Key takeaways
- EIA-860 is a census of every U.S. generator of 1 MW or more, with planned additions and retirements; EIA-861 lists the counties each utility serves.12
- FERC Form 715 power flow cases are the closest public view of transmission capacity, but they are Critical Energy Infrastructure Information and need a request.35
- Interconnection queues show competition for the grid: about 2,061 GW of capacity was waiting at the end of 2025, and only 13% of capacity requested in 2000–2020 reached operation.6
- Load forecasts move with data center requests. PJM’s 2026 forecast lowered near-term peaks partly because it vetted large-load requests more closely.7
- Hosting capacity maps exist in 26 states plus D.C. and Puerto Rico, mostly for distributed generation, and have had accuracy problems.48
01What public data can and cannot tell you
The question a landowner or developer wants answered is simple: how much contract demand can this site get, and when? No public source answers it. Available capacity at a substation depends on the utility’s internal studies, other customers’ commitments and planned upgrades, and utilities treat much of that as confidential. What public data can do is tell you which utility serves the land, what transmission and generation are nearby, how crowded the region’s queue is, and how fast the planning authority expects load to grow. That is enough to rank sites and to ask the utility sharper questions.
The sources fall into layers, from bulk generation down to the distribution feeder. Mapping layers such as transmission lines and substation points are covered in our guide to GIS data sources; this guide focuses on the datasets that speak to capacity.
Fig. 1Public power data, from grid to feeder
- 01Generation (EIA-860, 860M)Plants, capacity, planned additions and retirements
- 02Utilities (EIA-861, FERC Form 1)Service territory, sales, transmission and substation schedules
- 03Transmission planning (FERC 715)Power flow base cases, ratings, planning criteria
- 04Market signals (OASIS, queues, forecasts)Transfer capability, queue backlog, load growth
- 05Distribution (hosting capacity maps)Feeder-level estimates where published
02EIA-860 and EIA-861: generators and utility territories
Form EIA-860 is a mandatory annual census of every existing and planned U.S. generating facility with at least 1 MW of nameplate capacity, including plans for new plants over a ten-year horizon.1 EIA publishes the detailed data as Excel files containing nearly everything on the form except tested heat rates and construction costs of new units.9 For site work, the useful fields are plant location, nameplate capacity, the transmission or distribution owner, and planned retirement dates. A retiring plant can mean a strong interconnection point with headroom; see our guide to surplus interconnection and retired plant sites.
The annual files drop retired units in later years, so use the monthly EIA-860M for retirements; it has a tab listing utility-scale generators retired since 2002.910 EIA also cautions that planned addition dates often change and that the 860M is not a forecast.10
Form EIA-861 covers utilities rather than plants. Its service territory file lists the counties in each state where a utility has distribution equipment, and its sales file reports revenue, megawatt-hours and customer counts by state, sector and balancing authority.2 That makes it the quickest way to identify which utilities may serve a county, though county-level territory is coarse and boundaries inside a county need the utility’s own map; see utility service territory. As of October 2026, EIA had posted early-release 2025 data in August with final files scheduled for October.2 EIA has used the same sales data to show commercial electricity sales soaring in Virginia because of data centers.11
03FERC Form 1 and Form 715: transmission assets and planning models
FERC Form 1 is the annual financial and operating report of major investor-owned electric utilities. It is now filed in XBRL, and FERC also offers older database files for report years 1994 through 2020.12 Most of it is accounting, but a few schedules matter for siting: Transmission Line Statistics, Transmission Lines Added During the Year, and Substations, which in recent filings appear on pages 422–427.13 The substation schedule gives an inventory of the filer’s substations. It does not show loading or committed capacity, and cooperative and municipal utilities generally do not file it.
FERC Form 715 is more technical and more useful. Utilities operating integrated transmission facilities at 100 kV or above must file it, and Part 2 contains solved power flow base cases in standard formats (PSS/E, GE PSLF or PowerWorld), with forward-looking cases such as one-, two-, five- and ten-year summer and winter peaks.3 Utilities in a regional planning process can have the regional organization file the cases.3 FERC treats Parts 2 through 6 as Critical Energy Infrastructure Information (CEII), so you have to request access.3 FERC charges no fee for CEII requests and says they usually carry less burden and a better chance of success than FOIA requests.5
04OASIS and available transfer capability
Every transmission provider under FERC open access rules posts information on an Open Access Same-Time Information System (OASIS), so that all users see it at the same time; postings include notice of curtailments and the reason a transaction could not be completed.14 OASIS also carries available transfer capability (ATC) on transmission paths, along with the provider’s tariff, business practices and study reports.
For a data center, OASIS is indirect evidence. ATC measures how much additional power can be moved across a path for transmission service, not how much load a specific substation can serve. But frequent curtailments or near-zero ATC on paths into a load pocket suggest congestion that a large new load will make worse. Many providers also post system impact and facilities studies on OASIS, which can reveal upgrade costs and timelines on nearby requests. Our guide to transmission upgrades and cost allocation explains how those costs get assigned.
05Interconnection queues and load forecasts
ISO and RTO generator interconnection queues are public, and Berkeley Lab compiles them nationally. Its 2026 edition counted roughly 2,061 GW of capacity actively seeking interconnection at the end of 2025; more than 750 GW withdrew during the year and about 600 GW of new requests arrived.6 Only about 13% of the capacity that requested interconnection from 2000 to 2020 reached commercial operation.6 The prior edition found that the median time from request to operation had more than doubled, to over four years for projects built in 2018–2024.15
Fig. 2U.S. interconnection queues, end of 2025
For a load project, queue data helps two ways. Generation projects queued near a site suggest where transmission is being studied and upgraded, and a large planned plant close by can be a useful partner. Heavy queues also mean slow studies. See power timelines and interconnection queues.
Load forecasts are the other public signal. PJM’s 2026 long-term forecast projected a summer peak of about 222,000 MW in 2036, growing about 3.6% a year over ten years, while lowering near-term peaks through 2032 partly through improved vetting of data center and large-load adjustments.7 The vetting matters: Maryland’s Office of People’s Counsel calculated that utilities’ requested large-load adjustments for 2028 rose from about 19 GW in the 2025 forecast to 32 GW in the 2026 requests.16 Forecast filings and stakeholder letters often name the zones where large loads cluster, which tells you where your request will compete.
06Hosting capacity maps
Hosting capacity maps estimate how much generation or load a distribution feeder can take without upgrades. The Department of Energy’s atlas, updated in July 2025 with data as of May 2024, listed 58 utilities and state agencies publishing maps in 26 states, Washington, D.C., and Puerto Rico, and noted that some utilities publish load-related maps.4 Most maps were built for rooftop and community solar, and coverage within a state can be partial.4
Accuracy is a known issue. Pacific Gas and Electric’s first map showed little or no room for new solar on 80% of its feeders, results the utility later conceded were erroneous.8 Even accurate maps describe distribution feeders, which are far smaller than a campus load. A 100 MW campus will connect at transmission voltage through a dedicated substation, so a feeder map is useful mainly for small edge sites, construction power or an early phase.
Fig. 3Open, restricted and utility-only data
Start here
Open download
- EIA-860, 860M and 861
- FERC Form 1 filings
- ISO queues and load forecasts
- Hosting capacity maps
Request required
- FERC Form 715 base cases (CEII)
- Some ISO planning models
- Detailed study reports on OASIS
Utility only
- Substation loading and commitments
- Other customers’ load requests
- Load study results for your site
07Putting the sources together
- 01Use EIA-861 and the utility’s territory map to confirm who serves the parcel.
- 02Pull EIA-860 plants and FERC Form 1 substations within a reasonable radius, and flag planned retirements.
- 03Check the regional queue and OASIS postings for nearby generation and transmission studies.
- 04Read the latest load forecast for the zone, including large-load adjustments.
- 05If the site still looks promising, request Form 715 cases or hire an engineer who has them.
- 06Then ask the utility directly, through a capacity inquiry or a formal load study.
Public data is a filter, not an answer. Its limits are lag (annual data can be a year or more old), aggregation (county territories, system-wide forecasts) and access (the most useful models are restricted). A utility will-serve letter or study result outranks any public dataset. BlackForge uses these sources in its methodology to screen sites before the utility conversation; you can get a site reviewed or explore our tools.
Common questions
Is there a public map of available grid capacity for data centers?
Not for transmission-scale loads. Hosting capacity maps exist in 26 states plus D.C. and Puerto Rico but mostly cover distribution feeders and distributed generation.4 Transmission capacity for a large load comes only from utility studies.
How do I get FERC Form 715 power flow cases?
File a CEII request with FERC, or with the regional planning organization that submitted the cases.3 FERC charges no fee for CEII requests.5 You will need power systems software and an engineer to use the files.
Does EIA data show substations?
Not directly. EIA-860 covers generators and EIA-861 covers utilities, sales and service territory.12 Substation schedules appear in FERC Form 1 for utilities that file it.13
How current is interconnection queue data?
ISO queue pages update often, but national compilations lag. Berkeley Lab’s 2026 edition, published in mid-2026, reflects queues as of the end of 2025.6
Notes
- 1.U.S. Energy Information Administration, “Electric Power Annual Technical Notes,” n.d. eia.gov
- 2.U.S. Energy Information Administration, “Annual Electric Power Industry Report, Form EIA-861 detailed data files,” 2026. eia.gov
- 3.Federal Energy Regulatory Commission, “Form No. 715 - Annual Transmission Planning and Evaluation Report: Filing Instructions,” n.d. ferc.gov
- 4.U.S. Department of Energy, “U.S. Atlas of Electric Distribution System Hosting Capacity Maps,” 2025. energy.gov
- 5.Federal Energy Regulatory Commission, “Critical Energy/Electric Infrastructure Information (CEII),” n.d. ferc.gov
- 6.Lawrence Berkeley National Laboratory, “Queued Up: 2026 Edition,” 2026. eta-publications.lbl.gov
- 7.American Public Power Association, “PJM’s updated 20-year forecast continues to see significant long-term load growth, slightly decreases,” 2026. publicpower.org
- 8.pv magazine USA, “Solar hosting capacity maps must be accurate to be useful,” 2020. pv-magazine-usa.com
- 9.U.S. Energy Information Administration, “A Guide to EIA Electric Power Data,” 2018. eia.gov
- 10.U.S. Energy Information Administration, “Resource Advisory: Understanding electricity generation capacity in the United States,” 2025. eia.gov
- 11.U.S. Energy Information Administration, “Commercial electricity sales have soared in Virginia, driven by data centers,” 2026. eia.gov
- 12.Federal Energy Regulatory Commission, “Form 1 - Electric Utility Annual Report,” n.d. ferc.gov
- 13.Public Service Electric and Gas Company, “2023 FERC Form 1,” 2024. nj.pseg.com
- 14.Federal Energy Regulatory Commission, “Open Access Same-Time Information System, Order No. 605,” n.d. ferc.gov
- 15.Lawrence Berkeley National Laboratory, “Queued Up: 2025 Edition, Characteristics of Power Plants Seeking Transmission Interconnection As of the End of 2024,” 2025. emp.lbl.gov
- 16.Maryland Office of People’s Counsel (via PJM), “Letter re large load adjustments for the 2026 load forecast,” 2025. pjm.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Related guides
More in Feasibility, diligence & deals
- What Does a Data Center Feasibility Study Cover?
- Data Center Site Due Diligence Checklist
- Why Data Center Sites Fail: Common Red Flags
- How to Screen a Land Portfolio for Data Center Potential
- Selling or Leasing Land to a Data Center Developer
- How Long Does Data Center Site Selection Take?
- Desktop Screening vs. Field Assessment for Data Center Sites
- How to Read a Data Center Feasibility Report
- Site Scoring and Weighting Methods for Data Center Selection
- Letters of Intent for Data Center Land Deals: Binding Terms, Exclusivity and Pitfalls
- How Developers Underwrite Data Center Sites
- Data Center Construction Costs per MW and the Site Factors That Drive Them
- Due Diligence Periods and Purchase Contingencies for Data Center Land
- Confidentiality, NDAs and Code Names in Data Center Site Searches
- What to Check on a Data Center Site Visit: A Field Checklist