A BlackForge Ventures company
BlackForge Data Centers

Power & interconnection

Power Timelines: Why “When” Matters as Much as “Where”

For a data center site, the date power can be delivered is often as important as how much power is available, because a campus that cannot be energized when its buyer needs it has little value. Dates are set by utility studies, required upgrades, equipment such as power transformers that took two to three years to deliver in 2025, and new transmission lines, which have averaged more than a decade to site, permit and build.12 As of October 2026, load queues are also becoming formal, with Texas studying large loads in batches and FERC reviewing how six grid operators connect loads of about 50 MW and up.34

Last reviewed · 9 min read · BlackForge Data Centers

Key takeaways

  • A site with less power available sooner can beat a site with more power later; compare sites in megawatts by year.
  • New transmission lines are usually the longest item: for lines that needed a federal environmental impact statement, the review alone averaged about 4.3 years.5
  • Power transformers took two to three years to arrive in 2025 and high-voltage breakers about 125 weeks, enough to set a date on their own.16
  • Generator queues held about 2,060 GW at the end of 2025, and the median project built that year took 61 months from request to operation.7
  • Load queues can stall too: an August 2026 Texas audit of data center requests put ERCOT’s first large-load batch study on hold.8
  • Ask what drives a utility’s date, not just what the date is.
Public data · Power trackerLarge-load power tracker39 utilities and their data center power rules, from public filings.

01Why the power date can decide a site

Data center buyers plan capacity years ahead, but they still need it on a schedule. If a utility can serve a site’s load only well after the buyer’s target date, the site may lose to a less attractive one that can be energized sooner. Some utilities now allocate capacity formally: in February 2026 Dominion Energy asked Virginia regulators to approve a large-load queue that would release capacity to new requests in clusters, matching new load to what its system can carry.9

This changes how sites should be compared. Two tracts with the same acreage near the same transmission line can have very different value if one can be served from an existing substation with modest work and the other needs a new line. The useful metric is not just megawatts, but megawatts by year: how much load can be energized in each year of the buyer’s ramp. See load ramp schedules.

Timing also affects land deals. Purchase options and lease terms need to run long enough to cover utility studies and agreements, and closing conditions are often tied to power milestones. A land contract that expires before the utility can commit to a date leaves both parties in a difficult position. Aligning option periods with a realistic power path is one of the more practical ways to keep a good site from being lost to the calendar.

02What sets the energization date

A service date is the sum of several stages, some in sequence and some in parallel. The longest chain sets the date.

Components of a large-load power timeline
ComponentWhat drives its durationRelative scale
Utility studiesStudy backlog, complexity, whether requests are groupedMonths, sometimes longer
Agreements and securityNegotiation, regulatory review where required, credit supportMonths
Customer substationDesign, equipment procurement, constructionOften paced by transformer delivery
Long-lead equipmentManufacturing slots for large transformers and breakersTwo to three years for power transformers in 20251
Network upgrades at existing substationsOutage scheduling, equipment, utility workloadOne to several years
New transmission linesRouting, easements, environmental review, state siting approval, constructionSeveral years; major lines have averaged more than a decade2

These are relative scales, not commitments; durations vary widely by utility, state and equipment market. Federal environmental reviews for lines that needed an impact statement averaged about 4.3 years between 2010 and 2020, ranging from one to 11.5 The utility’s own estimate, and the reasoning behind it, is the number to plan around.

Fig. 1Illustrative critical path for a first phase

Illustrative
  • Load studiesFeasibility, system impact and facilities studies
  • Agreements and security
  • Transformer manufactureOrdered at risk to hold a factory slot
  • Network upgradeBreaker and bus work at the utility substation
  • Customer substation build
  • Energization and ramp
0204060months
Illustrative example, not a real project. An early transformer order sets the date; two to three years for delivery was typical in 2025.1

Some of this work can overlap. Customer substation design can start while agreements are negotiated, and equipment can be reserved before final studies close, usually with money at risk. Utilities are now ordering equipment well ahead of need to secure supply, as Reuters reported in July 2026.6 Developers who sequence these steps carefully can take months off a schedule. See transformer and switchgear lead times.

03Generator queues vs. load queues

The phrase “interconnection queue” usually refers to the generator queue: the formal list of power plants and storage projects waiting to connect to the transmission grid. Those queues are governed by FERC-approved procedures and run by ISOs, RTOs or transmission providers. Lawrence Berkeley National Laboratory’s latest count shows how crowded they are and how little of what enters them gets built; active capacity fell about 10% in 2025 amid high withdrawals.7

Fig. 2The generator interconnection backlog

Generation and storage in active queues
~2,060 GW
Median request-to-operation, 2025 builds
61 months
Capacity requested 2000–2020 now online
13%
Capacity requested 2000–2020 withdrawn
75%
Lawrence Berkeley National Laboratory data through the end of 2025. Most queued capacity is never built.7

FERC’s Order No. 2023, issued in July 2023, replaced first-come, first-served serial studies with first-ready, first-served cluster studies.10 It raised site-control and deposit requirements, added withdrawal penalties, and gave transmission providers firm study deadlines, such as 150 days for an initial cluster study, with penalties of $1,000 to $2,500 per business day when studies run late.11 The D.C. Circuit upheld the rule in full on July 31, 2026.12

Generator queues matter to data centers in two ways: a project with on-site or co-located generation that exports to the grid may have to join one, and the pace of new generation affects how much capacity a region has to serve new load.

Load requests follow a separate path through the utility, described in our guide to the large-load interconnection process. That path is turning into a queue of its own. ERCOT used to study each large load on its own, so a new request could force restudies of projects already in review;13 in June 2026 the PUCT approved a batch process that starts with “Batch Zero.”3 Dominion’s proposal would put requests of about 100 MW and up into a formal queue, cap each request at 300 MW and study them in clusters.9 On June 18, 2026, FERC ordered PJM, MISO, SPP, CAISO, ISO-NE and NYISO to justify or reform their rules for large loads of about 50 MW and up connecting above 69 kV.4

Fig. 3Generator queues vs. large-load queues

FERC procedures

Generator queue

  • Run by the RTO, ISO or transmission provider
  • First-ready cluster studies under Order No. 2023
  • Deposits and withdrawal penalties
  • Matters when a project exports power

Utility and state rules

Large-load queue

  • Run by the serving utility
  • Moving from one-by-one to batch studies
  • Rules set mostly at the state level so far
  • FERC reviewing RTO rules for big loads
Simplified, as of October 2026; rules differ by region and are changing.

04What a queue position is and is not worth

Being in line is not the same as having power. A position in a utility’s large-load process or an ISO’s generator queue is valuable only if the project behind it is real and can keep its place. Order No. 2023’s deposits and withdrawal penalties were aimed at speculative generator requests, where a developer holds several positions but expects to build one.11 Treat a load queue position with the same skepticism.

  • Find out whether the position is tied to a specific site, load size and point of connection.
  • Check what milestones, deposits or security are needed to keep it.
  • Learn whether it can be transferred to a new owner, and on what terms.
  • Identify what happens if the load or schedule changes. Material changes often mean restudy.
  • Look at what is ahead in line. Earlier requests at the same substation can absorb the available capacity.
  • Check whether regulators have paused or re-sequenced the process, as Texas did with an August 2026 audit of data center requests.8

05Phased energization and bridge power

Utilities often can deliver part of a load well before all of it. An existing substation might support a first building while a new line is built for later phases. Structuring the campus around that first block of power can start revenue years earlier.

Some projects also use on-site generation as bridge power to start operations before full utility service, or to reduce the load the grid must carry at peak. BloombergNEF reports that because grid hookups can take years, developers are increasingly turning to on-site gas, lifting demand for turbines, engines, fuel cells and batteries.14 Our guide to on-site generation and bridge power covers the permitting, fuel and cost tradeoffs.

Flexibility can help timelines too. A load willing to curtail during grid emergencies, or to accept a lower firm level for a period, may be served sooner than one that requires full firm service from the first day. Google, for example, has agreed with Indiana Michigan Power and TVA to scale back machine-learning workloads at some data centers when the grid is under stress.15

Grid operators are starting to write this into their rules. In August 2026 PJM asked FERC to approve an interim service that would let new large loads of 50 MW or more energize before matching new capacity is in place, with loads that lack new supply subject to curtailment early in a shortage. It would apply to loads entering service after June 1, 2027, and PJM asked FERC to act by October 12, 2026; check whether FERC has ruled.16 Availability depends on the utility and market; see flexible data center loads.

06How to test a utility’s power date

A power date with no explanation is hard to rely on. These questions help reveal how firm it is.

  1. 01Which facilities have to be built or upgraded to serve the first phase, and which for the full build?
  2. 02Do any upgrades need a new transmission line, a new substation or state siting approval?
  3. 03Which equipment is long-lead, and has it been ordered or reserved? High-voltage breaker lead times rose from about 77 weeks in 2023 to about 125 weeks in late 2025.6
  4. 04Is the date conditional on other projects, other customers or an ISO or RTO planning process?
  5. 05What study stage is the request in, and what could change the result?
  6. 06What does the customer have to commit, and by when, to hold the date?

The answers belong in the site’s overall schedule alongside zoning, permitting and construction. Our data center site selection timeline shows how power usually sits on the critical path, and the energization timeline covers the steps after agreements are signed. A site with a documented, credible power path is also the core of what the industry calls powered land. For an outside read on a power date, you can get a site reviewed.

CalculatorIT load to grid demand →CalculatorBackup generators & fuel →

Common questions

How long does it take to get power for a data center?

It depends on what has to be built. If an existing substation can serve the load with modest work, the limits are studies, agreements and the customer substation, often paced by a transformer that took two to three years to deliver in 2025.1 If the load needs new transmission lines or major network upgrades, timelines commonly run several years, and major new lines have averaged more than a decade from siting to service.2 The utility’s study results are the reliable source.

What is an interconnection queue?

An interconnection queue is the ordered list of projects waiting to be studied and connected to the grid. The term usually means generator queues run by ISOs, RTOs or transmission providers under FERC-approved procedures, which held about 2,060 GW at the end of 2025.7 Large-load requests such as data centers increasingly move through their own queues, often studied in batches.3

Can a data center start operating before full utility power is available?

Often, yes, in phases. A utility may be able to serve a first building from existing facilities while upgrades for later phases are built. Some projects also use on-site gas generation as bridge power until utility service catches up, a practice BloombergNEF says is growing.14 Either path needs planning from the start, including air permits and fuel supply for generation.

Why do large power transformers affect data center timelines?

Large power transformers are built to order and factory capacity is limited, so lead times of two to three years can set a project’s energization date by themselves.1 High-voltage breakers, at about 125 weeks in late 2025, are similar.6 Ordering early, and confirming the utility has done the same, is one of the best ways to protect a power date.

What is ERCOT’s Batch Zero?

Batch Zero is the first group study under ERCOT’s new process for connecting large loads in batches rather than one at a time, which the PUCT approved in June 2026.3 In August 2026 the governor directed the PUCT and ERCOT to audit data centers in the interconnection pipeline, and the Batch Zero study was put on hold while the audit runs, as of the latest reporting we found.8 Check ERCOT’s current notices, and our guide to Texas Senate Bill 6, before relying on any date.

Notes

  1. 1.Wood Mackenzie and American Clean Power Association, “Making the Connection: Executive Summary,” 2025. powermag.com
  2. 2.Atlantic Council, “Prospects for Reform in US Grid Permitting and Planning,” 2024. atlanticcouncil.tv
  3. 3.Electric Reliability Council of Texas, “Trending Topics: ERCOT’s New Batch Connection Process for Large Electricity Users,” 2026. ercot.com
  4. 4.Orrick, “FERC Show Cause Orders Signal Broad Reform to Large Load Interconnection Policies,” 2026. orrick.com
  5. 5.Clean Air Task Force, “From Decades to Years: Does CITAP Program Progress Towards Faster Transmission Projects?,” 2024. catf.us
  6. 6.Reuters, via Kitco News, “US Power Companies Scramble to Secure Equipment as Surging Data Center Demand Strains Supplies,” 2026. kitco.com
  7. 7.Lawrence Berkeley National Laboratory, “Queued Up: 2026 Edition,” 2026. eta-publications.lbl.gov
  8. 8.Greenberg Traurig, “Texas Imposes New Audit Requirement for Data Center Projects, Delaying ERCOT Interconnection Reviews,” 2026. gtlaw.com
  9. 9.Data Center Dynamics, “Dominion Files Large Load Connection Queue Plan With State Regulators,” 2026. datacenterdynamics.com
  10. 10.Federal Energy Regulatory Commission, “Explainer on the Interconnection Final Rule,” 2023. ferc.gov
  11. 11.Orrick, “FERC Finalizes Rule Adopting Interconnection Reforms,” 2023. orrick.com
  12. 12.White & Case, “DC Circuit Upholds Interconnection Reforms of FERC Order No. 2023,” 2026. whitecase.com
  13. 13.Lloyd Gosselink Rochelle & Townsend, “ERCOT Develops New Batch Study Process for Large Load Interconnections,” n.d. lglawfirm.com
  14. 14.BloombergNEF, “Gas Is Letting Data Centers Grow Beyond the Grid,” n.d. about.bnef.com
  15. 15.Data Center Dynamics, “Google Partners With I&M and TVA to Expand Use of Demand Response at Its AI Data Centers,” 2025. datacenterdynamics.com
  16. 16.T&D World, “PJM Board Seeks FERC Approval on Data Center Curtailments Amid Grid Capacity Concerns,” 2026. tdworld.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Terms in this guide

Related guides

More in Power & interconnection

Guide 5 of 35 in Power & interconnection · all 242 guides · glossary · calculators