studies progress, and to treat a material change in any of these inputs as a reason to restudy. The load figures should come from a real design basis, not a placeholder. Our guide to data center power requirements explains how to build them from IT load and PUE.
04Costs and financial commitments
Serving a very large load can require new substations, lines and network upgrades. Utilities and regulators want existing customers protected from costs caused by one new customer, and large-load tariffs are now the main tool. Lawrence Berkeley National Laboratory’s August 2026 analysis of a sample of 55 tariffs from 47 utilities found 39 approved and 13 pending as of August 6, 2026, and grouped minimum demand thresholds, minimum billing demand, minimum bills, exit fees and collateral among the established practices.3
- Study fees and deposits. Texas’s adopted rule sets a flat $100,000 study fee for large-load customers.11
- Contribution in aid of construction (CIAC), where the customer pays directly for facilities built to serve it. In a July 2026 order, Virginia regulators directed Dominion to develop rules that assign more transmission costs directly to large loads, including mandatory contributions for defined direct-connect transmission facilities.1213
- Credit support, such as letters of credit or parent-company credit. Pennsylvania’s model tariff requires security covering network and interconnection facility costs, which can step down as milestones are met.14
- Minimum-demand charges. Pennsylvania’s model sets 80% of contracted demand, and Dominion’s new GS-5 class bills transmission on at least 85% of peak demand from January 1, 2027.1214
- Long contract terms and exit fees if the customer reduces its load or leaves early.
Fig. 2Three recent large-load frameworks
Pennsylvania model tariff
- Minimum demand charge of 80% of contracted demand
- Security covers network and interconnection facility costs
- Security can step down as milestones are met
Dominion GS-5 (Virginia)
- New class for customers of 25 MW or more
- Takes effect January 1, 2027
- Transmission billed on at least 85% of peak demand
- CIAC policy ordered for direct-connect lines
Texas PUCT rule (SB 6)
- Applies to loads of 75 MW or more
- Site control required
- Flat $100,000 study fee
- Rule issued September 18, 2026
Virginia shows how quickly terms move. The State Corporation Commission’s November 2025 order created the GS-5 class for customers of 25 MW or more, effective January 1, 2027, with stronger financial requirements.15 Texas’s rule, adopted September 18, 2026, dropped the non-refundable $50,000 per MW interconnection fee in the March 2026 proposal in favor of the flat study fee.11 White & Case reports that a $50,000 per MW financial security, posted before studies, remains, so read the adopted text before budgeting.16 These terms affect site economics, so bring them into comparisons early. See large-load tariffs and electric service agreements and contribution in aid of construction.
05What slows the process down
- Changes to the load, ramp or site after a study has started, which can send the request back to an earlier stage.
- Many large requests in the same area. Utility Dive reported ERCOT’s large-load queue at about 474 GW in 2026, roughly 90% of it data centers.11
- Network upgrades that need new transmission lines with state siting approval.
- Long lead times for large power transformers and high-voltage breakers.
- Coordination with a separate transmission owner or the ISO or RTO, now including new FERC-directed procedures.
- Unresolved site control, zoning or easements for the utility’s facilities.
Most of these are within the developer’s control only at the start: a stable request, a controlled site and early work on easements remove several common sources of delay. How these pieces add up to a service date is covered in our guides to power timelines and interconnection queues and the energization timeline.
06Where flexibility and on-site generation fit
A load that asks for full firm service from day one, at all hours, under all grid conditions, is the hardest kind to serve. Research suggests modest flexibility opens a lot of room. Duke University’s Nicholas Institute estimated that the 22 largest U.S. balancing authorities, covering about 95% of U.S. load, could add 76 GW to 126 GW of new load if it could be curtailed for 0.25% to 1% of its maximum uptime.5 ESIG has recommended expanded non-firm, surplus and provisional service options where firm service is not immediately available.8
Fig. 3Grid headroom from flexible load
- New load at 0.25% curtailment
- 76 GW
- New load at 1% curtailment
- 126 GW
- Share of U.S. load in the study area
- 95%
- Agreeing to reduce load during declared grid emergencies, supported by on-site generation or storage.
- Accepting a lower firm level for an interim period while upgrades are built, with the balance served when available.
- Phasing energization to match the utility’s upgrade schedule rather than a single large step.
- Pairing the load with on-site or co-located generation, subject to the utility’s and market’s rules.
Each option comes with its own engineering, permitting and contractual work. See flexible data center loads and on-site generation and bridge power. Raise flexibility early, because it can change what the utility studies.
07How to strengthen a large-load request
- Secure site control before the formal request. Many utilities require it.
- Present a ramp you can stand behind. Overstated early phases create cost obligations and lose credibility.
- Identify a preferred point of connection, informed by your own screening of substation capacity and proximity.
- Document ride-through behavior and backup transfer schemes, since planners now ask about both.
- Offer flexibility where you can: phased energization, curtailment during grid emergencies, or on-site generation.
- Keep one consistent project contact and respond quickly to data requests.
Common questions
How long does large-load interconnection take?
It varies widely by utility and by what must be built. If existing facilities can serve the load with modest substation work, the process can move relatively quickly. If the load needs new transmission lines or major upgrades, timelines commonly stretch over several years because of siting approvals, construction and equipment lead times. Ask the utility for its study schedule and the drivers of its estimated service date.
Who pays for the upgrades needed to serve a data center?
It depends on the utility’s tariffs and state rules. Facilities built only for the customer are often paid for through a contribution in aid of construction, and in July 2026 Virginia regulators directed Dominion to require one for defined direct-connect transmission facilities.12 Broader network upgrades may be shared or recovered through rates, subject to each tariff’s protections for other customers.
Is a data center load request the same as a generator interconnection queue?
No, though they are converging. Generator interconnection runs through FERC-approved grid operator queues, while load interconnection has usually been handled by the local utility under state rules. FERC’s June 2026 orders direct the six RTOs and ISOs to justify or revise their rules for loads of about 50 MW and up connecting above 69 kV, and Texas now studies large loads in batches.29
Do I need to own the land before applying for utility service?
Many utilities require site control, such as ownership, a purchase option or a lease, before accepting a formal request or starting detailed studies, and Texas law requires it for loads of 75 MW or more.4 Informal conversations can happen earlier. Because studies are location-specific, moving the project usually means starting over.
What is a large-load tariff?
It is a utility rate schedule with special terms for very large customers, typically above a set MW threshold. LBNL’s 2026 analysis found common features include minimum billing demand, minimum bills, exit fees and collateral.3 Thresholds and percentages vary; Dominion’s GS-5 class, for instance, starts at 25 MW.15
Notes
- 1.RMI, “Understanding Large Load Interconnection,” n.d. rmi.org
- 2.Beveridge & Diamond, “FERC Moves to Speed Interconnection of Data Centers and Other Large Loads,” 2026. bdlaw.com
- 3.Lawrence Berkeley National Laboratory, “Rate Designs for Large Loads,” 2026. eta-publications.lbl.gov
- 4.Foley & Lardner, “Public Utility Commission of Texas Issues Proposed Rules for Large Load Interconnection,” 2026. foley.com
- 5.Duke University Nicholas Institute, “Rethinking Load Growth: Assessing the Potential for Integration of Large Flexible Loads in US Power Systems,” 2025. nicholasinstitute.duke.edu
- 6.Beveridge & Diamond, “DOE Invokes Rare Authority to Direct FERC to Accelerate Grid Access for Large Loads and Data Centers,” 2025. bdlaw.com
- 7.Renewable Energy World, “DOE Directs FERC to ‘Rapidly Accelerate’ Large Load, Data Center Interconnection,” 2025. renewableenergyworld.com
- 8.Energy Systems Integration Group, “Interconnection Processes for Large Loads: Current Practices and Recommendations,” n.d. esig.energy
- 9.Sheppard Mullin, “PUCT Approves Batch Zero Framework That Will Provide a Pathway for Large Load to Connect to the Grid and Receive Electricity,” 2026. sheppard.com
- 10.North American Electric Reliability Corporation, “Incident Review: Large Load Loss,” 2025. nerc.com
- 11.Utility Dive, “Texas PUC Adopts Data Center Interconnection Rules,” 2026. utilitydive.com
- 12.Data Center Dynamics, “Virginia Regulators Order Dominion Energy to Directly Assign Transmission Costs to Data Centers,” 2026. datacenterdynamics.com
- 13.Virginia Mercury, “SCC Orders Dominion to Develop Tariff to Assign More Transmission Costs to Data Centers,” 2026. virginiamercury.com
- 14.JD Supra, “Pennsylvania’s Large Load Model Tariff Offers a Road Map for North Carolina,” n.d. jdsupra.com
- 15.Southern Environmental Law Center, “Dominion Customers to See Rate Increase, Though SCC Takes Steps Designed to Ensure Data Centers Pay Fair Share,” 2025. selc.org
- 16.White & Case, “PUCT Sets Financial Commitments for Data Center Interconnection as Governor Pauses Permit Approvals,” 2026. whitecase.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Power & interconnection
- How Much Power Does a Data Center Need?
- Transmission Voltage and Data Centers: 69 kV to 765 kV
- ISOs, RTOs and Utility Territories in Data Center Siting
- On-Site Generation and Bridge Power for Data Centers
- What Is Powered Land?
- Load Ramp Schedules: How to Phase Power for a Data Center Campus
- Redundant Utility Feeds and Dual Substations for Data Centers
- Behind-the-Meter vs. Front-of-the-Meter Power for Data Centers
- Transmission Upgrades for Data Centers: Who Pays for Them?
- Microgrids and Battery Storage at Data Center Sites
- Co-Locating Data Centers With Power Plants
- Nuclear and Small Modular Reactors: Siting Considerations for Data Centers
- Renewable Energy Procurement and How It Affects Data Center Siting
- Firm vs. Interruptible Electric Service for Data Centers
- PJM Capacity Prices and Data Center Load Growth
- Contribution in Aid of Construction (CIAC) and Line Extensions for Data Centers
- Transformer and Switchgear Lead Times for Data Centers
- Substation Configurations for Data Center Campuses: Ring Bus, Breaker-and-a-Half and Double Bus
- Electricity Rates and Power Costs for Data Center Sites
- Power Purchase Agreements for Data Centers: Physical, Virtual and Sleeved
- 24/7 Carbon-Free Energy and Hourly Matching for Data Centers
- Gas Turbines vs. Reciprocating Engines for Data Center On-Site Power
- Fuel Cells for Data Center Power: How They Work and Where They Fit
- NERC Reliability Standards and Large Data Center Loads: Ride-Through, Load Loss and Registration
- From Signed Agreement to Energization: The Data Center Power Timeline
- Hydropower and Data Center Siting: Public Power, Allocations and Drought Risk
- Geothermal Power for Data Centers: Enhanced Geothermal, Clean Tariffs and Siting in the West
- Surplus Interconnection Service and Retired Power Plant Sites: How Existing Grid Rights Get Reused
Guide 4 of 35 in Power & interconnection · all 242 guides · glossary · calculators
