Key takeaways
- Diligence confirms facts; it should rarely be the first time a major issue appears.
- Order long-lead items first: utility studies, wetland delineation and the Phase I ESA, which has a limited shelf life under federal rules.3
- Title and survey often reveal easements and pipelines that cut buildable area, and the 2026 ALTA/NSPS standards put more weight on documentation.4
- Get power, water and zoning answers in writing, and read the large-load tariff: minimum bills, collateral and exit fees now come with capacity.5
- Track every item against the diligence deadline in the purchase or option agreement.
01How to use this checklist
Diligence starts once a site is under contract or option, and it runs against a deadline. Most agreements give the buyer a defined due diligence period to investigate and walk away. That clock makes sequencing important. Items that take the longest, or that could kill the deal outright, should start on day one. Our guide to diligence periods and purchase contingencies covers how those terms are negotiated.
This checklist assumes a feasibility study has already been done. If it has not, diligence tends to become an expensive way of discovering basic problems. Each item below lists what to obtain and the kinds of findings that should trigger a closer look.
Fig. 1Illustrative diligence schedule
Illustrative- Zoning verification
- Phase I ESA
- Title and ALTA survey
- Geotechnical borings
- Wetland delineation and JDSeasonal; Corps timing varies by district
- Utility load studyOften runs past the period
02Title, survey and ownership
| Item | What to obtain | Watch for |
|---|---|---|
| Title commitment | Commitment with copies of all recorded exceptions | Easements, restrictive covenants, liens, unclear vesting |
| ALTA/NSPS survey | Survey under the 2026 standards, with selected Table A items and easements plotted4 | Gaps or overlaps between parcels, encroachments, unplotted rights-of-way |
| Mineral and subsurface rights | Search of severed mineral, oil, gas or other subsurface interests | Rights that allow surface access or drilling |
| Pipelines and transmission | Location and width of every utility and pipeline easement | Easements that split the site or limit crossings |
| Access | Confirmation of legal access to a public road | Landlocked parcels, access only by private easement |
The 2026 ALTA/NSPS Minimum Standard Detail Requirements were adopted in October 2025 and took effect on February 23, 2026, replacing the 2021 version; a survey contracted on or after that date generally follows the new standards.1 ALTA describes refined definitions, clarified responsibilities, expanded documentation requirements and notable changes to Table A, so confirm the current Table A list with the surveyor, title company and lender rather than reusing an old order form.4
On assembled sites, each parcel needs its own title commitment review, and the survey should confirm the parcels are contiguous with no strips held by others. Our guides to parcel assembly and title and ALTA surveys cover the common gaps.
03Power and utility confirmation
Power diligence turns feasibility indications into commitments, or as close to commitments as the utility will provide during the diligence period. Formal answers usually come through the large-load interconnection process, and that process often runs longer than a diligence period: Wood Mackenzie reported in 2025 that data center and manufacturing requests had packed load queues and lengthened waits.6 Buyers commonly negotiate extensions tied to utility milestones for this reason.
The process itself is changing. In June 2026 FERC issued six show-cause orders directing PJM, SPP, NYISO, MISO, CAISO and ISO-NE, and their transmission owners, to justify or reform their large-load interconnection rules.7 Ask the utility which rules will govern the request and how pending changes could affect it.
- Submit a load request or study application as early as the utility allows, with a realistic load ramp.
- Confirm the serving substation, voltage and the utility’s view of available capacity.
- Identify required upgrades, who pays for them and their indicated timing, including lead times for transformers and other major equipment.
- Identify the tariff that will apply and its minimum bill, collateral and exit terms.
- Get written correspondence where possible: capacity letters, study results or meeting summaries. A will-serve letter is often conditional.
- Locate land for an on-site substation and confirm the utility’s requirements for it.
- Check whether the site sits in a regulated utility territory or a retail choice area, as this changes the process.
Fig. 2One large-load tariff: AEP Ohio
- new or expanded data center loads covered
- >25 MW
- maximum minimum-demand share of contract capacity
- 85%
- of total minimum charges, posted as collateral
- 50%
- of minimum charges as the exit fee
- 3 years
Equipment can control the date even when capacity exists. Wood Mackenzie’s 2025 survey found standard large power transformers averaging 128 weeks for delivery, and it estimated a 30% shortfall in U.S. power transformer supply that year.9
04Environmental and physical condition
| Item | What to obtain | Watch for |
|---|---|---|
| Phase I ESA | Report under ASTM E1527-21, recognized by EPA for all appropriate inquiries since February 13, 20232 | Recognized environmental conditions that call for a Phase II |
| Wetland delineation | Field delineation, then a jurisdictional determination if needed | Jurisdictional wetlands or streams that mapped data missed or overstated10 |
| Floodplain | FEMA FIRM review, survey elevations against base flood elevation | Zone A/AE in building areas, floodway (needs a no-rise analysis), map revisions pending11 |
| Geotechnical | Borings and a preliminary geotechnical report | Shallow rock, karst, expansive clays, high groundwater |
| Protected species | Database review and habitat assessment where indicated | Listed species habitat that limits clearing or timing |
| Cultural resources | Records search and survey where required | Known archaeological or historic sites |
A Phase I ESA is the standard first step for contamination risk and supports certain liability protections for buyers. Timing matters. Under the all appropriate inquiries rule, a Phase I completed within 180 days before acquisition can generally be used as is; between 180 days and one year, the interviews, lien search, government records review, site visit and environmental professional’s declaration must be updated; after one year, a new assessment is needed.3 Our Phase I ESA guide covers what it includes and when a Phase II follows.
Wetland work is seasonal in many regions, and a jurisdictional determination from the U.S. Army Corps of Engineers can take time, so start it early. Federal jurisdiction is also in flux. As of 2026, the revised 2023 definition of “waters of the United States” applies in some states and the pre-2015 definition in others,12 and in September 2026 EPA and the Army sought more input on the definition they proposed in November 2025.13 Ask the wetland consultant which definition the Corps district is applying.
05Zoning, entitlement and local approvals
- Zoning verification: confirm the current district and whether data centers are permitted by right, conditionally or not at all. A zoning verification letter from the local government helps where one is available. See zoning for data centers.
- Development standards: height limits, setbacks, lot coverage, landscaping, screening and parking.
- Noise rules: applicable ordinances and property-line limits, especially near homes.
- Comprehensive plan: whether the future land use map supports industrial or data center use.
- FAA review: whether structures or cranes would require filing Form 7460-1 under 14 CFR Part 77, which must reach the FAA at least 45 days before construction starts.14
- Incentives: eligibility for state or local incentives and the steps needed to apply before commitments are made.
- Approval history: how similar projects have fared before the local planning body. Data Center Watch estimated that local opposition blocked or delayed about $64 billion of U.S. projects from May 2024 to March 2025.15
06Water, fiber, gas and access
- Water: confirm source, available capacity and the provider’s willingness to serve the planned cooling load. Note any need for new mains or wells.
- Wastewater: confirm discharge capacity, pretreatment rules and whether blowdown from cooling can be accepted.
- Fiber: identify carriers, distance to long-haul and metro routes, and the feasibility of two physically diverse entry paths.
- Natural gas: if on-site generation is planned, confirm pipeline proximity, pressure and the operator’s process for new taps.
- Roads: confirm that roads and bridges can carry construction traffic and heavy loads such as large transformers.
Water use draws growing public attention. Berkeley Lab estimated that U.S. data centers consumed about 17 billion gallons of water directly for cooling in 2023, and projected that the figure could double or quadruple by 2028.16 Providers may ask detailed questions about peak and annual demand, so bring the cooling design to the conversation. Our guide to data center water requirements covers the trade-offs.
Many of these answers come as will-serve letters or carrier quotes. They are often conditional, so read the conditions carefully.
07Tracking diligence against the deadline
Keep a single tracker with each item, the responsible party, the date ordered, the expected date and the status. Review it weekly. When an item reveals a problem, record the cost or schedule effect and whether it can be cured, priced or negotiated.
Before the diligence period ends, the buyer needs a clear position on every item that affects value or schedule. That position becomes the basis to proceed, renegotiate, extend or terminate.
Separate findings into three groups. Cured items are resolved and need no further action. Priced items have a known cost, such as extra grading or a utility contribution, that can be reflected in the price or budget. Open items still carry uncertainty, usually around power timing or approvals. Open items drive most extension requests, so document what would close each one and how long it is expected to take.
Fig. 3Cured, priced or open
Closed
Cured
- Resolved by seller or buyer action
- Example: a lien released of record
- No further cost or schedule effect
Priced
- Cost or delay is known
- Example: extra grading or a utility contribution
- Reflected in price, credit or budget
Drives extensions
Open
- Outcome still uncertain
- Example: utility study results not yet issued
- Basis for extension or termination decisions
Watch the dates inside the reports too. A Phase I that was current when ordered may need updates if closing slips past 180 days.3 If the schedule is tight, BlackForge can help sequence the work; get a site reviewed.
Common questions
How long is a typical due diligence period for data center land?
It is set by negotiation and varies widely. Data center buyers often seek longer periods than conventional land buyers because utility studies, wetland work and entitlement checks take time. It is common to see initial periods with paid extensions tied to milestones such as utility study results or zoning approvals. The right length depends on how much was learned in feasibility before signing.
What diligence items take the longest?
Utility capacity confirmation and interconnection studies usually take the longest, and load queues have lengthened as data center requests have grown.6 Wetland delineation and jurisdictional determinations come next, depending on the season and agency workload. Rezoning or special use approvals, if needed, can also take months. A Phase I ESA, title commitment and survey are usually faster but should still be ordered on the first day.
Is a Phase I ESA required for data center land?
It is not required by law for every transaction, but it is standard practice for commercial land deals and lenders typically expect one. A Phase I ESA prepared under ASTM E1527-21, which EPA recognized for the “all appropriate inquiries” rule effective February 13, 2023, supports certain buyer liability protections under federal law.2 It must be current at acquisition: generally within 180 days, or up to one year with specific updates.3
What does an ALTA survey show that a regular survey does not?
An ALTA/NSPS land title survey follows national standards and is tied to the title commitment. It plots recorded easements and rights-of-way, shows encroachments and improvements, and can include optional Table A items selected by the client. The 2026 standards, effective February 23, 2026, changed Table A and expanded documentation requirements, so check the current list.4 For data center sites, it is the most reliable way to see how easements and pipelines cut into the buildable area.
What happens if due diligence finds a problem?
The buyer has several options, depending on the agreement. It can ask the seller to cure the issue, renegotiate price or terms to reflect the cost, request an extension to investigate further, or terminate within the diligence period. Title objections usually follow a defined notice-and-cure process. The key is raising issues in writing before the relevant deadline passes.
Notes
- 1.The American Surveyor, “The 2026 Minimum Standard Detail Requirements for ALTA/NSPS Land Title Surveys,” 2026. amerisurv.com
- 2.Quarles, “New Phase I Standard ASTM E1527-21 Authorized for All Appropriate Inquiries Starting February 13, 2023,” 2022. quarles.com
- 3.State of Indiana, “When does a Phase I Environmental Site Assessment (ESA) report need to be updated to satisfy all appropriate inquiry requirements?,” n.d. faqs.in.gov
- 4.American Land Title Association, “Why the ALTA/NSPS Land Title Survey Standards Matters,” n.d. alta.org
- 5.AEP Ohio, “Data Center Tariff,” n.d. aepohio.com
- 6.Wood Mackenzie, “US power struggle: How data centre demand is challenging the electricity market model,” 2025. woodmac.com
- 7.Foley & Lardner, “FERC Issues Six Tailored “Show Cause” Orders to Accelerate Large Load Interconnection,” 2026. foley.com
- 8.Vorys, “Public Utilities Commission of Ohio Authorizes Tariff for AEP Ohio’s Data Center Customers, Requires End of Moratorium on New Services for Data Centers,” 2025. vorys.com
- 9.pv magazine USA, “U.S. transformer market faces severe supply constraints as lead times extend to four years,” 2026. pv-magazine-usa.com
- 10.U.S. Fish and Wildlife Service, “Wetlands Data Limitations, Exclusions and Precautions,” n.d. fws.gov
- 11.FEMA Region X (hosted by the Utah Floodplain Management Program), “FEMA No-Rise Floodway Analysis Requirements,” 2013. floodhazards.utah.gov
- 12.Harvard Law School Environmental and Energy Law Program, “Regulatory Tracker: Defining Waters of the United States (WOTUS),” n.d. eelp.law.harvard.edu
- 13.U.S. Environmental Protection Agency, “EPA and Army Seek Additional Input on Proposed Waters of the U.S. Definition While Advancing Toward Durable Final Rule,” 2026. epa.gov
- 14.Federal Aviation Administration, “Notification of Proposed Construction or Alteration on Airport Part 77,” n.d. faa.gov
- 15.Data Center Watch, “$64 billion of data center projects have been blocked or delayed amid local opposition,” 2025. datacenterwatch.org
- 16.Lawrence Berkeley National Laboratory, “2024 United States Data Center Energy Usage Report,” 2024. eta-publications.lbl.gov
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Feasibility, diligence & deals
- Why Data Center Sites Fail: Common Red Flags
- How to Screen a Land Portfolio for Data Center Potential
- Selling or Leasing Land to a Data Center Developer
- How Long Does Data Center Site Selection Take?
- Desktop Screening vs. Field Assessment for Data Center Sites
- How to Read a Data Center Feasibility Report
- Site Scoring and Weighting Methods for Data Center Selection
- GIS Data Sources for Data Center Site Selection: What Each Layer Shows
- Letters of Intent for Data Center Land Deals: Binding Terms, Exclusivity and Pitfalls
- How Developers Underwrite Data Center Sites
- Data Center Construction Costs per MW and the Site Factors That Drive Them
- Confidentiality, NDAs and Code Names in Data Center Site Searches
- What to Check on a Data Center Site Visit: A Field Checklist
- Public Data Sources for Power Capacity: EIA, FERC, OASIS, Queues and Hosting Maps
Guide 2 of 18 in Feasibility, diligence & deals · all 242 guides · glossary · calculators