Zoning for Data Centers: By-Right, Special Use and Rezoning

A data center can be approved by right, through a special or conditional use permit, or only after a rezoning, and which path applies to a parcel largely decides how long entitlement takes and how certain the outcome is. By-right sites need administrative approvals only; special use and rezoning sites need public hearings and a vote, and in the busiest markets the by-right path is shrinking.12 Many local codes were written before large data centers were common, so the first job is finding out how the jurisdiction classifies the use.3

Last reviewed · 11 min read · BlackForge Data Centers

Key takeaways

  • By-right zoning offers the most certainty; rezoning offers the least and takes the longest.
  • Leading markets are moving data centers out of by-right status: Loudoun County, Virginia, made them a special exception use in its former by-right districts in March 2025.1
  • Get the zoning administrator’s interpretation in writing early, ideally as a zoning verification letter.
  • Special use and rezoning approvals usually come with conditions on noise, setbacks, height and screening, and some counties now write those standards into the code itself.2
  • Check for moratoriums and pending text amendments: hundreds of local governments took formal action on data center pauses in 2026.4

01The three zoning paths for a data center

Every data center site falls into one of three situations. The use is permitted outright in the current district, it is allowed only with a discretionary permit, or it is not allowed at all and the land must be rezoned. Each path has a different decision-maker, a different standard of review and a different level of risk. In North Carolina, for example, a rezoning is a legislative decision made on the public interest, while a special use permit is a quasi-judicial decision that applies existing standards to the facts of one application.5 Most states draw a similar line, though the labels and procedures differ.

Zoning paths compared
PathWho decidesPublic hearingRelative timelineMain risk
By-right (permitted use)Staff, through site plan reviewUsually notShortestCode changes before you file; strict site plan standards
Special or conditional use permitBoard of zoning appeals, planning commission or governing bodyYesModerateDenial or heavy conditions if findings are not met
Rezoning (map amendment)Elected governing body, after planning commission reviewYes, often more than oneLongestPolitical discretion; the board can say no for broad policy reasons
Planned development or PUDElected governing bodyYesLongNegotiated standards; tied to a specific master plan

Timelines vary widely by jurisdiction, by how complete the application is and by how much public interest the project draws. The ranking above holds almost everywhere, though: administrative approvals move faster and more predictably than anything that needs a vote. Loudoun County’s own description of its 2025 change makes the point. By-right applications there had been approved administratively through site plan review, while a special exception requires staff review and public hearings before both the Planning Commission and the Board of Supervisors.1

02What “by-right” really means

A by-right site is one where the zoning ordinance lists a data center, or a use the zoning administrator agrees covers a data center, as permitted in that district. The project still needs site plan approval, building permits and other technical reviews, but no board gets to weigh whether the use belongs there. If the plans meet the code, staff must approve them.

By-right does not mean unrestricted. Industrial districts set height limits, setbacks, lot coverage, parking, landscaping and often performance standards for noise and lighting. A growing number of jurisdictions have added data-center-specific standards that apply even where the use is permitted. Fairfax County, Virginia, adopted an amendment in September 2024 that limits by-right data centers to its heavy industrial districts and requires a 200-foot building setback from residential lot lines, a 300-foot setback for ground-level equipment such as generators (unless the building itself screens it), and noise studies before and after construction.26 Standards like these reduce the buildable footprint, which is why we check them against gross vs. buildable acreage before calling a site by-right.

Fig. 1Fairfax County data center standards, 2024

building setback from residential lot lines
200 ft
ground equipment setback, unless screened by the building
300 ft
only districts where data centers stay by-right
I-5 and I-6
Selected standards from the amendment Fairfax County adopted in September 2024. Lesser distances can be sought through a special exception.26

By-right status can also be taken away. In March 2025 Loudoun County’s Board of Supervisors voted 7–2 to make data centers a special exception use in every district where they had been permitted by right.1 A grandfathering resolution protected applications already under review on February 12, 2025, but only for sites more than 500 feet from residential areas and only without substantial changes.7 In September 2026 the board directed staff to bring back a legal analysis of ending that grandfathering, so even those applications were not settled as of early October 2026.8

03When the code does not mention data centers

Many zoning ordinances were written before large data centers were common. They list warehouses, manufacturing, utilities and offices, but not data centers. The Urban Land Institute’s 2024 guidance for local officials notes that data centers are a relatively new land use and are often misunderstood or mischaracterized by local decision-makers, which is why it offers a model zoning ordinance for jurisdictions to adapt.3 Where the code is silent, the zoning administrator makes a use interpretation, and the answer can go several ways:

  • Treated as a warehouse, distribution or light industrial use, often permitted in industrial districts.
  • Treated as a public utility or utility facility, which may carry its own approval process.
  • Treated as an unlisted use, which some codes prohibit until the ordinance is amended.
  • Sent to a text amendment, where the jurisdiction writes a new data center definition and standards before any site can be approved. Our guide to data center zoning ordinances and overlay districts covers what those new standards usually contain.

An interpretation can usually be appealed to a board of zoning appeals, and it can be changed later by ordinance. When a jurisdiction is drafting data center standards, applications already filed may or may not be protected, depending on state vesting law and any grandfathering the jurisdiction adopts. Loudoun’s 2025 resolution shows how narrow that protection can be.7 Treat it as a question for local land use counsel, not an assumption.

04Special use and conditional use permits

A special use permit (also called a conditional use permit, special exception or use on review) means the use is allowed in the district only after a hearing body finds that it meets set criteria. Those criteria typically ask whether the use is compatible with neighboring properties, consistent with the comprehensive plan, adequately served by roads and utilities, and not harmful to public health, safety and welfare.

This is a quasi-judicial decision in many states. In North Carolina the board must hold an evidentiary hearing and base its findings on competent evidence in the record, and generalized neighbor opinion that might sway a rezoning carries little weight.59 That gives applicants a clearer standard than a rezoning, but it also means the record matters: sound studies, traffic analysis, visual simulations and utility service letters all carry weight. The label varies. Virginia counties call the same tool a special exception and treat it as a legislative decision by the board, so the standard of review depends on the state.1 Approvals usually come with conditions, and those conditions run with the land. Common ones include:

  • Minimum setbacks or buffers from residential property lines.
  • Maximum sound levels at the property line, often lower at night.
  • Generator testing limited to daytime weekday hours.
  • Landscaped berms, opaque screening or architectural treatment of facades.
  • Building height caps below what the base district allows.
  • Phasing, road improvements or limits on construction traffic routes.

Our guide to noise, setbacks and buffers for data centers covers how these conditions are measured and how much land they take.

05Rezoning and planned developments

If the current district does not allow a data center, the owner or developer asks the governing body to change the zoning map. In most states rezoning is a legislative act. The elected board has broad discretion and can deny a request even when the application is technically complete. The planning commission usually holds a hearing and makes a recommendation first, then the governing body holds its own hearing and votes. Rezonings also carry formal notice requirements, typically published notice plus mailed and posted notice to neighbors.5

Fig. 2How a rezoning request usually moves

  1. 01

    Pre-application

    Meeting with staff on plan consistency and issues.

  2. 02

    Application

    Concept plan, studies and any proffered conditions.

  3. 03

    Staff review

    Agency comments, revisions and a staff report.

  4. 04

    Planning commission

    Noticed public hearing and a recommendation.

  5. 05

    Governing body

    Second noticed hearing and the vote.

A common sequence; names, notice rules and the number of hearings vary by state and jurisdiction.51

Notice and procedure are not formalities. The rezonings for Prince William County’s PW Digital Gateway, a massive proposed data center campus, were voided by a circuit court, which found the county had not met Virginia’s public notice requirements. The Virginia Court of Appeals upheld that ruling on March 31, 2026, and QTS withdrew its petition to the Supreme Court of Virginia in July 2026, ending the project as approved.1011

Many jurisdictions allow or encourage conditional rezoning, where the applicant offers binding conditions (proffers, in some states) or a development agreement as part of the request. Others use planned development districts with a master plan that fixes building locations, heights and buffers. These tools can make a rezoning more acceptable to officials, but they lock in a layout early, before engineering is final. Agricultural land is the most common rezoning case, and it often draws the most public attention, which our guides to public hearings for data center projects and community engagement for data centers cover.

06Comprehensive plans, overlays, moratoriums and other layers

Zoning is not the only land use document that matters. Check each of these:

  • Comprehensive plan and future land use map. A rezoning that matches the planned future use has a much easier path than one that contradicts it, and some states require consistency. See comprehensive plans and future land use maps.
  • Overlay districts. Airport, historic, corridor, watershed or technology overlays can add standards or, in some cases, streamline approval.
  • Annexation. A site in an unincorporated area may need to annex into a city to get water or sewer service, which brings it under city zoning; see annexation and utility service areas.
  • Airport zoning and FAA review, which can cap building and stack heights; see FAA airspace and height limits.
  • Private restrictions. Recorded covenants, deed restrictions or industrial park rules can prohibit uses that zoning allows.

Moratoriums are now a routine screening item. One tracker of local government meetings counted 632 jurisdictions that took formal action on data center moratoriums since January 2026, including 270 adoptions.4 A National League of Cities tracker found at least 28 city and county governments had passed data center ordinances, and a few, including Marshall County, Indiana, and St. Charles, Missouri, had enacted permanent bans.12 Most moratoriums are temporary study periods while the jurisdiction writes standards, but they stop new applications in the meantime. Our guide to data center moratoriums and local restrictions explains how to screen for them.

Fig. 3Local data center pauses in 2026

jurisdictions with formal moratorium action in 2026
632
moratoriums adopted in that count
270
local data center ordinances passed (NLC)
28+
Counts differ by tracker and by what each treats as a moratorium; figures are as reported in 2026.412

07How to check zoning on a candidate site

  1. 01Confirm the current zoning district from the official zoning map, not a third-party parcel viewer.
  2. 02Read the use table and definitions to see whether data centers, or a likely equivalent use, are listed.
  3. 03Read the district’s dimensional standards and any data-center-specific or performance standards.
  4. 04Check the comprehensive plan designation and any overlays.
  5. 05Look at recent decisions on similar projects in the jurisdiction, including denials, conditions imposed and any court challenges.
  6. 06Ask the zoning administrator for a written interpretation or zoning verification letter.
  7. 07Check whether any moratorium, text amendment, grandfathering change or plan update affecting data centers is under way, and read recent board agendas, not just the adopted code.

When we screen a site, zoning status is one of the first filters, because it sets the realistic entitlement timeline. That timeline then has to line up with power delivery and the rest of the data center permitting process. If you want a second opinion on a parcel’s zoning path, you can get a site reviewed.

CalculatorGross to buildable →CalculatorLand for a load →

Common questions

What zoning do data centers usually need?

Most data centers are built in industrial, light industrial, technology or business park districts, or in planned development districts approved for the project. The exact district name varies by jurisdiction. Some codes list data centers as a permitted use, some require a special use permit, and some do not mention them at all, in which case the zoning administrator decides how to classify the use. Some counties now limit by-right data centers to heavy industrial districts only.6

Can a data center be built on agricultural land?

Usually not without a rezoning or special approval, because agricultural districts rarely allow large industrial or utility-scale buildings by right. Many large campuses do start on farmland, but they go through a rezoning or planned development process with public hearings. The comprehensive plan designation, nearby homes and the availability of utilities strongly affect whether officials support the change.

What is the difference between a special use permit and a rezoning?

A special use permit approves a specific use in a district that already allows it with conditions, and in many states the board decides on stated criteria and evidence in a quasi-judicial hearing. A rezoning changes the district itself and is generally a legislative decision where elected officials have broad discretion.5 Special use permits are generally more predictable; rezonings carry more political risk and take longer.

How long does data center zoning approval take?

It depends on the path and the jurisdiction. By-right projects need only administrative review, which is the fastest route. Special use permits and rezonings require public notice, staff review and one or more hearings, and contested cases can be continued, appealed or challenged in court for years.10 Rezonings tied to comprehensive plan amendments generally take the longest, so the zoning path should be part of the project schedule from the first site screen.

Can a county take away by-right approval for data centers?

Yes. A governing body can amend its zoning ordinance to move data centers from permitted to special exception or special use status, as Loudoun County did in March 2025.1 Whether a pending application keeps the old rules depends on state vesting law and any grandfathering the county adopts, and even grandfathering can be revisited.8

Notes

  1. 1.McGuireWoods, “Loudoun County Eliminates By-Right Use for Data Centers, Increasing Development Hurdles,” 2025. mcguirewoods.com
  2. 2.Fairfax County, Virginia, “Board of Supervisors Approves New Data Center Zoning Ordinance Amendment,” 2024. fairfaxcounty.gov
  3. 3.Urban Land Institute, “Local Guidelines for Data Center Development,” 2024. knowledge.uli.org
  4. 4.CRE Daily, “Data Center Moratoriums Formalize in 600+ Jurisdictions,” 2026. credaily.com
  5. 5.UNC School of Government, “Types of Decisions Chart,” n.d. sog.unc.edu
  6. 6.Fairfax Connection, “Supervisors Approve New Requirements for Data Centers,” 2024. m.fairfaxconnection.com
  7. 7.Holland & Knight, “Loudoun County, Virginia, Eliminates By-Right Data Center Development,” 2025. hklaw.com
  8. 8.Loudoun County, Virginia, “Loudoun Board Advances Review of 2025 Grandfathering Exceptions,” 2026. loudoun.gov
  9. 9.UNC School of Government, Coates’ Canons, “Can the Opinions of Neighbors be Considered in a Zoning Hearing?,” 2009. canons.sog.unc.edu
  10. 10.FOX 5 DC, “QTS drops appeal, ending plans for massive Prince William County data center,” 2026. fox5dc.com
  11. 11.WTOP, “Digital Gateway data center project dies after final developer withdraws appeal,” 2026. wtop.com
  12. 12.Route Fifty, “Many localities have tried data center moratoriums, tracker finds,” 2026. route-fifty.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.