A BlackForge Ventures company
BlackForge Data Centers

Zoning, permitting & community

Annexation, Jurisdiction and Utility Service Areas for Data Center Sites

Two questions about a site are settled by maps and statutes, not by negotiation: which government has land use authority over it, and which utilities are allowed to serve it. Annexation into a city can change the first, and in some states the second; cities often tie water and sewer service to annexation, as data center approvals in Menomonie, Wisconsin,1 Granger, Indiana,2 and Temple, Texas, show.3 Exclusive retail electric territories mean the utility of record is usually the only one that can serve the load, with exceptions such as Georgia’s choice for new loads of 900 kW or more and retail choice in a minority of states.45

Last reviewed · 10 min read · BlackForge Data Centers

Key takeaways

  • Confirm whether the site is in a city, in unincorporated county land or in a city’s extraterritorial area; in Texas, landowners can now petition out of a city’s ETJ.
  • Cities often require annexation before extending water or sewer, which brings the site under city zoning and taxes.16
  • Many states assign exclusive retail electric service territories; the utility of record usually cannot be swapped.7
  • Investor-owned utilities served about 72% of U.S. electricity customers in 2017, but cooperatives cover far more land, which matters for rural sites.89
  • Water, sewer and gas service areas are separate maps and can each have their own provider.10
Public data · Power trackerLarge-load power tracker39 utilities and their data center power rules, from public filings.

01Why jurisdiction is a first-pass check

The jurisdiction controls zoning, site plan review, building permits, local taxes and many incentives. The utility service territory controls who can deliver power, water and sewer, under what rules and on what schedule. A parcel on the edge of a city, near a county line or at the boundary of two electric providers can have very different outcomes depending on which side of a line it falls on.

These boundaries are also hard to change. Zoning can be amended through a public process. Service territories and municipal boundaries change only under state law, often with consent from several parties. In Georgia, for example, whether a site was inside a city’s limits as they stood on March 29, 1973 still affects which electric suppliers may serve a new large load.4 When we screen a site, we confirm both jurisdiction and service areas before spending time on anything else that depends on them, because they shape zoning, taxes, power options and timeline.

02Incorporated, unincorporated and extraterritorial land

Land inside a city or town is governed by that municipality’s zoning and permitting. Land outside any municipality is usually governed by the county, though some rural counties have little or no zoning. In some states, cities also exercise extraterritorial jurisdiction (ETJ) over land just beyond their limits, which can include subdivision, platting or other authority. Townships carry land use authority in some states as well.

  • City land: city zoning and building codes; city services often available; city property tax in addition to county.
  • Unincorporated county land: county zoning, if any; services may come from districts or rural providers; often fewer tax layers.
  • Extraterritorial areas: a city may control some approvals even though the land is not in the city.
  • Boundary parcels: a tract split between jurisdictions may need approvals from both, under different rules.

ETJ rules are changing in Texas. Senate Bill 2038, effective September 1, 2023, created a petition process for releasing land from a city’s ETJ; once the required signatures are verified, the city must release the area, and if it fails to act, the area is released by operation of law.11 The City of Austin states that it has no discretion over a compliant petition, while noting ongoing litigation over the law.12 Texas cities can also contract with ETJ landowners to secure the land’s continued extraterritorial status and immunity from annexation, while extending planning authority and providing for roads, drainage and utilities.13 Confirm the current status of any ETJ before relying on it.

03How annexation works and why it comes up

Annexation brings unincorporated land into a city. State law sets the method, and it varies widely. Common requirements include contiguity with existing city limits, a petition or consent from the landowner, a service plan and a vote by the city council. Some states allow cities to annex without owner consent under certain conditions; others require consent or an election.

For data centers, annexation usually comes up because a city will extend water or sewer only to land that annexes, or that signs a pre-annexation agreement committing to annex later. In August 2025, Menomonie, Wisconsin annexed and rezoned 324 acres for a proposed data center, with officials pointing to a nearby water main, capacity for the roughly 75,000 gallons per day the facility would need and an update to the urban sewer service area plan.1 In Cheyenne, Wyoming, Microsoft sought annexation so its property could tie into city water and sewer.6 The arrangement can also run the other way: Mishawaka, Indiana agreed with St. Joseph County to serve a planned Microsoft data center in unincorporated Granger, a deal that could open the door to later annexation.2

Fig. 1Staying in the county vs. annexing into a city

Stay in the county

  • County zoning, which may be lighter or absent
  • Often fewer local tax layers
  • Water and sewer from districts, wells or none
  • County board hears the case

Annex into the city

  • City zoning and site plan rules apply
  • City property and other local taxes may apply
  • City water, sewer and fire service become available
  • Terms can be set in an annexation agreement
  • City residents and council weigh in
General patterns; outcomes depend on state law and the specific city and county.

An annexation agreement can set zoning, fees and service terms, much like a development agreement for a data center. In April 2026, Temple, Texas annexed land and rezoned about 300 acres for a data center campus, along with a development agreement setting the project timeline and terms for noise, construction traffic and utility agreements.3 In California, a city may sign a development agreement for unincorporated land in its sphere of influence, but it becomes operative only if annexation is completed within the period the agreement sets.14 Annexation adds a public process and time, and it changes who the community conversation involves; see public hearings for data center projects.

Fig. 2Illustrative annexation and rezoning schedule

Illustrative
  • Pre-application and service plan
  • Annexation petition and notice
  • Annexation agreementZoning, fees and utility extension terms
  • Hearings and council votes
  • RezoningOften heard with the annexation
  • Utility extension design
051015months
Illustrative example; many cities run annexation, rezoning and the agreement in parallel, and state law sets notice periods.

04Exclusive electric service territories

In many states, the utility commission or state law assigns each area an exclusive retail electric provider, sometimes through a certificate of public convenience and necessity or territorial agreements between utilities. Inside a certificated territory, only the assigned utility may serve new retail customers. A data center cannot simply choose a neighboring utility with more capacity or better rates, even if that utility’s line runs along the property.

There are variations. Georgia’s Territorial Electric Service Act of 1973 assigns territories but lets a new customer with connected load of 900 kW or more at initial full operation, excluding redundant equipment, choose its supplier if it is located outside municipal limits as they stood on March 29, 1973; areas annexed later follow separate rules.4 A Georgia economic development site describes this as allowing competition among the state’s utilities for most new large commercial and industrial loads, with the chosen supplier then keeping the premises.7 In states with retail competition, the local wires utility is fixed, but the customer may buy energy from a competitive supplier: as of 2022, the District of Columbia and 13 states offered choice to all investor-owned utility customers, and customers in competitive ERCOT areas must choose a retail provider.5 Territorial boundaries can sometimes be adjusted by agreement between utilities with regulatory approval. None of these are quick or certain, and the rules vary by state; see regulated utility vs. competitive market sites.

Once the provider is known, the large-load interconnection process runs through that utility, along with any wholesale supplier or transmission owner it depends on, and the regional market structure shapes the rest; see ISOs, RTOs and utility territories.

05Investor-owned, cooperative and municipal utilities

Retail electric providers in the U.S. fall into three broad groups, described in our glossary entry on utility ownership types. Investor-owned utilities are few but large, and they served about 72% of U.S. electricity customers in 2017.8 Cooperatives serve fewer people but cover more ground. Each type can serve a data center, but they handle large loads differently.

Fig. 3Who serves U.S. electricity customers

of U.S. customers served by investor-owned utilities, 2017
72%
of U.S. landmass powered by cooperatives
56%
people served by cooperatives
42 million
generation and transmission cooperatives
63
Investor-owned share from EIA (2017 data); cooperative figures from NRECA’s 2023 fact sheet.89
Electric utility types, in general terms
Investor-owned utility (IOU)Electric cooperativeMunicipal utility
OwnershipShareholdersMember-consumersCity or town
Rate oversightState utility commissionUsually its own board; commission oversight varies by stateCity council or utility board; commission oversight varies
Typical service areaOften large and multi-countyOften rural and suburban; most of the nation’s land areaCity limits and sometimes nearby areas
Power supplyOften owns generation and transmission, or buys in an organized marketOften buys wholesale from a generation and transmission cooperative or other supplierOften buys wholesale, sometimes through a joint action agency, or owns some generation
Large-load considerationsEstablished large-load tariffs and processes are commonA single large load can exceed the co-op’s existing system; supplier coordination is centralLarge loads can be significant to city finances; council approval may be involved

With cooperatives and many municipal utilities, the retail provider may not control the generation or transmission needed for a large campus. The wholesale supplier and the transmission owner become part of the conversation, and contracts may run through several parties. NRECA advises co-ops to engage early, to bring in their wholesale power suppliers and regional transmission operators before choosing a path, and notes that co-ops can ask prospective customers to fund engineering studies; co-ops are also building rate structures and contract terms to protect other members from the financial risk.15 In November 2025, NRECA told federal regulators that co-ops need coordinated federal policy to serve large loads while keeping rates affordable.16 Our guides to large-load tariffs and electric service agreements and what utilities and co-ops look for cover how those terms are structured.

06Water, sewer and gas service areas

Water and sewer service areas are separate from electric territories and from city limits. A site may sit in a city water area, a rural water district, a special utility district or no service area at all. Some states issue certificates for water and sewer service much as they do for electric service. In Texas, the Public Utility Commission issues certificates of convenience and necessity (CCNs) that obligate the holder to provide continuous and adequate service to every customer who requests it in the certificated area, and the official maps keep water and sewer service areas in separate layers.10

Sewer is often the tighter constraint, since treatment plants and lift stations have fixed capacity and sewer service areas may be set in regional plans; Menomonie’s 2025 annexation came with an update to its urban sewer service area plan with state and regional partners.1 A city may also attach water limits to an extension, so the provider’s stated capacity and any cap should be read together. Gas service usually comes from a local distribution company holding a franchise for the area, with transmission pipelines operated separately.

For cooling demand and discharge, see data center water requirements, municipal water and sewer capacity and wastewater and cooling water discharge.

07How to check jurisdiction and service areas

  1. 01Confirm municipal limits and any extraterritorial area from the city and county, not a parcel viewer alone, and check for pending ETJ releases or annexations.
  2. 02Identify the zoning authority and whether county zoning exists in that area.
  3. 03Ask whether water or sewer service requires annexation or a pre-annexation agreement.
  4. 04Confirm the retail electric provider of record with the utility or the state commission’s territory maps, and whether any large-load choice rule applies.
  5. 05Identify that provider’s wholesale supplier and the transmission owner near the site.
  6. 06Check the water, sewer and gas providers for the parcel, their certificated areas and their stated capacity.
  7. 07Note any boundary that splits the site, and what each side would require.

Write down the source for each answer, since a map layer and a utility’s own records can disagree. If you want a second look at who regulates and serves a parcel, you can get a site reviewed.

CalculatorGross to buildable →CalculatorLand for a load →

Common questions

Can a data center choose its electric utility?

Usually not. Many states assign exclusive retail service territories, so the utility of record for a parcel is the only provider allowed to serve it. Georgia lets new loads of 900 kW or more outside 1973 city limits choose a supplier,4 and in the 13 states and D.C. with full retail choice, customers can pick an energy supplier while the local wires utility stays the same.5 Changing territories generally requires agreement between utilities and regulatory approval.

Why would a data center site need to be annexed?

The most common reason is that a city will only extend water or sewer service to land inside its limits, or to land that agrees to annex later.61 Annexation moves the site under city zoning and taxes, and it may make city services available. The process is set by state law and usually involves a petition, a service plan and a council vote, so it adds time to entitlement.

Can a Texas landowner take land out of a city’s ETJ?

Yes, under Senate Bill 2038, effective September 1, 2023, owners or residents can petition for release, and the city must release the area once the required signatures are verified.11 The City of Austin notes that the law has been the subject of litigation,12 and disputes continue: in August 2026 a federal judge preliminarily barred Austin from reversing ETJ releases it had already granted.17 Confirm the current status with counsel before relying on a release.

Can an electric cooperative serve a large data center?

Yes, many cooperatives can, but the process often involves more parties. A large campus may exceed the co-op’s existing system, so its wholesale supplier, often a generation and transmission cooperative, and the transmission operator usually need to plan for the load.15 Contract terms may include customer-funded studies and other protections for existing members. Timelines depend on generation and transmission availability more than on the co-op itself.

What is a certificated service territory?

It is an area where state law or the utility commission has granted one utility the exclusive right, and usually the obligation, to provide retail service.10 The certificate or territorial agreement prevents competing utilities from extending service to customers inside it. For site selection, it means the provider of record determines the power path, tariffs and timeline for any load built on that land.

Notes

  1. 1.DeWitt Media, “Menomonie annexes 324 acres and rezones for proposed data center development,” 2025. dewittmedia.com
  2. 2.WVPE, “County, Mishawaka OK extending city water, sewers into Granger,” 2025. wvpe.org
  3. 3.KXXV 25 News, “Temple council reaches development agreement for city’s third data center,” 2026. kxxv.com
  4. 4.City of Marietta, Georgia, “Commercial Customers,” n.d. mariettaga.gov
  5. 5.U.S. Energy Information Administration, “Can electric utility customers choose their electricity supplier?,” 2024. eia.gov
  6. 6.Your Wyoming Link, “Cheyenne approves Microsoft annexation after hours of debate,” n.d. yourwyominglink.com
  7. 7.LocationGeorgia, “Georgia Electricity,” n.d. locationgeorgia.com
  8. 8.U.S. Energy Information Administration, “Investor-owned utilities served 72% of U.S. electricity customers in 2017,” 2019. eia.gov
  9. 9.NRECA, “Electric Co-op Facts and Figures (2023),” 2023. electric.coop
  10. 10.Travis County (PUC Texas data), “PUC CCN - Water,” n.d. gis.traviscountytx.gov
  11. 11.Texas Legislature, “Bill Analysis, S.B. 2038, 88th Legislature,” 2023. capitol.texas.gov
  12. 12.City of Austin, “Petition for an extraterritorial jurisdiction (ETJ) release,” n.d. austintexas.gov
  13. 13.Texas Statutes (Public.Law), “Tex. Local Gov’t Code Section 212.172,” n.d. texas.public.law
  14. 14.California Legislature (Public.Law), “Government Code section 65865,” n.d. california.public.law
  15. 15.NRECA, “New NRECA Report Explores Cost Recovery Strategies for Serving Data Centers,” n.d. cooperative.com
  16. 16.NRECA, “NRECA Urges ‘Whole-of-Government Approach’ to Help Co-ops Serve Large Loads,” 2025. electric.coop
  17. 17.Texas Policy Research, “Federal Judge Blocks Austin’s Attempt to Reclaim ETJ Authority,” 2026. texaspolicyresearch.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Terms in this guide

Related guides

Power & interconnectionHow the Large-Load Utility Interconnection Process WorksHow large-load utility interconnection works for data centers, from the first load request through studies, agreements, financial commitments and energization.Zoning, permitting & communityDevelopment Agreements for Data Center Projects: What They CoverWhat a data center development agreement is, what it usually covers, how it can vest rights for a phased campus, and which terms to review before signing one.Power & interconnectionISOs, RTOs and Utility Territories in Data Center SitingHow ISOs, RTOs, utility types and state retail rules affect data center siting, who actually connects your load, and what market structure changes for a site.Water, gas & fiberMunicipal Water and Sewer Capacity for Data Center Sites: Treatment Plants, Extensions and Will-Serve LettersHow to check municipal water and sewer capacity for a data center site: treatment plant headroom, mains, fire flow, extensions, fees and will-serve letters.Zoning, permitting & communityZoning for Data Centers: By-Right, Special Use and RezoningHow zoning applies to data centers: by-right use, special or conditional use permits, rezoning, overlays and what each path means for timeline and certainty.Decisions and trade-offsRegulated Utility vs. Competitive Market Sites for Data CentersRegulated utility vs. competitive market sites for data centers: how vertically integrated states, ERCOT and PJM retail choice compare on power, cost and risk.

More in Zoning, permitting & community

Guide 8 of 20 in Zoning, permitting & community · all 242 guides · glossary · calculators