Key takeaways
- Contract demand, the capacity reserved for the customer year by year along the ramp, is the base for minimum bills and collateral.
- Minimum bills of 80–85% of contracted demand appear in several recent tariffs, including AEP Ohio and Indiana Michigan Power.23
- Terms are getting longer: in LBNL’s 2026 sample, tariffs proposed since 2025 typically set minimum terms of about 12 years, against about five years in earlier tariffs.1
- Collateral, direct assignment of facility costs and, increasingly, exit fees protect other customers from costs built for one large load.14
- Texas Senate Bill 6 directs regulators to require screening study fees, proof of site control and financial commitments from large loads.5
- Compare these terms across sites early; they are part of site economics, not just legal detail.
01Tariff vs. electric service agreement
A tariff is a utility’s published schedule of rates, charges and conditions of service, approved by its regulator. Investor-owned utilities file tariffs with a state public utility commission; municipal utilities and cooperatives set rates through their own governing bodies, sometimes with state oversight. A growing number of utilities have provisions for very large loads such as data centers, and their starting points differ widely: minimum demand thresholds in the tariffs LBNL reviewed range from 0.3 MW to 150 MW.1
The electric service agreement is the contract between the utility and one customer. It applies the tariff to a specific site and load and fills in the details: the ramp, contract demand, facilities to be built, who pays for them, security, term and what happens if plans change. For the largest loads it may be a negotiated special contract that needs regulatory approval of its own. Georgia’s Public Service Commission, for example, requires Georgia Power to submit new contracts with customers above 100 MW for commission review.6
The ESA usually follows the load studies in the large-load interconnection process. It is the point where the utility’s cost and capacity commitments, and the customer’s financial commitments, become binding.
02The key terms in a large-load agreement
| Term | What it means | Why it matters |
|---|---|---|
| Contract demand | The capacity in MW the utility agrees to provide, often set for each year | Sets the base for demand charges, minimum bills and collateral |
| Demand charge | A charge per kW or kVA of peak demand in a billing period | A large share of the bill for high-load-factor customers |
| Minimum bill / take-or-pay | A floor charge based on a share of contract demand, owed even if load is lower | Turns an optimistic ramp into a fixed cost |
| Ratchet | A rule that bills demand at a share of a past peak or of contract demand | Limits savings from lower usage after a high month |
| Collateral / credit support | Letters of credit, cash deposits or parent-company credit sized to the utility’s exposure | Ties up capital; amount often depends on credit rating |
| CIAC | Contribution in aid of construction: the customer pays for facilities built to serve it | Can be a large upfront cost for substations and lines |
| Term | Length of the service commitment | Long terms reduce flexibility to move or shrink |
| Exit or termination fee | Charges if the customer leaves early or cuts contract demand | Defines the cost of changing course |
Not every agreement uses all of these, and the same term can work differently between utilities. Newer tariffs also add exit fees, capacity reassignment provisions and hold-harmless mechanisms aimed at the risk that a customer reduces or ends service before the utility recovers its investment.4
03Contract demand, minimum bills and take-or-pay
Contract demand is the center of the agreement. It is the capacity the utility plans and builds for, and it usually follows the project’s load ramp schedule. If the campus is planned to reach 150 MW in year three, contract demand for year three is likely to be near 150 MW.
Minimum bill and take-or-pay provisions exist because utilities and regulators do not want other customers paying for capacity built for a load that never arrives. The customer pays a floor tied to contract demand even if actual demand is lower, so a delayed tenant or a slow fit-out does not cut the bill as much as it would under a normal tariff. Recent floors are high:
- AEP Ohio. A July 9, 2025 Ohio commission order requires new data centers above 25 MW to pay for at least 85% of their subscribed electricity demand for up to 12 years, including a four-year ramp-up period.27
- Indiana Michigan Power. Its settlement, approved by Indiana regulators in February 2025, applies to new or expanded loads of at least 70 MW at a site or 150 MW in aggregate and sets an 80% minimum monthly billing demand.38
- Dominion Energy Virginia. Virginia’s State Corporation Commission approved a new GS-5 class for customers of 25 MW or more, effective January 1, 2027, with 14-year commitments to pay at least 85% of contracted transmission and distribution demand and at least 60% of generation demand, as reported at the time of the order.9
Fig. 1Where a minimum bill bites
Low exposure
The floor rarely binds if the ramp holds.
Manageable
Fine if the ramp holds; model a delay case.
Flexible
Check exit fees and reduction rights.
Highest exposure
Negotiate deferral rights or phase contract demand.
Lower ← Minimum bill share → Higher
- Ask what share of contract demand the minimum applies to, and whether it changes over the term.
- Ask whether contract demand can be deferred or reduced with notice, and at what cost.
- Ask whether the minimum covers only demand charges or energy and other charges too.
04Collateral and contributions in aid of construction
Collateral protects the utility if the customer fails to pay or walks away. It is usually sized to the utility’s unrecovered investment or to a set period of minimum bills, and it may step down as the load ramps. Customers with strong credit may be able to substitute parent-company credit support for cash or a letter of credit; project-level entities often post more. AEP Ohio’s tariff pairs higher collateral requirements with a showing that the data center owner is financially able to meet its obligations,7 and Indiana Michigan Power’s settlement also increased collateral.3
CIAC is different. It pays for facilities built mainly to serve the customer: the line extension, the customer substation, a new switching station or similar. Some utilities require it up front; others recover it through a facilities charge or credit part of it back as the load generates revenue. Regulators are tightening this too: the Virginia SCC directed Dominion to file an amended line-extension policy requiring a mandatory CIAC for defined “direct connect” transmission facilities built for large loads that are the but-for cause of them.10 See CIAC and line extensions for the mechanics and who pays for transmission upgrades for shared network upgrades.
05Contract term, exit fees and flexibility
Large-load agreements now run much longer than a typical commercial contract. In LBNL’s 2026 sample of 55 tariffs, those proposed since 2025 typically set minimum contract terms of about 12 years, against about five years in earlier tariffs.1 For Georgia Power customers above 100 MW, the Georgia PSC said its January 2025 rule extends terms from five years to 15 years and allows minimum billing, so a customer cannot leave before the infrastructure built for it is paid for.6 Long terms let the utility recover its investment but reduce the customer’s flexibility.
Fig. 2Minimum contract terms for large loads
- Typical, earlier tariffs (LBNL)5
- Typical, proposed since 202512
- AEP Ohio data centers12
- Indiana Michigan Power12
- Georgia Power, over 100 MW15
years
Exit fees set the cost of shrinking or leaving. Indiana Michigan Power’s exit fee equals the minimum charge, capped at five years,3 and Indiana regulators added a condition that any mutually agreed reduction of more than 20% in a customer’s contracted capacity needs commission approval before it takes effect.8 AEP Ohio’s tariff includes an exit fee if a project is canceled or cannot meet its obligations.7
- Assignment. Can the agreement be assigned to a buyer of the campus, a tenant or a lender?
- Load reductions. Can contract demand be reduced, on what notice, and does a regulator have to approve it?
- Delays. What happens if the utility’s facilities are late, or the customer’s are?
- Changes in law or tariff. Does the agreement follow later tariff changes, or are terms fixed?
- Curtailment. Is any part of the load non-firm, and on what conditions can it be interrupted? See firm vs. interruptible service.
Assignment matters for land deals: a landowner or developer who signs an early agreement may want to transfer it with the site. Utilities differ on whether that is allowed and what consent it takes, so confirm it with the utility and counsel before pricing a site as “powered.”
06Rules are still moving: Texas and FERC
Statutes and federal proceedings are also setting terms. Texas Senate Bill 6, enacted in 2025, directs the Public Utility Commission of Texas to set interconnection standards for loads of 75 MW or more (or a lower threshold it chooses). The standards include a screening study fee of at least $100,000, proof of site control, financial commitments and disclosure of substantially similar service requests elsewhere in Texas.5 The PUCT adopted its implementing rule on September 18, 2026. It dropped the non-refundable per-MW interconnection fee proposed in March in favor of a flat study charge, but still requires $50,000 per MW of requested capacity to be posted as security before interconnection studies begin.11 For a 300 MW request, that is $15 million committed before the first study. See Texas Senate Bill 6.
Fig. 3Financial gates for a large load in Texas
- 01
Screening study
Fee of at least $100,000 to the utility.
- 02
Site control
Deed, qualifying lease or option.
- 03
Security posted
$50,000 per MW of requested capacity before studies.
- 04
ERCOT study
Reliability review of the request.
- 05
Agreements
Interconnection agreement, then service.
In October 2025 the Department of Energy asked FERC to assert jurisdiction over interconnection of loads above 20 MW to the transmission system and to assign full network upgrade costs to large loads, a contested expansion into an area states have traditionally regulated.12 Rather than issue one national rule, FERC on June 18, 2026 issued show cause orders directing each of the six RTOs and ISOs to justify or reform its large-load interconnection rules.13 Regional changes to study, cost and service terms could follow, so reconfirm any set of terms close to signing.
07Comparing large-load terms across sites
Tariff terms are often treated as a late-stage legal task. They belong in site comparison. A site with a lower energy rate but heavy minimum bills, high collateral and a long term can be the more expensive choice for a project with an uncertain ramp. Market structure matters too, because it changes which parts of the bill the tariff controls: see ISO and RTO markets and data center siting and electricity rates for data center sites.
- 01Identify each site’s utility and whether it has a large-load tariff or uses special contracts.
- 02Collect its terms for contract demand, minimum bills, collateral, CIAC, term and exit fees.
- 03Run the project’s base and slow-ramp cases through each set of terms.
- 04Compare capital committed before first power, not only the energy rate.
- 05Flag terms that would block assignment or financing.
For a second view on how a utility’s terms affect a parcel, you can get a site reviewed.
Common questions
What is a large-load tariff?
A utility rate schedule, approved by its regulator or governing board, that sets the prices and conditions of service for very large customers such as data centers. It typically covers demand charges, minimum demand thresholds, contract term, minimum billing demand, collateral and direct assignment of costs.1 Details vary widely by utility and state.
What is a minimum bill or take-or-pay provision?
A floor on what the customer pays, usually tied to a share of contract demand and owed even if the customer uses less power. AEP Ohio’s data center tariff sets it at 85% of subscribed demand,2 and Indiana Michigan Power’s at 80%.3 A slow ramp or tenant delay can still produce large bills, so the ramp should be realistic.
What is CIAC in utility service?
Contribution in aid of construction: a payment to the utility for facilities built mainly to serve one customer, such as a line extension or customer substation. It may be due up front, recovered through a monthly facilities charge or credited back as load grows. Virginia regulators have directed Dominion to require it for direct-connect transmission facilities serving large loads.10
Why do utilities require collateral from data centers?
Serving a large data center can require major spending on substations, lines and generation before the customer pays its first bill. Collateral, such as a letter of credit, cash deposit or parent-company credit support, protects the utility and its other customers if the project stalls or leaves early. LBNL counts it among the standard large-load protections.1
Notes
- 1.Lawrence Berkeley National Laboratory, “Rate Designs for Large Loads (webinar slides),” 2026. eta-publications.lbl.gov
- 2.POWER Magazine, “Regulator Approves AEP Ohio’s Landmark Data Center Tariff,” 2025. powermag.com
- 3.EPRI, “Summary of Indiana Michigan Power Large Load Tariff Settlement (IURC Cause No. 46097),” 2025. restservice.epri.com
- 4.Lawrence Berkeley National Laboratory, “Rate Designs for Large Loads,” 2026. eta-publications.lbl.gov
- 5.Texas Legislature, “S.B. No. 6, 89th Legislature, Regular Session (Enrolled),” 2025. capitol.texas.gov
- 6.Georgia Public Service Commission, “Media Advisory: Data Centers Rule,” 2025. psc.ga.gov
- 7.Renewable Energy World, “Ohio utility regulators approve AEP’s contested data center tariff proposal,” 2025. renewableenergyworld.com
- 8.American Electric Power, “Indiana Michigan Power Receives Order in Large Load Settlement,” 2025. aep.com
- 9.Cardinal News, “Regulators approve Dominion Energy rate increase,” 2025. cardinalnews.org
- 10.Data Center Dynamics, “Virginia regulators order Dominion Energy to directly assign transmission costs to data centers,” 2026. datacenterdynamics.com
- 11.White & Case, “PUCT sets financial commitments for data center interconnection as governor pauses permit approvals,” 2026. whitecase.com
- 12.Foley & Lardner, “DOE Proposes New Federal Standards for Interconnecting Large Loads to the Grid,” 2025. foley.com
- 13.Akin Gump Strauss Hauer & Feld, “FERC Issues Landmark Show Cause Orders on Large Load Interconnection,” 2026. akingump.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Power & interconnection
- How Much Power Does a Data Center Need?
- Transmission Voltage and Data Centers: 69 kV to 765 kV
- Substation Proximity and Capacity for Data Center Sites
- Power Timelines: Why “When” Matters as Much as “Where”
- ISOs, RTOs and Utility Territories in Data Center Siting
- On-Site Generation and Bridge Power for Data Centers
- What Is Powered Land?
- Redundant Utility Feeds and Dual Substations for Data Centers
- Behind-the-Meter vs. Front-of-the-Meter Power for Data Centers
- Microgrids and Battery Storage at Data Center Sites
- Co-Locating Data Centers With Power Plants
- Nuclear and Small Modular Reactors: Siting Considerations for Data Centers
- Renewable Energy Procurement and How It Affects Data Center Siting
- What Is a Utility Load Study for a Data Center?
- Firm vs. Interruptible Electric Service for Data Centers
- Flexible Data Center Loads and Demand Response
- PJM Capacity Prices and Data Center Load Growth
- Transformer and Switchgear Lead Times for Data Centers
- Substation Configurations for Data Center Campuses: Ring Bus, Breaker-and-a-Half and Double Bus
- Power Purchase Agreements for Data Centers: Physical, Virtual and Sleeved
- 24/7 Carbon-Free Energy and Hourly Matching for Data Centers
- Gas Turbines vs. Reciprocating Engines for Data Center On-Site Power
- Fuel Cells for Data Center Power: How They Work and Where They Fit
- NERC Reliability Standards and Large Data Center Loads: Ride-Through, Load Loss and Registration
- From Signed Agreement to Energization: The Data Center Power Timeline
- Hydropower and Data Center Siting: Public Power, Allocations and Drought Risk
- Geothermal Power for Data Centers: Enhanced Geothermal, Clean Tariffs and Siting in the West
- Surplus Interconnection Service and Retired Power Plant Sites: How Existing Grid Rights Get Reused
Guide 11 of 35 in Power & interconnection · all 242 guides · glossary · calculators
