Key takeaways
- Sole-use (direct-assignment) facilities are usually charged to the customer; network upgrades that serve all grid users have mostly been recovered through rates.
- In seven PJM states, more than 95% of 2024 data center connection projects passed their full cost to local ratepayers, by one advocacy group’s count.2
- Pennsylvania’s 2026 model tariff charges large loads for upgrades they cause even if others benefit, and Virginia has ordered Dominion to assign direct-connect costs to the loads served.34
- Direct assignment alone does not end cost shifts; ongoing network transmission charges matter too.6
- FERC’s June 2026 show cause orders target large-load cost shifts, and PJM’s response is due November 16, 2026.57
- Upgrade cost and timing often decide between otherwise similar sites.
01Why serving a data center often requires transmission upgrades
A large data center can add hundreds of megawatts at a single point on the grid, and loads above roughly 20 MW commonly connect at transmission voltage.8 Even where a high-voltage line runs past the site, the system around it was planned for existing loads. Load studies test whether it can carry the new demand normally and with a major line or transformer out of service; Southwest Power Pool’s delivery point studies, for example, compare cases with and without the new load and attribute to it only the overloads and voltage violations it causes.9 Where it falls short, upgrades are needed.
- New or expanded substations and switching stations.
- New transmission lines, or rebuilding existing lines with larger conductors.
- Additional transformers at existing substations.
- Breakers, protection and control changes at substations miles from the site.
- Voltage support equipment where a large load weakens local voltage.
Network upgrades usually surface in the system impact study, and the customer may be asked to pay for them on top of its own interconnection facilities.8 The sums are large: the Union of Concerned Scientists (UCS) found a single data center connection in PJM often costs $25 million to $100 million.2 See the large-load interconnection process and utility load studies.
Fig. 1From load request to cost assignment
- 01
Load request
Location, peak MW, ramp schedule and site control.
- 02
System studies
Normal and contingency cases, with and without the load.
- 03
Upgrades identified
Fixes for the overloads and voltage problems the load causes.
- 04
Classification
Sole-use facility or network upgrade.
- 05
Cost assignment
CIAC, a facilities charge, rates or a split.
- 06
Agreement
Costs, security and schedule set in the service agreement.
02Direct-assignment facilities vs. network upgrades
Most cost allocation starts with one question: who benefits? Open access transmission tariffs, which follow FERC’s pro forma, draw the line. Direct assignment facilities are built by the transmission provider for the sole use or benefit of one customer and are specified in its service agreement; network upgrades are additions integrated with the overall transmission system for the general benefit of all its users.1
| Category | Examples | Who usually pays |
|---|---|---|
| Customer-owned facilities | Customer substation, on-site distribution, transformers on the customer side | Customer, directly |
| Direct-assignment (sole-use) facilities | Line extension or tap to the site, dedicated switching station bays | Customer, through CIAC or a facilities charge |
| Network upgrades | Reconductored lines, new regional lines, transformer additions at shared substations | Varies: customer, all ratepayers or a split |
| Upgrades already planned | Projects in the utility or regional plan for other reasons | Usually recovered through rates, though a new load can change their timing |
The boundaries are not fixed. A switching station built for one campus may count as a network facility if it also serves the grid, and a sole-use line extension may become shared if others connect. Classifications are often negotiated, can be reviewed by regulators and are being redrawn by newer rules, covered below. For payment mechanics, see contributions in aid of construction.
03Participant funding vs. rate-based recovery
There are two broad ways to pay for upgrades, and many utilities use a mix.
Participant funding
Under participant funding, the customer that causes the upgrade pays for it, either up front or over time through a dedicated charge. The logic is cost causation: other customers should not carry costs for facilities they did not need. It is common for direct-assignment facilities and is increasingly applied to network upgrades driven by very large loads.3
Rate-based recovery
Under rate-based recovery, the utility builds the upgrade, adds it to its rate base and recovers the cost from all customers over the life of the asset, on the logic that network upgrades serve the whole system and a large customer pays its share through its bills. This has been the default for ordinary load growth, and in PJM it has often covered the connections built for data centers too.2 See also data centers and electricity ratepayers.
Hybrids
Hybrids are common: a utility may rate-base an upgrade but require collateral or a minimum bill that covers it if the load never arrives, or credit back part of an upfront payment as the load generates revenue. See large-load tariffs and electric service agreements.
Direct assignment alone does not settle it, because a load also pays ongoing network transmission charges. A March 2026 Concentric Energy Advisors analysis, prepared for the utility holding company Exelon, argues that charging upgrades to large loads while relieving them of network integration transmission service charges could shift $33–47 billion (present value, over 30 years) to other customers for PJM large loads expected from 2025 to 2030.6
Fig. 2Three ways to pay for a network upgrade
Growing for large loads
Participant funding
- The customer that causes the upgrade pays
- Paid up front as CIAC or over time
- Protects other customers if the load leaves
- Adds capital needed before first power
Traditional default
Rate-based recovery
- Utility adds the upgrade to rate base
- All customers pay over the asset’s life
- The large load pays its share through its bills
- Others carry the cost if the load shrinks
Hybrid
- Rates fund the upgrade; the customer backs it
- Collateral or a minimum bill covers the risk
- Upfront payments may be credited as load grows
- Terms set in the tariff or service agreement
04Who sets the rules, and why they vary
Transmission cost allocation sits where state and federal authority meet. State commissions generally regulate retail service, including service to data centers, while public power utilities and cooperatives answer to their own boards. FERC regulates interstate transmission outside ERCOT, and in ISO and RTO regions, regional planning decides how some upgrades are shared. The boundary for large loads is now disputed, with state regulators opposing federal authority over connecting retail load.10
- Vertically integrated utilities apply state-approved tariffs and line extension rules. Georgia’s January 2025 rule lets Georgia Power bill new customers above 100 MW for transmission and distribution costs incurred as construction progresses.11
- In PJM, UCS says data center connections fall into a regulatory gap, with costs typically spread across every customer in the utility’s footprint.2 Regional projects are shared across states; Maryland’s ratepayer advocate has told FERC that Maryland customers will pay about $1.6 billion over ten years for lines built mainly for data centers elsewhere.12
- In ERCOT, transmission costs are charged to distribution utilities based on demand in four summer peak intervals (4CP), which large customers can lower by curtailing at those peaks.13
- Municipal utilities and cooperatives set their own policies and may rely on a separate transmission provider or generation and transmission cooperative.
Fig. 3Data center connection costs in PJM, 2024
- connection costs in seven PJM states
- $4.3B
- direct links to high-voltage lines
- 130
- passed full cost to local ratepayers
- 95%+
- in Virginia, the largest state total
- $1.9B
05How the rules are changing (as of October 2026)
In October 2025 the Department of Energy directed FERC to consider rules for connecting loads above 20 MW to the transmission system,10 proposing that large loads bear 100% of network upgrade costs.14 On June 18, 2026 FERC instead ordered PJM, MISO, SPP, CAISO, ISO-NE and NYISO to show cause, finding their tariffs may not address the network upgrade costs and cost shifts large loads present; its PJM and SPP orders pressed for upgrade cost transparency and cost recovery agreements that put upgrade risk on large loads.5 At PJM’s request, FERC paused its case; PJM’s response is due November 16, 2026.7
Several states have already acted:
- Virginia. In Dominion’s Rider T1 transmission case, the State Corporation Commission ordered Dominion to draft, within about 90 days, a tariff assigning the cost of “direct connect” transmission facilities to the new or growing large loads they serve. Dominion had reported that about half of its roughly 200 planned transmission projects were driven solely by data centers.4
- Pennsylvania. The PUC’s May 2026 model tariff is a nonbinding template for customers above 50 MW, or 100 MW or more in aggregate.15 It charges them as CIAC for upgrades that would not be needed but for their load, even if others benefit, unless the work is already in an approved long-term infrastructure plan.3
- Texas. Under Senate Bill 6, the PUCT adopted a rule on September 18, 2026 that standardizes capital contributions and financial security for ERCOT loads of 75 MW or more.16 A March 2026 PUCT draft report on transmission cost recovery floated ending interconnection cost allowances and possibly requiring CIAC for system upgrades, and the commission must amend its rules by December 31, 2026.13 See Texas Senate Bill 6.
Rules can change after a site is chosen, so treat cost allocation as open until the service agreement is signed.
06How upgrade costs affect site selection
Upgrade cost and timing are among the clearest differences between sites that look similar on a map. Two parcels beside the same line can face very different upgrades because one sits near a strong substation and the other at the end of a long, heavily loaded line; see substation capacity and proximity.
- Distance. Longer line extensions mean more direct-assignment cost and more easements.
- Upstream constraints. A binding limit miles away can add network upgrades the site’s neighbors did not face.
- Competing requests. Several large loads in one area may be studied together and share, or compete for, the same upgrades.
- Timing. Network upgrades needing new lines can take much longer than the customer’s own substation, and often set the power date; see power timelines and interconnection queues.
- Redundancy. A second independent source, discussed in our guide to redundant utility feeds, can trigger its own set of upgrades.
Fig. 4Illustrative upgrade schedule for one campus
Illustrative- Load and facilities studies
- Customer substationDesign, long-lead transformers, construction
- Switching station and tap
- Reconductored lineNetwork upgrade; needs outage windows
- New transmission lineRouting, siting approval, easements, construction
07Questions to ask about upgrades and cost allocation
- 01Which facilities will be classified as customer-specific, and which as network upgrades?
- 02Does a “but for” or direct-connect rule apply, and which upgrades does it reach?
- 03Are network upgrades participant-funded, recovered through rates or split?
- 04Will the load also pay ongoing network transmission charges, and on what basis?
- 05Is any upfront payment refundable or creditable, and what collateral or minimum bill is required?
- 06Are needed upgrades already planned, and could nearby large requests change them or their cost share?
- 07Are cost allocation rules under review by the state commission, the regional operator or FERC?
Answers firm up as studies advance, so ask early for every shortlisted site and confirm with the utility and regulatory counsel. For an independent read on a parcel’s upgrade exposure, get a site reviewed.
Common questions
Who pays for transmission upgrades for a new data center?
It depends on how each upgrade is classified and on utility, state and regional rules. Sole-use facilities are usually charged to the data center, while network upgrades have mostly been recovered from all customers through rates.12 Newer rules, such as Pennsylvania’s model tariff, push more of those costs onto the large load that caused them.3
What is a network upgrade?
An addition to the shared transmission system, such as a rebuilt line or a transformer at a shared substation, that is integrated with the grid for the general benefit of its users. Because others benefit too, network upgrades have usually been rolled into rates, though rules charging them to the load that caused them are spreading.
What is participant funding?
A cost allocation approach in which the customer that causes an upgrade pays for it, rather than all customers through rates. For data centers it usually covers customer-specific facilities and, increasingly, network upgrades; DOE’s 2025 proposal to FERC would have applied it to 100% of network upgrade costs.14
Why do transmission upgrade costs vary so much between sites?
Because studies attribute to each load the specific overloads and voltage problems it causes on the local grid.9 Distance to a strong substation, loading on nearby lines, competing requests and the need for a second source all change the result, so two sites beside the same line can face very different costs.
Is FERC changing who pays for data center transmission upgrades?
It is pressing for change but has not set a national rule. Its June 2026 show cause orders told all six RTOs and ISOs to justify or reform their large-load rules, including how network upgrade costs are handled, and any tariff changes that follow will need FERC approval.5
Notes
- 1.El Paso Electric Company, “Open Access Transmission Tariff,” 2020. epelectric.com
- 2.Union of Concerned Scientists, “New UCS Analysis Reveals Billions of Dollars in Unreported Data Center Costs Passed onto PJM Customers,” 2025. ucs.org
- 3.Womble Bond Dickinson (via JD Supra), “Pennsylvania’s Large Load Model Tariff Offers a Road Map for North Carolina,” n.d. jdsupra.com
- 4.Virginia Mercury, “SCC orders Dominion to develop tariff to assign more transmission costs to data centers,” 2026. virginiamercury.com
- 5.Akin Gump Strauss Hauer & Feld, “FERC Issues Landmark Show Cause Orders on Large Load Interconnection,” 2026. akingump.com
- 6.Concentric Energy Advisors, “The Risks of Cost Shifts in Serving Large Loads Under a Framework With Direct Allocation of Transmission Costs,” 2026. ceadvisors.com
- 7.PJM Interconnection, “Granted Abeyance: Docket EL26-67-000,” 2026. pjm.com
- 8.RMI, “Understanding Large Load Interconnection,” n.d. rmi.org
- 9.Southwest Power Pool, “Delivery Point Network Study DPNS-2022-September-1658,” 2024. opsportal.spp.org
- 10.American Bar Association, “The Jurisdictional Collision over Large Loads and Data Center Interconnection,” 2026. americanbar.org
- 11.Data Center Dynamics, “Georgia PSC approves new billing rules for data centers and large load customers,” 2025. datacenterdynamics.com
- 12.Bloomberg Government, “AI Push to Add $1.6 Billion to Maryland Power Bills, State Says,” 2026. news.bgov.com
- 13.K&L Gates, “Request for Comments on Texas PUCT Draft Report Regarding Transmission Cost Recovery in the ERCOT Region,” 2026. klgates.com
- 14.Joint Consumer Advocates of Pennsylvania, Delaware and New Jersey, “Supplemental Comments of Joint Consumer Advocates,” 2026. oca.pa.gov
- 15.K&L Gates, “Pennsylvania Public Utility Commission Adopts Model Interconnection Tariff for Large Load Customers,” 2026. klgates.com
- 16.White & Case, “PUCT sets financial commitments for data center interconnection as governor pauses permit approvals,” 2026. whitecase.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Power & interconnection
- How Much Power Does a Data Center Need?
- Transmission Voltage and Data Centers: 69 kV to 765 kV
- Power Timelines: Why “When” Matters as Much as “Where”
- ISOs, RTOs and Utility Territories in Data Center Siting
- On-Site Generation and Bridge Power for Data Centers
- What Is Powered Land?
- Load Ramp Schedules: How to Phase Power for a Data Center Campus
- Redundant Utility Feeds and Dual Substations for Data Centers
- Behind-the-Meter vs. Front-of-the-Meter Power for Data Centers
- Microgrids and Battery Storage at Data Center Sites
- Co-Locating Data Centers With Power Plants
- Nuclear and Small Modular Reactors: Siting Considerations for Data Centers
- Renewable Energy Procurement and How It Affects Data Center Siting
- Firm vs. Interruptible Electric Service for Data Centers
- Flexible Data Center Loads and Demand Response
- Texas Senate Bill 6: What It Means for Data Centers and Large Loads
- PJM Capacity Prices and Data Center Load Growth
- Transformer and Switchgear Lead Times for Data Centers
- Substation Configurations for Data Center Campuses: Ring Bus, Breaker-and-a-Half and Double Bus
- Electricity Rates and Power Costs for Data Center Sites
- Power Purchase Agreements for Data Centers: Physical, Virtual and Sleeved
- 24/7 Carbon-Free Energy and Hourly Matching for Data Centers
- Gas Turbines vs. Reciprocating Engines for Data Center On-Site Power
- Fuel Cells for Data Center Power: How They Work and Where They Fit
- NERC Reliability Standards and Large Data Center Loads: Ride-Through, Load Loss and Registration
- From Signed Agreement to Energization: The Data Center Power Timeline
- Hydropower and Data Center Siting: Public Power, Allocations and Drought Risk
- Geothermal Power for Data Centers: Enhanced Geothermal, Clean Tariffs and Siting in the West
- Surplus Interconnection Service and Retired Power Plant Sites: How Existing Grid Rights Get Reused
Guide 13 of 35 in Power & interconnection · all 242 guides · glossary · calculators
