A BlackForge Ventures company
BlackForge Data Centers

Feasibility, diligence & deals

What Does a Data Center Feasibility Study Cover?

A data center feasibility study tests whether a specific site can support a specific data center: enough power on a usable timeline, enough buildable land, workable water and fiber, and a realistic path through zoning and permitting. With data centers estimated at about 4.4% of U.S. electricity use in 2023 and projected at 6.7–12% by 2028, power timing now decides more studies than any other factor.1 The study turns a promising parcel into a clear yes, no or “yes, if,” and sits between a quick desktop screen and full transaction diligence.

Last reviewed · 11 min read · BlackForge Data Centers

Key takeaways

  • Feasibility answers one question: can this site deliver this load, on this land, on a timeline that works?
  • Power availability and timing decide more outcomes than any other workstream, and waits for large grid connections have grown as load queues fill.2
  • Buildable acreage, not gross acreage, sets what the site can hold, and federal wetland maps are screening tools, not regulatory determinations.3
  • Approval risk is real: one tracker estimated about $64 billion of U.S. projects were blocked or delayed by local opposition from May 2024 to March 2025.4
  • A good study ends with a clear verdict, the conditions behind it and the open items still to resolve.
  • Feasibility is not diligence: it narrows the field before money is spent on surveys, borings and legal review.
Public data · Power trackerLarge-load power tracker39 utilities and their data center power rules, from public filings.

01What question does a feasibility study answer?

A feasibility study asks whether a site can host a defined project. That definition matters. A 20 MW colocation building and a 300 MW hyperscale campus put very different demands on the same parcel, so the study starts by fixing the target: load in megawatts, phasing, building count, cooling approach and the date the first megawatts are needed.

Size also changes the rules that apply. The Department of Energy’s October 2025 proposal to FERC would have put new loads greater than 20 MW that connect directly to transmission under federal interconnection standards,5 and some utilities now apply dedicated tariffs to large new data center loads, with minimum bills tied to contracted capacity.6 A realistic ramp schedule is therefore part of the project definition, not a detail for later.

With the target set, the study works through every factor that could stop or reshape the project. Some are hard knockouts, like a site that sits mostly in a regulated floodway. Others are conditions, like a site that works only if the utility builds a new substation. The output is a verdict and a list of what has to be true for that verdict to hold.

The study is not a design and not a legal opinion. It is a structured, evidence-based judgment about whether the site deserves the time and money that diligence and entitlement will cost.

02The core workstreams

Most feasibility studies cover the same workstreams. The depth in each depends on how far along the site is and what the client already knows.

Typical feasibility workstreams and the questions each answers
WorkstreamKey questionsTypical evidence
PowerHow much capacity, from which substation or line, at what voltage, and when?Transmission maps, utility conversations, load or interconnection study results
LandHow many acres are buildable after constraints? Does the shape fit a campus?Parcel data, constraint mapping, concept layout
EnvironmentalFloodplain, wetlands, protected species, contamination, slope and soilsFEMA FIRMs, National Wetlands Inventory and soil data, desktop Phase I screening
Water and wastewaterCan the site meet the cooling design’s water needs and discharge?Utility capacity, groundwater availability, permitting path
FiberHow far to long-haul and metro routes? How many carriers? Diverse paths?Carrier route data, carrier inquiries
EntitlementIs a data center allowed by right? If not, what approval is needed?Zoning code, comprehensive plan, local precedent
Airspace and hazardsFAA height limits, seismic, wind, wildfire and other hazards14 CFR Part 77 review, hazard maps7
ScheduleWhat controls the date the site can be energized and occupied?Combined view of power, equipment, permitting and construction timing

03Power: the workstream that usually decides the answer

For most large sites, power is the deciding factor. The study needs to establish where the nearest usable transmission or substation capacity is, what voltage it runs at, how much headroom it has and what upgrades would be needed. Start with a realistic load figure; our guide to how much power a data center needs covers how to size it.

Fig. 1Data center electricity use in the U.S.

of U.S. electricity used by data centers, 2023
4.4%
data center electricity use, 2023
176 TWh
projected share of U.S. electricity, 2028
6.7–12%
projected data center use, 2028
325–580 TWh
Berkeley Lab estimates; the 2028 range depends on scenario assumptions and on how fast the rest of the economy grows.1 The full report reconstructs use back to 2014.8

Distance to a line on a map is only the first clue. A site next to a 345 kV line may still face years of network upgrades, while a site farther out may sit near a substation with room to spare. That is why the study looks at substation proximity and capacity together, not distance alone.

At the feasibility stage, power findings are usually provisional. The utility’s formal answer comes through the large-load interconnection process, and Wood Mackenzie found in 2025 that a surge of data center and manufacturing requests had packed load interconnection queues and lengthened wait times.2 A good study states what is known, what the utility has indicated informally and what still depends on formal studies or a written will-serve letter.

The rules are also moving. After DOE’s October 2025 directive,5 FERC chose not to issue a single national rule and in June 2026 issued six show-cause orders requiring PJM, SPP, NYISO, MISO, CAISO and ISO-NE, and the transmission owners in them, to justify or reform their large-load interconnection rules.9 A study written in 2026 should name the process that applies to the site and note that it may change.

Hardware and commercial terms belong in the power finding too. Wood Mackenzie estimated a 30% shortfall in U.S. power transformer supply in 2025, and its survey found standard large power transformers averaging 128 weeks for delivery, so a site that needs a new substation may wait on equipment even after the utility says yes.10 On the commercial side, AEP Ohio’s data center tariff sets minimum billing demand at up to 85% of contract capacity and requires collateral, which changes the cost of reserving more capacity than the project will use.6

04Land, environmental and physical constraints

Gross acreage overstates what a site can hold. The study maps floodplain, wetlands, streams and their buffers, steep slopes, easements, setbacks and rights-of-way, then subtracts them. What is left is the buildable acreage, and its shape matters as much as its size. Large data halls, substations and generator yards need wide, regular footprints.

Fig. 2From gross to buildable acres

Illustrative
  • Gross acres400
  • Floodplain-55
  • Wetlands and buffers-30
  • Pipeline and line easements-22
  • Setbacks and road right-of-way-28
  • Steep slopes-15
  • Buildable acres250

acres

Illustrative example. On real sites constraints overlap, so each acre is subtracted only once.

Environmental review at this stage is mostly desktop work: FEMA Flood Insurance Rate Maps, the National Wetlands Inventory, soil surveys, topography and records of known contamination. These sources are imperfect. The U.S. Fish and Wildlife Service notes that NWI maps use a biological definition of wetlands that may not match Clean Water Act boundaries, and that they should not be read as showing the presence, absence or extent of regulated wetlands.3 So the study flags where field work such as a wetland delineation, geotechnical borings or a Phase I ESA is needed before a decision is final.

  • Flood: how much of the site falls in Zone A/AE or shaded Zone X, and whether building pads can sit well above them. Fill or construction in a regulated floodway generally needs an engineer’s “no-rise” analysis, and FEMA treats “no-rise” as a zero increase in flood levels.11
  • Wetlands and streams: likely jurisdictional features that would trigger Clean Water Act Section 404 permitting. As of 2026, which federal definition of “waters of the United States” applies depends on the state, and a new definition proposed in November 2025 was still pending.12
  • Slope and soils: grading volume, rock, karst or poor bearing soils that raise cost.
  • Species and cultural resources: known habitat or sites that could add review time.

05Zoning, permitting and community

A site that works physically can still fail on approvals. The study checks whether data centers are a permitted use under current zoning for data centers, or whether the project would need a special use permit, conditional use or rezoning. It also reviews the comprehensive plan, height limits, noise rules, setbacks and any local history with similar projects, including any moratoriums or local restrictions.

Height deserves an early look near airports. FAA rules require notice of proposed construction on Form 7460-1 at least 45 days before work starts or a construction permit application is filed, whichever comes first, and cranes can trigger filing even when the finished building does not.7 Our guide to FAA airspace and height limits covers the tests.

Community context is part of feasibility, not an afterthought. Data Center Watch estimated that local opposition blocked or delayed about $64 billion of U.S. data center projects between May 2024 and March 2025, with $18 billion canceled outright and $46 billion delayed.4 Common concerns included higher utility bills, water use, noise, property values and loss of green space, and opposition crossed party lines.13 Neighbor proximity and recent public debate all affect how long and uncertain the approval path will be. The study should say plainly whether the path is routine, contested or unclear.

06Screening vs. feasibility vs. diligence

These terms get used loosely. They describe different levels of depth and cost, and each one feeds the next. Our guide to desktop screening vs. field assessment covers where the line between them usually falls.

How feasibility compares with screening and diligence
StagePurposeDepthTypical output
Desktop screenEliminate sites that clearly failMapped data, simple filtersPass, fail or watch list
Feasibility studyDecide whether a site deserves pursuitDesktop analysis plus targeted outreach to utilities, carriers and officialsVerdict, conditions, open items, concept layout
Due diligenceConfirm facts before closing or committing capitalALTA/NSPS survey,14 title, Phase I ESA under ASTM E1527-21,15 geotech, wetland delineation, legal reviewReports and findings that support a transaction

When feasibility is done well, diligence mostly confirms what is already expected. Our site due diligence checklist covers that next step.

07What a good feasibility report delivers

The report should be easy to act on. A reader should be able to see the verdict on the first page and trace every conclusion to its evidence. Our guide to reading a feasibility report explains how to test one.

  1. 01A clear verdict for the defined project: feasible, feasible with conditions, or not feasible.
  2. 02A constraint map and buildable acreage figure, with a concept layout where useful.
  3. 03A power summary: source, voltage, indicated capacity, upgrade needs, applicable tariff and the realistic energization window.
  4. 04Water, fiber and gas findings with the level of confidence in each.
  5. 05The entitlement path and the main community considerations.
  6. 06A ranked list of risks and open items, each with the step that would resolve it.

Fig. 3Sample feasibility scorecard

Illustrative
  • WatchPower230 kV line on site; utility indicates capacity only after a new substation.
  • PassBuildable acreageAbout 250 buildable acres in one regular block.
  • PassFloodplainZone AE limited to the stream corridor, outside the pad areas.
  • WatchWetlandsNWI shows two features; field delineation needed.
  • WatchZoningAgricultural zoning; rezoning required, no local precedent.
  • PassFiberTwo carriers within a few miles on separate routes.
Illustrative sample. Not a real parcel; a real report ties each status to its evidence.

The ranked risk list is the part clients use most. It tells them what to spend diligence money on first. Many of those risks are the same ones covered in why data center sites fail.

08How to start a feasibility study

A study moves faster when the inputs are fixed before work begins. Most delay comes from a moving target, not from the analysis itself.

  • Define the project: target load in MW, phasing, the date the first power is needed and the cooling approach.
  • Identify the land: parcel numbers, a boundary file if one exists, known easements and any prior studies or surveys.
  • List what is already known: utility conversations, will-serve letters, zoning history and environmental reports.
  • Decide what a “yes” requires: the minimum capacity, the latest acceptable energization date and any approvals the deal cannot proceed without.

From there, early utility contact usually comes first, because power timing and the applicable tariff shape every other finding.2 Read our methodology for how we weigh each factor, or get a site reviewed.

CalculatorGross to buildable →CalculatorLand for a load →CalculatorLand option payments →

Common questions

How long does a data center feasibility study take?

It depends on scope and on how quickly utilities, carriers and local officials respond. A desktop-focused study on a single site can move in a matter of weeks. A study that waits on utility feedback or covers several sites can take longer. The formal utility interconnection study, if one is needed, is a separate process with its own timeline and usually runs well beyond the feasibility study itself.

What is the difference between a feasibility study and due diligence?

A feasibility study decides whether a site is worth pursuing for a defined project, mostly using mapped data and targeted conversations. Due diligence comes later and confirms facts before a closing or major commitment, using field work and legal review: an ALTA/NSPS survey, title commitment, Phase I ESA, geotechnical borings and wetland delineation. Feasibility narrows the field so diligence money goes to sites that are likely to work.

Who usually commissions a data center feasibility study?

Developers, operators and site selection teams commission them to compare candidate sites. Investors use them to test a land deal before committing capital. Large landowners and brokers sometimes commission one to understand what a property can realistically support before taking it to market. In each case the study is most useful when the target project, including load and timing, is defined up front.

Can a feasibility study confirm that power is available?

It can establish what is likely, based on transmission data, substation information and informal utility feedback, and it can flag what upgrades might be needed. Firm confirmation of capacity and timing comes only from the utility, usually through its formal large-load or interconnection study process. Those processes are changing: in June 2026 FERC ordered the six FERC-jurisdictional regional grid operators to justify or reform their large-load interconnection rules.9

Does a feasibility study need field work?

Usually not much. Most feasibility work relies on mapped data and outreach, with a site visit where access allows. Mapped data have limits, though: federal wetland maps, for example, are reconnaissance-level and do not show the extent of regulated wetlands.3 Where a finding could change the verdict, the study names the field work that would settle it.

Notes

  1. 1.Lawrence Berkeley National Laboratory, “Berkeley Lab Report Evaluates Increase in Electricity Demand from Data Centers,” 2024. energyanalysis.lbl.gov
  2. 2.Wood Mackenzie, “US power struggle: How data centre demand is challenging the electricity market model,” 2025. woodmac.com
  3. 3.U.S. Fish and Wildlife Service, “Wetlands Data Limitations, Exclusions and Precautions,” n.d. fws.gov
  4. 4.Data Center Watch, “$64 billion of data center projects have been blocked or delayed amid local opposition,” 2025. datacenterwatch.org
  5. 5.Beveridge & Diamond, “DOE Invokes Rare Authority to Direct FERC to Accelerate Grid Access for Large Loads and Data Centers,” 2025. bdlaw.com
  6. 6.AEP Ohio, “Data Center Tariff,” n.d. aepohio.com
  7. 7.Federal Aviation Administration, “Notification of Proposed Construction or Alteration on Airport Part 77,” n.d. faa.gov
  8. 8.Lawrence Berkeley National Laboratory, “2024 United States Data Center Energy Usage Report,” 2024. eta-publications.lbl.gov
  9. 9.Foley & Lardner, “FERC Issues Six Tailored “Show Cause” Orders to Accelerate Large Load Interconnection,” 2026. foley.com
  10. 10.pv magazine USA, “U.S. transformer market faces severe supply constraints as lead times extend to four years,” 2026. pv-magazine-usa.com
  11. 11.FEMA Region X (hosted by the Utah Floodplain Management Program), “FEMA No-Rise Floodway Analysis Requirements,” 2013. floodhazards.utah.gov
  12. 12.Harvard Law School Environmental and Energy Law Program, “Regulatory Tracker: Defining Waters of the United States (WOTUS),” n.d. eelp.law.harvard.edu
  13. 13.Route Fifty, “Report highlights community pushback stalling $64 billion in data center development nationwide,” 2025. route-fifty.com
  14. 14.American Land Title Association, “Why the ALTA/NSPS Land Title Survey Standards Matters,” n.d. alta.org
  15. 15.Quarles, “New Phase I Standard ASTM E1527-21 Authorized for All Appropriate Inquiries Starting February 13, 2023,” 2022. quarles.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Terms in this guide

Related guides

More in Feasibility, diligence & deals

Guide 1 of 18 in Feasibility, diligence & deals · all 242 guides · glossary · calculators