Key takeaways
- Local moratoriums have become common, and a few jurisdictions, including St. Charles, Missouri, have gone on to permanent bans.5
- Restrictions also arrive through text amendments, overlays, plan policy and provider limits, such as a Michigan utility’s 12-month pause on water service to data centers.6
- State action now belongs in the screen: New York’s July 2026 executive order paused discretionary state permits for data centers of 50 MW or more.1
- Protection for pending projects depends on state law: Washington vests on a complete building permit application,7 Texas on the original application for a project’s first permit,8 and Utah lets a pending ordinance defeat vesting.9
- A temporary moratorium is not a per se taking under federal law, so a takings challenge is an uncertain way to end one.10
- Land contracts should give time and exit rights if a moratorium is adopted during diligence.
01What a data center moratorium is
A moratorium is a temporary ordinance or resolution that stops a jurisdiction from accepting, processing or approving certain applications. For data centers it typically covers rezonings, special or conditional use permits, site plans and building permits for that use. Its stated purpose is to give officials time to study impacts and draft standards.
Recent examples show the usual shape. In July 2026, York County, South Carolina, adopted a nine-month moratorium for unincorporated areas that bars the county from accepting site plans or issuing special exceptions, conditional use permits or other development approvals for new data centers while staff studies noise, groundwater, utility rates, energy infrastructure, waste heat and effects on nearby property; projects with civil site plan approval before the ordinance took effect are exempt.2 Neighboring Chester County adopted a six-month moratorium the same month to study and prepare development standards.4 In Georgia, Paulding County approved a pause through January 1, 2027 that does not affect applications already submitted.3
State law governs what a moratorium can do. Minnesota, for example, limits an interim ordinance to one year from its effective date, with extensions only on limited statutory grounds; one township that began with an eight-month pause extended it to the full 12 months.1112 Other states have little specific guidance, and courts review moratoriums under general land use principles. A moratorium may be countywide, limited to certain districts or limited to sites near homes or other sensitive uses.
Fig. 1Length of selected 2026 data center pauses
- Chester County, SC6
- York County, SC9
- Paulding County, GATo Jan. 1, 2027
- Minnesota interim limit12 (state limit)
months
02Moratoriums are only one form of restriction
Many restrictions arrive without the word moratorium, and they can last longer because they are written as permanent code or come from someone other than the zoning authority.
| Tool | What it does | Effect on a candidate site |
|---|---|---|
| Moratorium | Pauses applications or approvals for a set period | Delays everything; outcome depends on the rules adopted after |
| Text amendment | Adds a data center definition and standards | Setbacks, sound limits or size caps can shrink the buildable area |
| Use reclassification | Moves data centers from permitted to special use, or out of a district | Turns an administrative approval into a discretionary hearing |
| Permanent ban | Prohibits the use in the jurisdiction | No local path; a national tracker listed three such bans in August 20265 |
| Overlay or designated zone | Limits data centers to mapped areas | Sites outside the area need a map change |
| Comprehensive plan policy | Discourages data centers in certain areas | Weakens the case for rezoning |
| Performance standards | Sets noise, lighting, generator testing or water-source rules | Changes equipment design and sometimes the layout |
| Utility or water limits | A provider pauses or caps new large commitments | No service on the needed timeline |
| State action | A state pauses permits for large facilities | Can stop a project that local zoning allows |
Provider limits deserve as much attention as zoning. In April 2026, Michigan’s Ypsilanti Community Utilities Authority approved a 12-month moratorium on delivering or committing water and sewer service to data centers pending water system studies.6 Near Roanoke, Virginia, the Western Virginia Water Authority rejected an early request for 10 to 11 million gallons a day for a Google project and capped initial supply at 2 million.13 The Pacific Northwest utility Avista paused talks on serving a proposed 500 MW data center while it sought policy guidance and community input.14 See municipal water and sewer capacity for how to confirm service early.
Fig. 2Where a restriction on a site can come from
- 01State governmentExecutive orders, statutes and statewide permit pauses
- 02Local governing bodyMoratoriums, text amendments, overlays and permanent bans
- 03Comprehensive planPolicy language and future land use maps
- 04Utilities and water providersPauses or caps on new large-load and water commitments
- 05Candidate siteWhat is actually approvable and serviceable
Noise and setback rules are among the most common permanent standards; see noise, setbacks and buffers and data center zoning ordinances and overlay districts.
03Why jurisdictions and states adopt them
Moratoriums usually follow a pattern. A jurisdiction receives several large applications in a short time, or an operating facility draws complaints, and officials decide the existing code was not written for the use. Common concerns include:
- Noise from cooling equipment and generator testing near homes.
- Groundwater and public water supply, especially where supply is tight.
- Utility rates and electric reliability for existing customers.
- Transmission lines, substations and other energy infrastructure.
- Loss of farmland, building scale, construction traffic and waste heat.
- Whether tax incentives give away more than the community gets back.
States have begun to act on the same concerns. On July 14, 2026, New York Governor Kathy Hochul signed an executive order pausing discretionary state permits for data centers of 50 MW or more for up to a year while the state writes a regulatory framework; projects whose applications the Department of Environmental Conservation had already deemed complete are exempt, and local permits are not covered. A bill passed by the legislature would have applied at 20 MW.1 The state data center legislation guide tracks these trends.
Most local concerns can be addressed through design, siting and commitments, which is why many moratoriums end in standards rather than bans; see community engagement for data centers.
04What happens to projects already in process
Whether a pending project is affected depends on state vesting law, the moratorium’s exemptions and how far the project has gone. States differ widely:
- Washington vests rights on filing a valid and fully complete building permit application, with completeness defined by local ordinance; its courts have held that a site plan application alone did not vest rights.7
- Texas Chapter 245 judges a project’s permits against the rules in effect when the original application for its first permit was filed, if that application gave fair notice of the project, and treats later permits as one series.8
- Utah applies a pending ordinance rule: if the local government has already initiated an ordinance change when an application is filed, the applicant cannot claim a vested right under the language being changed.9
- An approved development agreement can vest rules for its term where state law allows it.
The ordinance text matters as much as the state rule. York County exempted projects with civil site plan approval,2 Paulding County exempted applications already submitted,3 and New York’s order exempts projects whose state applications had already been deemed complete.1
Fig. 3How exposed is a project at each stage?
Illustrative- FailPre-application talksGenerally no protection from a new pause or standard.
- WatchComplete application filedProtected in some states and under some exemptions only.
- WatchRezoning approvedZoning usually stands, but later permits may be paused.
- PassPermits issued, work under wayStrongest position in most states.
Legal challenges are a weak fallback. In Tahoe-Sierra Preservation Council v. Tahoe Regional Planning Agency (2002), the U.S. Supreme Court held that moratoria totaling 32 months were not per se takings, and that duration is one factor in a case-by-case analysis.10
05Early warning signs
Restrictions are rarely a surprise to anyone watching local government closely, and they tend to spread between neighbors, as the York and Chester pauses adopted in the same month show. Public trackers make the regional check faster: in August 2026, a National League of Cities tracker counted at least 76 local governments that had tried moratoriums or permanent bans, and described its list as incomplete.5 Signs that a restriction may be coming include:
- Work sessions or study items about data centers on planning commission or board agendas.
- A comprehensive plan update or zoning code rewrite under way.
- Several recent large applications in the same jurisdiction or a neighboring one.
- Organized public comment, petitions or new residents’ groups focused on data centers.
- Statements by officials or candidates about pausing or limiting the use.
- Neighboring jurisdictions that recently adopted moratoriums or new standards.
- Utility or water provider statements about limits on new large commitments.
- State executive or legislative action aimed at large facilities.
Two or three of these together justify slowing land commitments.
06How to screen a site for moratorium risk
- 01Read the current zoning code for any data center definitions, standards or recent amendments.
- 02Review planning commission and governing body agendas and minutes for the past year or more.
- 03Check whether a moratorium is in effect, its scope, its exemptions, its expiration and any extension history.
- 04Check the comprehensive plan for data center policy and any update in progress.
- 05Look at neighboring jurisdictions and public trackers, since restrictions often spread regionally.
- 06Ask staff directly whether standards are being drafted, and note the answer in writing.
- 07Confirm the state vesting rule and what stage would protect the project.
- 08Ask the utility and water provider whether any limits on new large commitments apply.
- 09Check for pending state orders or bills that would apply to a facility of the planned size.
Moratorium risk is one input to how a site is scored, alongside the zoning path covered in zoning for data centers, and it should be rechecked before each contract deadline.
07What to do if a site is affected
A moratorium does not always end a project. Options include waiting it out if the land contract allows, taking part in drafting the new standards, adjusting the site plan to meet likely rules, or shifting to another site. If the site no longer fits, moving on early usually costs less than waiting out the pause. Chester County, for example, planned expert workshops during its pause, which gives applicants a defined window to bring data on noise, water and power.4 Preparing for the hearings that follow is covered in public hearings for data center projects.
Land contracts should anticipate this. Extension rights, tolling of deadlines during a moratorium and termination rights tied to land use changes all help; see buy, option or lease and due diligence periods and purchase contingencies. If a candidate site sits in a jurisdiction showing these signs, look closely before deposits go hard, or get a site reviewed.
Common questions
What is a data center moratorium?
It is a temporary pause, usually adopted by a city or county, on accepting or approving data center applications such as rezonings, special use permits or site plans. Jurisdictions adopt one to study the use and write standards, and state law controls how long it can last; Minnesota, for example, limits an interim ordinance to one year before any extension.11 Many end with permanent rules on setbacks, noise, location or size.
Does a moratorium apply to projects already filed?
It depends on the ordinance’s exemptions and state vesting law. Some ordinances exempt applications already submitted or projects with site plan approval.23 Some states vest rights when a complete application is filed, others only at a later stage, and some let a pending ordinance defeat a later-filed application. Confirm the rule with local land use counsel.
How long do data center moratoriums usually last?
Recent county pauses have run from about five to nine months, some ending on a fixed date and others tied to finishing a study and new standards. Many can be extended. The practical delay often exceeds the moratorium, because applications must then be prepared again under the new rules.
Are there statewide data center moratoriums?
Yes. In July 2026, New York’s governor signed an executive order pausing discretionary state permits for data centers of 50 MW or more, reported as the first statewide data center moratorium.1 State action is moving quickly, so check current orders and bills for any site.
How can I tell if a county is likely to restrict data centers?
Read recent planning commission and governing body agendas and minutes, check for a comprehensive plan or zoning code update, and look at what neighboring jurisdictions have done. Work sessions about data centers, several recent large applications, organized public comment and provider statements about capacity are common warning signs.
Notes
- 1.Hodgson Russ LLP, “Governor Hochul Signs First Statewide Data Center Moratorium in the U.S.,” 2026. hodgsonruss.com
- 2.WRHI, “York County Council approves nine month data center moratorium,” 2026. wrhi.com
- 3.Spectrum News, “Paulding County hits pause on new data centers,” 2026. spectrumlocalnews.com
- 4.WBTV, “Chester County Council approves 6-month data center moratorium,” 2026. wbtv.com
- 5.Route Fifty, “Many localities have tried data center moratoriums, tracker finds,” 2026. route-fifty.com
- 6.Michigan Public, “Michigan utility OKs 12-month ban on supplying water for data centers,” 2026. michiganpublic.org
- 7.Municipal Research and Services Center, “Vested Rights,” n.d. mrsc.org
- 8.Texas Statutes (Public.Law), “Tex. Local Gov’t Code Section 245.002,” n.d. texas.public.law
- 9.Utah Department of Commerce, “Advisory Opinion 238,” n.d. commerce.utah.gov
- 10.Legal Information Institute, Cornell Law School, “Tahoe-Sierra Preservation Council, Inc. v. Tahoe Regional Planning Agency,” 2002. law.cornell.edu
- 11.Minnesota Office of the Revisor of Statutes, “2020 Minnesota Statutes, Section 462.355,” 2020. revisor.mn.gov
- 12.Mission Township, Minnesota, “Ordinance 2026-01 Extending Interim Ordinance on Administrative Subdivisions,” 2026. missiontownship.org
- 13.WDBJ7, “Roanoke water company addresses Google data center water usage concerns,” 2026. wdbj7.com
- 14.YourSourceOne, “Avista pauses energy service talks with 500-megawatt data center developer amid community concerns,” n.d. yoursourceone.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Zoning, permitting & community
- FAA Airspace, Airports and Height Limits for Data Centers
- The Data Center Permitting Process, Step by Step
- Data Center Tax Incentives: What to Look For
- Noise, Setbacks and Buffers for Data Centers
- Development Agreements for Data Center Projects: What They Cover
- Annexation, Jurisdiction and Utility Service Areas for Data Center Sites
- Site Plan Review for Data Centers: What It Covers and How Long It Takes
- Building and Fire Codes for Data Centers: IBC, NFPA 75 and 76, NFPA 855
- Data Center Sales Tax Exemptions by State: Thresholds, Pauses and Repeals (2026)
- Public Hearings for Data Center Projects: Notice, Testimony and How to Prepare
- Comprehensive Plans and Future Land Use Maps for Data Center Sites
- Traffic Impact Studies for Data Centers: Trip Generation, Construction Traffic and Road Improvements
- Impact Fees and Utility Connection Fees for Data Centers: How They Work and What Is Negotiable
- Data Center Architectural and Visual Standards: Facades, Screening, Lighting and Height
Guide 9 of 20 in Zoning, permitting & community · all 242 guides · glossary · calculators