Key takeaways
- A development agreement is a negotiated contract, adopted by the governing body by ordinance or resolution under procedures set by state and local law, and it usually runs with the land.5
- Its main value for a phased campus is vesting: in Florida, the local rules in force when the agreement is signed govern the land for its term, subject to narrow exceptions.6
- State law sets the limits: up to 30 years in Florida, and up to 45 years in total, including renewals, for Texas extraterritorial agreements.17
- Recent data center agreements center on infrastructure funding, investment thresholds and phase-by-phase approvals,2 and often cap water use.34
- The electric utility is rarely a party, so a development agreement does not by itself secure power.
01What a development agreement is
A development agreement is a binding contract between a local government and a person with a legal or equitable interest in a specific property. It sets out what the project may build, under which rules, on what schedule and with what obligations on each side. It is usually approved by the city council or county board after public notice and a hearing, adopted by ordinance or resolution, and recorded against the land so it binds future owners. California’s statute, one of the oldest, requires every city and county to establish procedures for considering development agreements, by resolution or ordinance, when an applicant asks.5
Many states have statutes that expressly authorize development agreements and set their limits. Florida’s Local Government Development Agreement Act caps the term at 30 years unless both parties extend it after a public hearing, and an agreement has no effect unless the related comprehensive plan provisions comply with state law.1 Texas lets a city contract with the owner of land in its extraterritorial jurisdiction, including a commitment that the land keeps its extraterritorial status and immunity from annexation for the contract term.8 Other states have no specific statute, and local governments rely on general contracting authority, conditional zoning, annexation agreements or proffer systems to reach similar results.
The name also varies. Some jurisdictions call it a development agreement, others a master development agreement, a pre-annexation agreement, a Chapter 212 agreement or a project agreement. The legal effect depends on the state statute and the document’s wording, not the title.
Fig. 1How a development agreement is approved
- 01
Pre-application
Scope, phasing and infrastructure needs discussed with staff.
- 02
Negotiation
Terms drafted by the developer, staff and attorneys.
- 03
Staff review
Checked against the comprehensive plan and zoning.
- 04
Public hearing
Notice, then a hearing before the governing body.
- 05
Adoption
Approved by ordinance or resolution.
- 06
Recording
Recorded so it binds future owners of the land.
02Why data center projects use them
A data center campus differs from a typical subdivision or warehouse in ways that make a long-term contract useful:
- Long build-outs. A campus may be built in several phases over many years, following the utility’s power delivery schedule. Without vesting, each later phase could face new zoning standards.
- Large infrastructure. Roads, water and sewer extensions, and sometimes reclaimed water lines need to be sized and paid for before the full campus exists.
- High public interest. Officials often want enforceable commitments on noise, buffers, generator testing, water use or community benefits, beyond what the zoning code requires.
- Coordination with incentives. Tax abatements or payment-in-lieu-of-tax arrangements usually sit in separate agreements, but their investment and job thresholds need to line up with the development schedule.
Recent agreements show the pattern. In August 2025, De Soto, Kansas approved a development agreement for a campus of four buildings of roughly 285,000 square feet each, built in phases with full build-out around 2035; the developer funds all required water, sewer and utility upgrades as phases proceed and must invest at least $700 million within seven years to stay eligible for incentives.2 Port Washington, Wisconsin approved an agreement with Vantage Data Centers under which the company fronts $175 million in infrastructure, reimbursed through a new tax incremental district, and may draw up to 1.2 million gallons of water per day from the city’s plant.3
Fig. 2Terms from 2025 data center agreements
- minimum investment within 7 years, De Soto, Kan.
- $700M
- developer-fronted infrastructure, Port Washington, Wis.
- $175M
- maximum water use, Port Washington, Wis.
- 1.2M gal/day
- potable water reserved, Fort Meade, Fla.
- 50,000 gal/day
For the local government, the agreement gives certainty that promised improvements and commitments will be delivered. For the developer, it gives certainty that the rules will not change partway through a multi-phase investment. It also often supports a rezoning request; our guide to zoning for data centers covers how conditional rezoning and planned developments work.
03What a data center development agreement typically covers
| Term | What it does | Why the developer cares | Why the jurisdiction cares |
|---|---|---|---|
| Vested rights | Fixes the land use rules that apply for the term | Later phases are built under known standards | Defines exactly what is being approved |
| Permitted uses and density | States the uses, building area or height allowed | Sets the campus envelope | Limits scope to what was reviewed |
| Phasing schedule | Sets milestones, outside dates or phase-by-phase approvals | Flexibility to follow power delivery | Assurance that the project actually proceeds |
| Infrastructure | Assigns who builds and pays for roads, water, sewer and other improvements | Cost certainty and possible reimbursement | Public systems are funded and built to standard |
| Operational commitments | Noise limits, buffers, generator testing hours, lighting, water source or volume caps | Clear, fixed conditions rather than case-by-case review | Enforceable protections for neighbors |
| Community benefits | Contributions, local hiring or other agreed commitments | Part of the negotiated approval | Visible public return from the project |
| Reporting | Annual reports on investment and progress | Documents compliance with incentive thresholds | Verifies commitments are met |
| Default and remedies | Defines breach, cure periods and consequences | Protects the investment against premature termination | Leverage if commitments are not met |
| Assignment | Rules for transferring rights to a buyer, affiliate or lender | Allows financing and sale of phases | Knows who is responsible |
Not every agreement includes every term, and some states limit what can be required. Separately, the U.S. Supreme Court held in Sheetz v. County of El Dorado (2024) that legislatively adopted permit conditions, including impact fees set by a fee schedule, are not exempt from the Nollan/Dolan tests, which require an essential nexus and rough proportionality to the project’s impacts.9 How that applies to terms a developer agrees to in a negotiated contract is a question for counsel, but it is one more reason jurisdictions tie exactions to documented impacts. Our guide to impact fees and connection fees covers fee schedules.
04Vesting: what can and cannot be locked in
Vesting is the core benefit. Florida’s statute is typical: the local laws and policies governing development when the agreement is executed govern the land for the agreement’s duration.6 That protection matters if the jurisdiction later amends its zoning code, adopts new data center standards or enacts a moratorium; our guide to data center moratoriums and local restrictions covers how those are screened. It matters most for a campus whose later buildings may not start for years.
Vesting has limits. Under the Florida act, a local government may apply later-adopted rules after a public hearing if they do not conflict with the agreement’s uses and densities, if the agreement anticipated them, if conditions have substantially changed, if the agreement relied on substantially inaccurate information from the developer, or if they are essential to public health, safety or welfare and expressly state that they apply to developments under an agreement.6 Agreements also generally cannot freeze building, fire and life safety codes, which update on their own cycle; see building and fire codes for data centers. Fees and utility rates may or may not be fixed, depending on local ordinance and the agreement’s wording. The term itself is limited, so phased projects need milestones that match a realistic schedule rather than a hopeful one.1
Fig. 3What vesting usually holds, and what still changes
Usually held fixed
- Permitted uses and intensity
- Density, height and building area
- Zoning and development rules in force at signing
- Agreed phasing and infrastructure terms
Can still apply
- Building, fire and life safety codes
- Rules essential to health, safety or welfare, with findings
- Rules the agreement anticipated
- Rules justified by substantially changed conditions
- Fees, unless the agreement fixes them
05Infrastructure, cost sharing and the utility gap
Infrastructure terms are usually the most negotiated. Common arrangements include the developer building a road or water main to public standards and dedicating it, oversizing a line for future users with reimbursement from later connectors, or the jurisdiction committing to build a public improvement by a date. In Yorkville, Illinois, CyrusOne agreed to pay for road improvements and for the city to build water and sewer lines to its site, with the city refunding the water and sewer cost from tax revenue over time.10 Each of these needs clear specifications, cost responsibility and a fallback if one side does not perform.
Water is often capped as well as funded. Fort Meade, Florida reserved 50,000 gallons of potable water per day for a 1,300-acre campus, down from the developer’s request of 150,000 gallons, and the regional water management district still had to approve the city’s supply before the project could proceed.4 Our guide to municipal water and sewer capacity covers how to test those numbers.
Electric service is the gap. Investor-owned utilities are regulated by the state utility commission, and many cooperatives and municipal utilities have their own governing boards, so a city or county development agreement usually cannot commit electric capacity. Power is secured through the utility’s own process and contracts, covered in large-load tariffs and electric service agreements. Cooperatives, for example, are building rate structures and contract terms specifically to limit the financial risk of serving data centers and protect other members.11 Where a city owns the electric utility, power terms may be negotiated alongside the development agreement, but they are often still handled in a separate utility contract. A utility will-serve letter is not a substitute for either.
07What to review before signing
- 01Confirm the state enabling statute, the maximum term (30 years in Florida, for example) and the approval process, including any referendum exposure.
- 02Check that the vested rules cover what the full campus needs: height, building area, accessory structures, substations and generator yards.
- 03Make phase milestones achievable even if power arrives later than planned, with extension rights.
- 04Define infrastructure specifications, cost shares, reimbursement terms and what happens if the public side does not deliver.
- 05Read operational commitments against the engineering: sound limits, buffers, water caps and water source must be achievable with the cooling design.
- 06Line up investment thresholds and reporting duties with any incentive agreement.
- 07Check assignment rights for affiliates, buyers of individual phases and lenders.
- 08Review default, cure and termination provisions, and whether termination unwinds the zoning approval.
- 09Assume the agreement will be public. Draft operational and community commitments with that in mind.
Commitments made in a development agreement are also part of the public conversation, which our guide to community engagement for data centers addresses. Before negotiating, it helps to know whether the site’s power, water and zoning can support the phasing the agreement will promise; you can get a site reviewed before those terms are set.
Common questions
What is a development agreement for a data center?
It is a contract between a data center developer or landowner and a city or county that sets the rules and obligations for a specific project, often for many years.5 It usually covers allowed uses and building area, phasing, infrastructure, operational commitments such as water caps or noise limits, and remedies for default.23 It is approved by the governing body after a public hearing and typically recorded so it binds future owners of the land.
Does a development agreement protect a data center from a moratorium?
Often it can, if state law allows the agreement to vest land use rules and the agreement is approved before the moratorium takes effect. In Florida, the rules in force at signing govern for the term, but later rules can apply in limited cases, including rules essential to public health, safety or welfare that expressly reach agreement developments.6 The exact protection depends on the state statute and the agreement’s wording.
How long does a development agreement last?
Terms vary by state and by negotiation. Florida caps them at 30 years unless both parties extend after a public hearing,1 and Texas extraterritorial agreements may run up to 45 years in total, including renewals, under a 2011 amendment.7 Agreements commonly include milestones and outside dates, so the effective term can be shorter if those are missed.
Who pays for infrastructure under a data center development agreement?
Usually the developer, at least up front. In 2025 agreements, De Soto, Kansas had the developer fund all required water, sewer and utility upgrades,2 while Port Washington, Wisconsin had Vantage front $175 million to be reimbursed through a tax incremental district.3 Reimbursement from later users or from project tax revenue is a common negotiated term.10
Can a development agreement secure power for a data center?
No. A city or county usually has no authority over electric capacity unless it owns the utility, and even then power is generally contracted separately. Investor-owned utilities answer to the state utility commission, and cooperatives answer to their boards and set their own large-load contract terms.11 Developers secure power through the utility’s large-load process and electric service agreement, then align the development agreement’s phasing with that schedule.
Notes
- 1.The Florida Senate, “2025 Florida Statutes, Section 163.3229,” 2025. m.flsenate.gov
- 2.City of De Soto, Kansas, “Data Center Campus Project,” 2025. desotoks.us
- 3.Spectrum News 1, “Port Washington data center,” 2025. spectrumnews1.com
- 4.Data Center Dynamics, “Plans to build 1,300-acre data center in Fort Meade, Florida, gets go-ahead from officials,” 2025. datacenterdynamics.com
- 5.California Legislature (Public.Law), “Government Code section 65865,” n.d. california.public.law
- 6.The Florida Senate, “2024 Florida Statutes, Section 163.3233,” 2024. m.flsenate.gov
- 7.Texas Legislature, “Bill Analysis, H.B. 1643, 82nd Legislature,” 2011. capitol.texas.gov
- 8.Texas Statutes (Public.Law), “Tex. Local Gov’t Code Section 212.172,” n.d. texas.public.law
- 9.International Municipal Lawyers Association, “Supreme Court Decides Impact Fee Case,” 2024. imla.org
- 10.WSPY News, “Yorkville City Council approves development agreement with CyrusOne for data center,” n.d. wspynews.com
- 11.NRECA, “New NRECA Report Explores Cost Recovery Strategies for Serving Data Centers,” n.d. cooperative.com
- 12.KXXV 25 News, “Temple council reaches development agreement for city’s third data center,” 2026. kxxv.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Zoning, permitting & community
- FAA Airspace, Airports and Height Limits for Data Centers
- Community Engagement and Local Concerns About Data Centers
- Noise, Setbacks and Buffers for Data Centers
- Site Plan Review for Data Centers: What It Covers and How Long It Takes
- Building and Fire Codes for Data Centers: IBC, NFPA 75 and 76, NFPA 855
- Data Center Sales Tax Exemptions by State: Thresholds, Pauses and Repeals (2026)
- Public Hearings for Data Center Projects: Notice, Testimony and How to Prepare
- Comprehensive Plans and Future Land Use Maps for Data Center Sites
- Data Center Zoning Ordinances and Overlay Districts: Recent Rules and Standards
- Traffic Impact Studies for Data Centers: Trip Generation, Construction Traffic and Road Improvements
- Contested Data Center Projects: Lessons From Prince William, Peculiar, Tucson and Other Public Fights
- State Data Center Legislation: 2025–2026 Trends in Tariffs, Incentives, Water and Moratoriums
- Data Center Architectural and Visual Standards: Facades, Screening, Lighting and Height
Guide 7 of 20 in Zoning, permitting & community · all 242 guides · glossary · calculators
