Data Center Large-Load Power Tracker

How US utilities and states are setting rules for data-center-sized power requests: special tariffs, minimum payments, contract terms and collateral. Compiled from public filings, with a source on every row.

Last checked October 22, 202639 utilities · 32 states23 state measuresDownload CSV

Why we give this away

Anyone could pull this. That’s the point.

Every row here comes from public tariffs, regulatory orders and news that anyone can read. We compile it because it’s useful and should be easy to find. But a published tariff is the same for every site in a utility’s territory. It tells you the terms if power is available, not whether your site can get it.

This tracker · Public, free

  • A utility’s published rules for large new loads
  • The same answer for every site in that utility’s territory
  • What the terms are if power is available
  • Compiled from filings anyone can read

A BlackForge report · Site-specific

  • Whether a specific parcel can actually be served, and roughly when
  • Substation headroom and the realistic connection path
  • Gas, water, fiber, buildable land and zoning, checked together
  • Built and refreshed for your load, your timeline and your parcels

By utility

Large-load rules, utility by utility.

  • Approved25
  • Settlement filed3
  • In review6
  • No specific rule found5

Showing 39 of 39 utilities

By state

State laws and rulemakings.

  • AL · enacted · 2026-10

    Act 2026-610

    Sends Alabama Power contracts with data centers of 150 MW or more to PSC review to confirm prices recover the cost of serving them; effective October 1, 2026.

    NBC 15 (2026); ABC 33/40 (2026)

  • AZ · in review · 2026-04

    Corporation Commission large load users workshop (Docket E-00000A-25-0069)

    Commission favors utility high load factor tariffs plus individual service agreements with long terms, minimum bills, collateral and termination terms.

    Arizona Corporation Commission (2026)

  • CA · enacted · 2025

    SB 57 (2025)

    Directs the CPUC to assess whether utility costs for new data center load shift costs to other customers, with the assessment due January 1, 2027.

    Mayer Brown (2025)

  • CA · enacted · 2026-09

    SB 886 and related data center package (2026)

    Directs the CPUC to set data center tariffs by January 1, 2028 so operators pay their upgrade and generation costs, with a 10-year early termination fee.

    Mayer Brown (2026); Ballard Spahr (2026)

  • IN · enacted

    House Enrolled Act 1007 (2025)

    Creates a fast approval path for generation built to serve large loads, with the large-load customer reimbursing at least 80% of its cost.

    Indiana Capital Chronicle (2025)

  • LA · enacted · 2025-12

    LPSC 'Lightning' directive on generation for large loads (December 2025)

    Lets utilities skip competitive bidding for new generation serving large loads that sign service agreements of at least 15 years.

    E&E News (2025); Louisiana Illuminator (2025)

  • MD · enacted

    Next Generation Energy Act (2025)

    Requires utilities to adopt PSC-approved rate schedules for customers of 100 MW or more with load factors above 80%, so those customers cover the grid costs they cause.

    Maryland Department of Legislative Services (2025); Maryland Department of Legislative Services (2026)

  • MI · proposed · 2026-06

    Senate Bills 1046 and 1047 (2026)

    Would require permits and hearings for high water use by data centers and address electricity rates and large-load utility classes; not passed as of latest reporting.

    Michigan Senate Democrats (2026)

  • MN · enacted · 2025-06

    HF 16, Chapter 12, 2025 First Special Session (data centers)

    Sets annual fees of $2 to $5 million for large data centers, adds water permit review and lets regulators review their utility tariffs or supply deals.

    Minnesota House Research (2025); Minnesota House of Representatives (2025)

  • MO · enacted · 2025-04

    Senate Bill 4 (2025)

    Requires large investor-owned utilities to offer special tariffs for customers above 100 MW so their costs are not shifted to other customers.

    POWER Magazine (2026); Missouri Public Service Commission (2026)

  • NC · proposed · 2026-06

    Senate Bill 730, Ratepayer Protection Act (House version, 2026)

    Would require 15-year power contracts for data centers above 100 MW, closed-loop cooling and an end to local incentives; it passed the House and returned to the Senate.

    NC Newsline (2026); WUNC (2026)

  • NJ · enacted · 2026-07

    S731 / A796 (2026)

    Directs the BPU to set a separate tariff for data centers of 50 MW or more, with financial security for at least 85% of requested supply over 10 years and curtailment before homes in emergencies.

    New Jersey Monitor (2026); Data Center Dynamics (2026); Insider NJ (2026)

  • NY · enacted · 2026-07

    Executive Order 62 (2026)

    Pauses discretionary state environmental permits for data centers that can use 50 MW or more until a statewide environmental review is complete.

    Foley & Lardner LLP (2026); Davis Wright Tremaine LLP (2026)

  • NY · in review · 2026-02

    PSC Case 26-E-0045, interconnection reforms for large loads

    Proceeding to make large new loads pay for the grid upgrades that benefit them, using a beneficiary-pays approach to protect other customers.

    New York State Public Service Commission (via RTO Insider) (2026)

  • OK · enacted · 2026-05

    House Bill 2992, Data Center Consumer Ratepayer Protection Act of 2026

    Requires all electricity providers, including co-ops and municipal systems, to set separate terms for large customers such as data centers.

    KGOU (2026); Oklahoma Voice (2026)

  • OR · enacted · 2025-06

    POWER Act, House Bill 3546 (2025)

    Requires a separate rate class for facilities of 20 MW or more, with contracts of at least 10 years and minimum payments regardless of use.

    Data Center Dynamics (2025); Oregon Public Utility Commission (2026)

  • PA · enacted · 2026-05

    PUC large-load model tariff (Docket M-2025-3054271)

    A nonbinding model for loads above 50 MW (or 100 MW in aggregate) that assigns upgrade costs they cause, sets exit fees, and has each utility file its own tariff.

    Pennsylvania Public Utility Commission (2026); Utility Dive (2026)

  • TX · in review · 2026-08

    Governor's data center audit directive (August 2026)

    Directs the PUCT and ERCOT to audit data center projects in the interconnection process, covering power use, water, incentives and ownership, before more advance.

    Office of the Texas Governor (2026)

  • TX · enacted · 2026-09

    PUCT large-load interconnection rule, 16 TAC §25.194 (2026)

    Requires ERCOT loads of 75 MW or more to post $50,000 per MW of requested capacity as security before interconnection studies begin.

    White & Case (2026); Foley & Lardner (2026)

  • TX · enacted · 2025-06

    Senate Bill 6 (2025)

    ERCOT loads of 75 MW or more must show site control, pay a study fee of at least $100,000, disclose backup generation and be able to curtail in emergencies.

    McGuireWoods (2025); Texas Legislature (2025)

  • UT · enacted · 2026-01

    Senate Bill 132 (2025) and PSC rule R746-318

    Loads of 100 MW or more get individual contracts; if the utility cannot serve without major investment, the customer may seek its own supply.

    Latitude Media (2025); Public Service Commission of Utah (2026)

  • WA · in review · 2026-04

    UTC large load inquiry, Docket UE-260162 (2026)

    State regulators are studying rates, cost sharing and interconnection conditions for large loads, aiming for a policy statement; HB 2515 (20 MW+) died in 2026.

    Washington Utilities and Transportation Commission (2026); Davis Wright Tremaine (2026)

  • WV · enacted · 2025-04

    House Bill 2014, Power Generation and Consumption Act (2025)

    Lets certified high impact data centers of 90 MW or more run on their own behind-the-meter microgrids and exempts them from local zoning and building permits.

    West Virginia Watch (2025); West Virginia Center on Budget and Policy (2025)

How it’s built

Sources, dates and limits.

Rows are compiled from utility tariffs, state commission orders and dockets, utility and regulator announcements, and trade press. Each row links its sources. The whole tracker was last checked on October 22, 2026.

Many of these rules are in active proceedings and change often. Confirm current terms with the utility or the commission docket before relying on them. This is a public reference, not legal, regulatory or engineering advice. “No specific rule found” means we found no published large-load rule, not that none exists.

Free to reuse under CC BY 4.0 with credit to BlackForge Data Centers. Missing a utility, or spotted a change? Tell us.

New to these terms? Start with our power and interconnection guides or the power calculator.

The tariff is public. Whether your site can get power isn’t.

That takes parcel-level screening and verification, built for your load and timeline. Start with your situation.