Key takeaways
- Utility interconnection is usually the longest single phase; Google has said utilities in many regions quote four to ten years to connect.3
- Screening and shortlisting can move quickly; approvals and power cannot be rushed.
- Phases overlap: diligence, utility studies and entitlement often run at the same time.
- Equipment can set the date too: large power transformers averaged about 128 weeks from order to delivery in Wood Mackenzie’s 2025 survey.4
- Rules can change mid-search, as when Texas’s governor ordered an August 2026 audit of data centers in ERCOT’s queue before approving more.5
- A delay in one critical phase pushes the energization date, no matter how fast the others move.
01The phases at a glance
Every project follows a similar sequence, though the time each phase takes varies a great deal. The table below describes the phases and what usually sets their pace. Durations are left out of the table on purpose: the same phase can be quick in one market and slow in another.
| Phase | What happens | What controls the pace |
|---|---|---|
| 1. Requirements | Define load, phasing, acreage, latency, cooling and target date | Internal decisions and business case |
| 2. Market selection | Choose regions or utility territories to search | Power availability, incentives, network and user needs |
| 3. Site screening | Filter candidate parcels, then shortlist | Data quality and how fast early outreach gets answers |
| 4. Site control | LOI, then option or purchase agreement | Negotiation and number of owners |
| 5. Feasibility and diligence | Survey, title, environmental, geotech, utility and zoning work | Seasonal field work, agency response times |
| 6. Utility interconnection | Load studies, facilities agreements, upgrades | Utility study process and upgrade construction |
| 7. Entitlement | Rezoning, special use, site plan and permits | Local approval process and public hearings |
| 8. Design and construction | Site work, substation, buildings, commissioning | Equipment lead times, labor and weather |
Fig. 1One illustrative schedule for a large campus
Illustrative- Requirements and markets
- Screening and shortlist
- Site controlLOI, then option or purchase agreement
- DiligenceSurvey, title, Phase I ESA, wetlands, geotech
- Utility studies and upgradesLoad study, agreements, substation and line work
- EntitlementRezoning or special use, then site plan
- Design and construction
- Commissioning and energization
02Requirements and market selection
The search starts inside the organization. The team defines the load, how it will ramp, the land needed, the cooling approach, latency needs and the date the first capacity must be online. Vague requirements slow everything later, because sites get screened against the wrong thresholds.
Requirements also need agreement across teams. Real estate, engineering, energy and finance groups often weigh factors differently. Settling the must-haves and the trade-offs before the search begins saves time when choosing between shortlisted sites.
Market selection then narrows the search to regions or utility territories. Teams weigh power availability, the regional grid and market structure, tax incentives, fiber networks, climate and proximity to users. For AI training campuses, power often outweighs location. For colocation and inference, proximity to users and network hubs matters more.
It helps to understand the grid structure in each candidate market. Whether a region sits inside an ISO or RTO such as PJM, ERCOT or MISO, or in a vertically integrated utility territory, affects who studies the load, how upgrades are assigned and how long the process tends to take. Our guide to ISOs, RTOs and utility territories explains the differences.
03Screening and securing site control
Screening filters parcels by acreage, power proximity, environmental constraints and zoning, then shortlists the strongest. With good data, the desktop work can move in weeks. Early outreach to utilities and local officials takes longer and often changes the shortlist. Our guide to desktop screening vs. field assessment covers where desk work ends and site work begins.
Site control comes next. A letter of intent sets the key terms, followed by an option or purchase agreement. A single owner can move quickly. A campus assembled from several owners takes longer, and each additional owner adds negotiation time and holdout risk.
The control period has to be long enough for what follows. Buyers usually negotiate option or diligence periods that cover utility studies and zoning, with paid extensions if those run long. Sellers push back on open-ended control, so the length and cost of that period is often the hardest term to settle. See due diligence periods and purchase contingencies.
04Diligence and utility interconnection
Diligence confirms title, survey, environmental and physical conditions, and zoning. Some items, like a Phase I ESA, are routine but have a shelf life. To support federal landowner liability protections, the inquiry must be done within one year before acquisition, and key parts, including the site visit, records review and interviews, must be completed or updated within 180 days before it.6 On a long option, that often means refreshing the Phase I before closing. Other items, like wetland delineation, depend on the season and agency workload. See Phase I environmental site assessments.
Utility interconnection is usually the longest phase. The utility studies the load, identifies upgrades and sets terms through facilities or service agreements. If new substations or transmission lines are needed, they have their own design, permitting and construction schedules. JLL’s 2026 outlook, as reported in trade press, put the average wait for a new U.S. grid connection at about four years, and about seven years for a 100 MW request in Northern Virginia.1 Our guides to the large-load interconnection process and power timelines and interconnection queues cover the details.
Fig. 2What sets the pace, 2025–2026
- average wait for a new U.S. grid connection
- ~4 years
- typical grid wait in Northern Virginia
- ~7 years
- average large power transformer delivery
- 128 weeks
- of projects hit by opposition, Q1 2026
- ~$130B
The rules are also moving. In August 2026, Texas Governor Greg Abbott directed that data centers in ERCOT’s interconnection process be verified before more are approved, and ERCOT said it planned to finish that audit by December.58 At the federal level, FERC’s June 2026 show-cause orders required all six FERC-jurisdictional regional grid operators to justify or reform their large-load interconnection rules,9 and by late August most had asked FERC to pause their cases for up to 90 days rather than file revised tariffs by the mid-August deadline.10 Assume the process may change mid-project.
05Entitlement and permitting
Where data centers are permitted by right, entitlement may be mostly site plan review and building permits. Where rezoning or a special use permit is needed, public hearings and potential appeals add time and uncertainty. That line can move. On March 18, 2025, Loudoun County, Virginia, ended by-right approval for data centers,11 so new projects need staff analysis and public hearings before the planning commission and the board, not just administrative site plan review.12 On September 15, 2026, the board voted 7-1-1 to pause action for up to 12 months on new data center and substation applications that need legislative approval while it rewrites its standards; as of early October, the formal resolution was set for the board’s October 20 meeting.2
Opposition is a schedule risk in its own right. Data Center Watch counted at least 75 U.S. projects worth about $130 billion blocked or delayed by local opposition in the first quarter of 2026, the most in any quarter it has tracked.7 Check for moratoriums and local restrictions before committing to a date.
State and federal permits run alongside local approvals. Wetland and stream impacts may fit one of the Army Corps’ nationwide permits, a streamlined Clean Water Act path that was reissued effective March 15, 2026, while larger impacts need an individual permit and more time.13 FAA review of tall structures and cranes near airports also runs in parallel. See the data center permitting process for the step-by-step sequence.
06Design, construction and energization
Once power and approvals are in hand, construction begins. Site work, the on-site substation, buildings and mechanical and electrical systems proceed in parallel where possible. Long-lead equipment can control the schedule: large power transformers averaged about 128 weeks from order to delivery in Wood Mackenzie’s 2025 survey, so they, along with switchgear and generators, are often ordered well before construction starts.4 See transformer and switchgear lead times.
The building is often not the slowest part. Microsoft’s data center building in Donnacona, Quebec, was finished about 21 months after work began in February 2024, while the site’s substation was scheduled for the second half of 2026.14 At campus scale, Epoch AI found that large builds usually take one to four years from groundbreaking to 1 GW of facility power.15
Many campuses are designed for phased delivery. The first building can move ahead on initial utility capacity while later phases wait for larger upgrades. Phasing lets the schedule start earlier, but it requires a site plan and utility agreement that allow expansion without redesign.
Energization of the first phase is the milestone that matters most. Later phases may follow as load grows, often on a schedule tied to utility upgrades. Our guide to the energization timeline covers the steps from signed agreement to first power.
07What usually causes delays
Delays tend to come from the same few sources. Most are visible early if someone looks for them.
- Power: utility studies take longer than expected, upgrades grow in scope, other large loads get ahead in line, or the rules change mid-process.
- Approvals: a site needs rezoning or a special use permit, hearings are continued, or approvals are appealed.
- Environmental: wetland delineation must wait for the right season, or a Phase I ESA leads to a Phase II.
- Land: an owner in a multi-parcel assembly holds out, or title issues need curing.
- Equipment: long-lead transformers, switchgear and generators arrive later than planned.
- Scope changes: the load or design changes partway through and studies must be redone.
Slippage is common even late in the process. Energy-intelligence firm Currence expected a third to half of the large data center capacity slated for 2026 to slip past year-end, and counted only about 5 GW of roughly 16 GW due that year as physically under construction.16
Fig. 3Which constraint sets the schedule
Power and approvals
Slowest case; both must clear before construction.
Approvals lead
Hearings, appeals and conditions set the date.
Power leads
Utility studies and upgrades set the date.
Equipment and build
Fastest case; lead times and labor set the pace.
Constrained ← Grid capacity → Available
08How teams shorten the timeline
- Start utility conversations during screening and submit load requests as early as the utility allows.
- Run diligence, utility studies and entitlement in parallel rather than in sequence.
- Favor sites with by-right zoning or supportive local plans.
- Favor single-owner or already-assembled sites.
- Consider sites with existing substation capacity or land the owner has already positioned with the utility.
- Order long-lead electrical equipment early.
Each of these moves trades money or flexibility for time. Early load requests and parallel studies spend money on sites that may not proceed, and early equipment orders commit capital before approvals are final. Decide in advance which risks are worth paying to retire early.
When we run national site searches, the schedule is usually set by the slowest of three items: power, approvals and land assembly. Knowing which of those is the bottleneck on each site is the most useful timeline insight.
Common questions
How long does it take to find a data center site?
Finding and shortlisting candidates can move in weeks to a few months with clear requirements and good data. Securing control, completing diligence, obtaining power commitments and winning approvals usually take much longer. The overall time from search to energization varies widely by utility, jurisdiction and project size, and power availability is usually the deciding factor.
Why does power take so long for data center sites?
Large loads can require the utility to study its network, build or expand substations and sometimes add or upgrade transmission lines. Each of those steps involves engineering, regulatory review, land rights and construction, and other large projects may already be waiting for the same capacity. Google has said that one utility estimated 12 years for the study phase alone.3 In areas with spare capacity the process can be shorter, but it is rarely quick for very large campuses.
Can site selection phases run at the same time?
Yes, and on most successful projects they do. Utility conversations often start during screening, and diligence, utility studies and entitlement commonly run in parallel once a site is under control. Watch for work that expires: a Phase I ESA relied on for liability protection needs key parts updated if they are more than 180 days old at closing.6 Teams manage the cost of parallel work by sequencing the cheapest checks with the most knockout risk first.
When should a developer contact the utility about a new site?
As early as possible, often during screening and before signing a purchase or option agreement. Informal conversations can show whether capacity is likely and roughly when, which helps rank sites. Formal load or interconnection requests usually need site control and more detail, but starting the relationship early shortens the overall timeline and avoids pursuing sites the utility cannot serve on the needed schedule. See our guide to utility load studies.
Notes
- 1.Electrical Contractor Magazine, “How Long Does It Take to Power a Data Center?,” 2026. ecmag.com
- 2.WJLA, “Loudoun County votes to pause new data center applications,” 2026. wjla.com
- 3.Network World, “Google warns transmission delays are now the biggest threat to data center expansion,” 2026. networkworld.com
- 4.pv magazine USA, “U.S. transformer market faces severe supply constraints as lead times extend to four years,” 2026. pv-magazine-usa.com
- 5.Texas Standard, “Gov. Greg Abbott pauses new data centers until energy, water usage audit is completed,” 2026. texasstandard.org
- 6.Electronic Code of Federal Regulations, “40 CFR 312.20: All appropriate inquiries,” n.d. ecfr.gov
- 7.Data Center Watch, “Q1 2026: Data Center Watch Report,” 2026. datacenterwatch.org
- 8.Texas Public Radio, “ERCOT says it plans to complete governor’s data center audit by December,” 2026. tpr.org
- 9.Foley & Lardner, “FERC Issues Six Tailored “Show Cause” Orders to Accelerate Large Load Interconnection,” 2026. foley.com
- 10.Capacity, “Five of six US grid operators seek delay on FERC’s data centre power deadline,” 2026. capacityglobal.com
- 11.Loudoun County, Virginia, “Data Center Standards & Locations,” n.d. loudoun.gov
- 12.McGuireWoods, “Loudoun County Eliminates By-Right Use for Data Centers, Increasing Development Hurdles,” 2025. mcguirewoods.com
- 13.Sidley Austin, “U.S. Army Corps of Engineers Finalizes 2026 Nationwide Permit Reissuance and Modifications,” 2026. environmentalhealthsafetybrief.sidley.com
- 14.Microsoft, “Donnacona datacentre construction update,” 2025. local.microsoft.com
- 15.Epoch AI, “Build times for gigawatt-scale data centers can be 2 years or less,” n.d. epochai.substack.com
- 16.Network World, “Up to 50% of data center capacity slated for 2026 could be delayed,” 2026. networkworld.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Feasibility, diligence & deals
- Data Center Site Due Diligence Checklist
- Why Data Center Sites Fail: Common Red Flags
- How to Screen a Land Portfolio for Data Center Potential
- Selling or Leasing Land to a Data Center Developer
- Desktop Screening vs. Field Assessment for Data Center Sites
- How to Read a Data Center Feasibility Report
- Site Scoring and Weighting Methods for Data Center Selection
- GIS Data Sources for Data Center Site Selection: What Each Layer Shows
- Letters of Intent for Data Center Land Deals: Binding Terms, Exclusivity and Pitfalls
- Utility Will-Serve Letters: What They Mean and What They Don’t
- How Developers Underwrite Data Center Sites
- Data Center Construction Costs per MW and the Site Factors That Drive Them
- Due Diligence Periods and Purchase Contingencies for Data Center Land
- Confidentiality, NDAs and Code Names in Data Center Site Searches
- What to Check on a Data Center Site Visit: A Field Checklist
- Public Data Sources for Power Capacity: EIA, FERC, OASIS, Queues and Hosting Maps
Guide 6 of 18 in Feasibility, diligence & deals · all 242 guides · glossary · calculators
