Key takeaways
- Notice is required for anything over 200 feet above ground, and for lower structures that exceed sloped surfaces near public-use and military airports and heliports: 100:1 out to 20,000 feet, 50:1 to 10,000 feet and 25:1 to 5,000 feet.1
- Temporary construction cranes are filed and studied separately, at the maximum height they will reach, and are often the first thing to trigger review.3
- File Form 7460-1 at least 45 days before construction or a permit application, whichever comes first; a determination of no hazard generally expires 18 months after its effective date unless extended.45
- FAA determinations are advisory for off-airport land; local airport zoning adopted under state law is what turns airspace surfaces into enforceable height limits.26
- Stormwater ponds, exhaust plumes and glare raise airport concerns even when height does not; FAA wildlife guidance recommends 5,000 to 10,000 feet of separation from airport operating areas, and 5 miles near approach and departure paths.7
- The FAA replaced its obstruction marking and lighting circular, AC 70/7460-1M, with AC 70/7460-1N, dated August 11, 2026.8
01Why airspace matters for a low-rise building
Most data centers are one to three stories, so airspace can seem irrelevant. It is not. Data centers often go on flat, open land near highways and industrial areas, exactly where general aviation and regional airports tend to be. The FAA’s notice surfaces slope up gently from the runways, so a modest building close to a runway can still need review: at a 100:1 slope, a structure 5,000 feet from a qualifying runway meets the notice surface at about 50 feet above the runway’s elevation.
The elements that stick up are often the issue: generator exhaust stacks, rooftop cooling equipment, lightning protection masts, communication antennas, substation structures and the transmission poles that bring power to the site. During construction, tower and mobile cranes reach far higher than the finished building. Grading matters too: a pad raised for drainage raises everything on it, so an accurate topographic survey is the starting point for any airspace check.
02When FAA notice is required under Part 77
Federal regulations at 14 CFR Part 77 require anyone proposing construction or alteration that meets certain criteria to notify the FAA, and the FAA can also ask for notice of a specific proposal. The main triggers are:
| Situation | Notice is required if the structure |
|---|---|
| Anywhere | Is more than 200 feet above ground level at its site |
| Within 20,000 feet of a public-use or military airport whose longest runway is more than 3,200 feet | Exceeds a 100:1 slope from the nearest point of the nearest runway |
| Within 10,000 feet of a public-use or military airport whose longest runway is 3,200 feet or less | Exceeds a 50:1 slope from the nearest point of the nearest runway |
| Within 5,000 feet of a public-use or military heliport | Exceeds a 25:1 slope from the nearest point of the landing and takeoff area |
| On a public-use, military or federal airport or heliport, or one with an FAA instrument approach | Is proposed at all, regardless of height |
A 100:1 slope rises one foot per 100 feet of distance from the runway’s elevation, so a site above the runway has less room. New roads and railroads count as construction too. Part 77 raises a traverse way by the height of the vehicles it carries (17 feet for an Interstate highway, 15 feet for other public roads, 10 feet or the tallest normal vehicle for a private road, and 23 feet for a railroad) before testing it against the same criteria.1 A new site entrance, heavy-haul road or rail spur close to a runway can need its own filing; see heavy-haul access.
Some objects are exempt, including antennas of 20 feet or less that do not increase the height of another antenna structure, and objects shielded by existing structures or terrain in a congested area.1 The FAA’s Obstruction Evaluation / Airport Airspace Analysis (OE/AAA) website offers a Notice Criteria Tool that checks coordinates, site elevation and height against these rules, a fast first screen for any site within a few miles of an airport.3
Fig. 1Height that meets the notice surface by distance
- 2,000 ft from runway20
- 5,000 ft (about 1 mile)50
- 10,000 ft100
- 15,000 ft150
- 20,000 ft200
feet above runway elevation
03How the Form 7460-1 process works
- 01Prepare surveyed coordinates and elevations for each structure and crane position; small elevation errors change the result.
- 02File FAA Form 7460-1, Notice of Proposed Construction or Alteration, through OE/AAA at least 45 days before construction begins or before an application for a construction permit is filed, whichever is earliest.4
- 03The FAA studies the proposal against obstruction standards, instrument procedures, radar and navigational aids, and may circulate it for public comment if there is a potential hazard.
- 04The FAA issues a determination of no hazard, often with marking and lighting conditions, or a notice of presumed hazard that can lead to negotiation over height or location.
- 05File Form 7460-2, the supplemental notice, when the determination calls for it or the structure exceeds 200 feet; if the determination sets no deadline, it is due within 5 days after the structure reaches its greatest height.9
A determination of no hazard expires 18 months after its effective date unless it is extended, revised or terminated, or sooner if the project is abandoned.5 An extension can be requested at least 15 days before the expiration date, provided actual structural work has not started.10 On phased campuses, track expiration dates and refile as designs change.
Marking and lighting conditions point to AC 70/7460-1, the FAA’s obstruction marking and lighting circular. The 1M edition, in effect since 2020, was superseded by AC 70/7460-1N, dated August 11, 2026, so check specifications against the current version.8
04Cranes and other temporary structures
Part 77 applies to temporary construction equipment as well as permanent structures, and on a data center job the crane is usually the tallest object on site. Airport crane guidance tells sponsors to file each crane at the maximum height it will reach and to check separately whether the permanent building needs its own filing.3 A crane determination covers that crane at that location and height; it does not study the building the crane is erecting.11
Crane determinations carry their own conditions and expiration dates. Moving a crane or raising it beyond the studied height can void the determination and require a new filing, and the letter states what supplemental notice the FAA expects.11 Some airports also run their own crane notification procedures.
On a multi-building campus, cranes move between pads and each new position or height can need its own case, so build the lift plan into the construction timeline early.
05Obstruction standards and imaginary surfaces
Filing notice is not the same as being a hazard. Part 77 also sets obstruction standards. An object is an obstruction if it is taller than 499 feet above ground; if, within 3 nautical miles of an airport whose longest runway exceeds 3,200 feet, it is taller than 200 feet above ground or the airport elevation, whichever is higher, a limit that rises 100 feet per additional nautical mile up to 499 feet; or if it penetrates one of the airport’s imaginary surfaces.12
The imaginary surfaces surround each runway: a primary surface along the runway, a horizontal surface 150 feet above the established airport elevation, a conical surface that slopes up from its edge at 20:1 for 4,000 feet, approach surfaces extending off each runway end, and transitional surfaces rising at 7:1 from the sides of the primary and approach surfaces.12 A structure that penetrates them is an obstruction and gets closer review, but the FAA can still find it is not a hazard after evaluating its effect on flight procedures.
The approach surfaces off runway ends are the most restrictive: a site in line with a runway faces lower limits than one the same distance to the side, and the runway protection zone adds land use limits on top of height.
Fig. 2Where airport height limits bite hardest
Transitional and horizontal
Side slopes and a surface 150 ft above the field cap heights.
Most restrictive
Approach surface and runway protection zone: low limits, use controls.
Usually notice only
Often clears the surfaces; still file if above the notice slope.
Watch the approach path
Tall cranes, stacks and plumes can still draw comment.
Off to the side ← Position relative to runway → In line with runway end
06Airport issues beyond height
- Wildlife attractants: FAA guidance recommends keeping hazardous wildlife attractants, including open water, 5,000 feet from airport operating areas at airports serving piston aircraft, 10,000 feet at airports serving turbine aircraft, and 5 statute miles where wildlife could be drawn across approach or departure airspace.713 It favors detention basins that drain within about 48 hours and stay dry between storms.7 Maryland goes further near BWI and Martin State airports, calling for 24-hour drawdown after 1- and 2-year storms.14
- Exhaust and thermal plumes: Part 77 addresses the height of a stack, not the plume above it, but FAA guidance identifies thermal exhaust plumes as a distinct hazard for aircraft taking off, landing or flying the traffic pattern, even though it judges the overall risk low.15 Generator stacks, cooling towers and heat rejection equipment near an airfield may come up in review or local zoning.
- Glare and lighting: FAA land use guidance lists glare, smoke and steam among the conflicts to manage near airports, so reflective roofs, solar arrays and unshielded lighting near approach paths may need attention.2
- Electromagnetic interference: large metal structures and some equipment can affect radar and navigational aids, which the FAA considers in its study.
- Military airspace: generation and transmission projects filed with the FAA, such as on-site power plants or new transmission lines, also go through the Department of Defense Siting Clearinghouse, which reviews them for effects on training routes, radar and other military operations.16
Stormwater strategy, generator placement and cooling equipment all interact with the airport, so raise them during layout rather than after engineering; see stormwater management for data center campuses and backup generators and fuel sizing.
07Local airport zoning and state rules
The FAA does not issue building permits or control land use off the airport; its own land use guidance says it lacks direct control there, and its role is advisory.2 Local governments hold that power: state law lets cities and counties adopt airport zoning that keeps incompatible uses and heights away from airports.6 Many communities have airport overlay or height hazard zoning that turns the FAA surfaces into enforceable limits, sometimes with noise and safety zone rules, and some states run their own airport hazard review.
Runway protection zones, the trapezoids off each runway end, exist mainly to protect people and property on the ground. FAA land use guidance treats concentrations of people or property in them as incompatible, and airports try to control them outright, so development there is usually discouraged or blocked.2
Fig. 3FAA determination vs. local airport zoning
FAA Part 77 determination
- Triggered by the notice criteria in 14 CFR 77.9
- Studies effects on air navigation and flight procedures
- Can add marking and lighting conditions
- Advisory for off-airport land; issues no building permit
- Lapses after 18 months unless extended
Enforceable
Local airport zoning
- Adopted by cities and counties under state law
- Turns airspace surfaces into height limits
- Can restrict uses in safety zones and runway protection zones
- Enforced through zoning and building permits
That means airspace belongs in zoning for data centers, data center overlay districts and the data center permitting process, not just in a separate FAA track.
08Screening a site near an airport
- 01Map every public-use, military and federal airport and heliport within about 4 miles (20,000 feet), with runway lengths and runway ends.
- 02Run the Notice Criteria Tool for the tallest permanent structure, the highest stack or mast, each crane position and any new road or rail spur.
- 03Check whether the site sits under an approach surface or inside a runway protection zone.
- 04Pull the local airport overlay or height hazard ordinance and any state airport hazard rules.
- 05Review stormwater, cooling and generator layouts against wildlife and plume concerns.
- 06If on-site generation or new transmission is planned, expect Siting Clearinghouse review of those filings.
- 07Build the 45-day filing lead time and the 18-month determination life into the schedule.
When we screen sites near airports, we run the notice criteria for the tallest likely structures and crane positions and check the local overlay at the same time. To have a specific parcel checked, get a site reviewed.
Common questions
Does a data center need FAA approval?
Not always. The FAA requires notice under 14 CFR Part 77 for structures over 200 feet tall, and for shorter structures near public-use or military airports and heliports that exceed sloped notice surfaces.1 Many rural data centers fall outside these criteria. Near airports, the building, stacks, rooftop equipment, transmission structures and cranes may each need a filing, while local airport zoning sets the enforceable limits.
How far from an airport do FAA height rules apply?
The notice criteria extend 20,000 feet from public-use or military airports with a runway longer than 3,200 feet, 10,000 feet from airports with shorter runways, and 5,000 feet from heliports. Within those distances, notice is required if a structure exceeds a 100:1, 50:1 or 25:1 slope from the nearest runway or landing area. Anything over 200 feet above ground needs notice regardless of location.1
Do construction cranes need FAA review?
Yes, when they meet the Part 77 notice criteria. Cranes are filed as temporary structures at the maximum height they will reach, and they often reach well above the finished building. Each filing is due at least 45 days before the crane goes up, and moving or raising a crane beyond what was studied needs a new filing.
How long is an FAA determination of no hazard valid?
Generally 18 months from its effective date, unless it is extended, revised or terminated, or the project is abandoned first.5 An extension can be requested at least 15 days before expiration, provided actual structural work has not started.
Notes
- 1.Legal Information Institute, Cornell Law School, “14 CFR § 77.9, Construction or alteration requiring notice,” n.d. law.cornell.edu
- 2.Federal Aviation Administration, “AC 150/5190-4B, Airport Land Use Compatibility Planning,” 2022. faa.gov
- 3.Mineta San José International Airport, “SJC Crane Policy: 7460-1 OE/AAA Tutorial,” n.d. flysanjose.com
- 4.Federal Aviation Administration, “FAA Form 7460-1, Notice of Proposed Construction or Alteration,” n.d. faa.gov
- 5.Legal Information Institute, Cornell Law School, “14 CFR § 77.33, Effective period of determinations,” n.d. law.cornell.edu
- 6.Iowa Department of Transportation, “Land Use Regulation,” n.d. iowadot.gov
- 7.Federal Aviation Administration, “AC 150/5200-33C, Hazardous Wildlife Attractants on or near Airports,” 2020. faa.gov
- 8.Federal Aviation Administration, “AC 70/7460-1N, Obstruction Marking and Lighting,” 2026. faa.gov
- 9.Legal Information Institute, Cornell Law School, “14 CFR § 77.11, Supplemental notice requirements,” n.d. law.cornell.edu
- 10.Legal Information Institute, Cornell Law School, “14 CFR § 77.35, Extensions, terminations, revisions and corrections,” n.d. law.cornell.edu
- 11.Federal Aviation Administration (filed with the Connecticut Siting Council), “Determination of No Hazard to Air Navigation for Temporary Structure, Aeronautical Study No. 2023-ANE-5222-OE,” 2023. portal.ct.gov
- 12.Legal Information Institute, Cornell Law School, “14 CFR Part 77, Subpart C: Standards for Determining Obstructions to Air Navigation or Navigational Aids or Facilities,” n.d. law.cornell.edu
- 13.Federal Aviation Administration, “Wildlife Hazards,” n.d. faa.gov
- 14.Maryland Aviation Administration, “Stormwater Management Design Guidance,” n.d. maa.maryland.gov
- 15.Federal Aviation Administration, “Technical Guidance Assessment Tool: Thermal Exhaust Plume Impact,” n.d. faa.gov
- 16.U.S. Department of Defense, Military Aviation and Installation Assurance Siting Clearinghouse, “The Clearinghouse Review Process,” n.d. dodclearinghouse.osd.mil
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Zoning, permitting & community
- Community Engagement and Local Concerns About Data Centers
- Data Center Tax Incentives: What to Look For
- Noise, Setbacks and Buffers for Data Centers
- Development Agreements for Data Center Projects: What They Cover
- Annexation, Jurisdiction and Utility Service Areas for Data Center Sites
- Data Center Moratoriums and Local Restrictions: How to Screen for Them
- Building and Fire Codes for Data Centers: IBC, NFPA 75 and 76, NFPA 855
- Data Center Sales Tax Exemptions by State: Thresholds, Pauses and Repeals (2026)
- Public Hearings for Data Center Projects: Notice, Testimony and How to Prepare
- Comprehensive Plans and Future Land Use Maps for Data Center Sites
- Traffic Impact Studies for Data Centers: Trip Generation, Construction Traffic and Road Improvements
- Impact Fees and Utility Connection Fees for Data Centers: How They Work and What Is Negotiable
- Contested Data Center Projects: Lessons From Prince William, Peculiar, Tucson and Other Public Fights
- State Data Center Legislation: 2025–2026 Trends in Tariffs, Incentives, Water and Moratoriums
- Data Center Architectural and Visual Standards: Facades, Screening, Lighting and Height
Guide 1 of 20 in Zoning, permitting & community · all 242 guides · glossary · calculators
