Title Review and ALTA Surveys for Data Center Land

Title review and an ALTA/NSPS Land Title Survey together show what a buyer is actually acquiring: who owns the land, what liens and recorded rights burden it, and where boundaries, easements and encroachments sit on the ground.1 For data center land, they confirm the site is contiguous, has legal access and is free of rights that would block buildings, substations or utility routes. As of October 2026, new surveys are performed to the 2026 ALTA/NSPS standards, which took effect February 23, 2026, and the work centers on the commitment’s requirements and exceptions and on the optional Table A items ordered with the survey.2

Last reviewed · 9 min read · BlackForge Data Centers

Key takeaways

  • The title commitment states what the insurer will cover, what must be done before closing, and what it will not cover.
  • Schedule B-I lists requirements to meet; Schedule B-II lists exceptions, which become the risks the buyer accepts.1
  • The 2026 ALTA/NSPS standards replaced the 2021 edition on February 23, 2026, and added an optional summary table of observed potential encroachments (Table A Item 20).23
  • Table A items are optional add-ons; choose them for the data center use, not by habit, and check any lender’s required list.45
  • Access, contiguity and same-as-survey endorsements (ALTA 17, 19 and 25 series) address the risks that matter most on assembled campuses.6

01Why title and survey matter more for data center sites

Data center campuses are large, expensive and long-lived. A title or boundary problem that would be a nuisance on a small commercial lot can stop a campus: an easement under a planned substation, a gap between two assembled parcels, an access road that turns out to be private, or an old reservation that lets someone else use the surface. Lenders, investors and the utility will all want clean answers, often before they commit.

Title and survey work are usually ordered during the diligence period after a purchase agreement or option is signed. On a large site they take time, especially with many parcels or old records, so they belong early in the due diligence checklist, not at the end.

Fig. 1Title and survey in a land deal

  1. 01

    Order title

    Commitment plus copies of every exception document.

  2. 02

    Scope the survey

    Pick Table A items for the use and the lender.

  3. 03

    Survey fieldwork

    Boundary, easements, access and visible evidence.

  4. 04

    Object

    Buyer objects to title and survey matters in time.

  5. 05

    Cure and close

    Releases, agreements, endorsements, policy.

A common sequence. The surveyor works from the commitment, so order title first.1

02How a title commitment is organized

A title commitment is the insurer’s offer to issue a policy once its requirements are met. The ALTA commitment form used in most of the country has a jacket of printed terms, Schedule A, and Schedule B in two parts.1 Labels differ slightly between form versions, and some states use their own forms.

Main parts of a title commitment
PartWhat it containsWhat to do with it
Schedule AEffective date, proposed insured, policy amount, current vested owner, legal descriptionConfirm the owner matches the seller and the legal description matches the intended land
Schedule B-I (Requirements)What must happen before the policy issues: payoffs, releases, authority documents, recorded deedAssign each item to a party and track to closing
Schedule B-II (Exceptions)Matters the policy will not cover: standard exceptions plus recorded easements, restrictions, reservations, leasesGet copies of every document, review each one, and object to or clear the problematic ones
Conditions and noticesTerms governing the commitmentRead once; rarely deal-specific

The exceptions in Schedule B-II are the core of the review. Each one is a risk the buyer would take on. Standard exceptions, such as matters a survey would show or parties in possession, can often be removed or narrowed with a current survey and owner affidavits. Specific exceptions, such as a recorded pipeline easement or a mineral reservation, stay unless the underlying right is released or modified.

Objections and cure

Most purchase agreements give the buyer a window to object to title and survey matters, then give the seller a period to cure. Typical objections for data center land include unreleased mortgages, judgments, unplottable blanket easements, restrictive covenants that bar industrial use, encroachments and gaps in access. Severed minerals and easements are often the hardest items, as covered in mineral rights and easements. Recorded use limits are covered in conservation easements and deed restrictions.

03What an ALTA/NSPS Land Title Survey is

An ALTA/NSPS Land Title Survey is a boundary survey performed to minimum standards jointly adopted by the American Land Title Association and the National Society of Professional Surveyors.7 The standards are updated periodically. The current edition took effect on February 23, 2026, and supersedes the 2021 edition and all earlier versions.2 They set out what the surveyor must research, measure and show, so title insurers and lenders can rely on the result across states.

  • Boundary lines, monuments and the legal description, with any differences between record and measured dimensions.
  • Every plottable easement and right listed in Schedule B-II, located on the drawing, with notes on items that cannot be plotted.
  • Legal and physical access to public roads, which affects frontage and site entries.
  • Visible improvements, utilities and evidence of use, such as roads, fences, poles and pipeline markers.
  • Encroachments onto or from neighboring land, and gaps or overlaps with adjoining parcels.
  • The surveyor’s certification to the named parties, usually the buyer, lender and title insurer.

Summaries of the 2026 edition describe it as a refinement rather than an expansion: clearer reporting of utilities, encroachments, access and off-site features, renumbering and cleanup of some optional items, and no major new mandatory items.8 Check which edition your survey contract calls for, since a survey ordered under the 2021 standards may still be in progress.2

The surveyor works from the title commitment and the documents listed in it, so order title first and send the commitment and copies of the exception documents to the surveyor.

04Choosing Table A items for a data center site

Table A is a list of optional items the client can add to the minimum standard. The numbering and exact wording change between editions, so order by description and confirm against the current version.4 Some lenders publish their own required lists.5 For large data center sites, the items that usually earn their cost are:

  • Monuments set or found at major property corners (Item 1).
  • Flood zone classification based on the FEMA Flood Insurance Rate Map or a state or local equivalent, shown by scaled map location only (Item 3).4 A survey note is not a flood study; see floodplains and data center sites.
  • Gross land area, so the acreage in the deal is measured rather than taken from tax records (Item 4).
  • Topography or contours, often at a coarser interval for screening and finer later for design, or paired with LiDAR.
  • Zoning classification and setback requirements, where the client provides a zoning report or letter.
  • Evidence of underground and overhead utilities based on markings and plans.
  • Names of adjoining owners from current tax records, useful for assembly and notice requirements (Item 13).
  • Evidence of recent earth moving, construction or dumping.
  • Off-site easements or rights that benefit the property, such as access or utility easements across neighbors.
  • The new summary table of observed potential encroachments, setback issues and access issues (Item 20).3

Wetlands are no longer a standard item. The 2021 edition deleted the item for locating wetland delineation markers because it was unrelated to title, though a client can still negotiate it as an added item.910 In the 2026 edition, client-specified additions are numbered 21(a), 21(b) and so on, and engineering design survey work should be negotiated there as well.84 If a wetland delineation has been done, list it as a write-in item.

Fig. 2Table A changes in the last two editions

Effective Feb. 23, 2021

2021 edition

  • Wetland marker item (old Item 18) deleted
  • Plumb-walls item 10(b) deleted
  • Later items renumbered
  • Wetlands can still be a negotiated add-on

Effective Feb. 23, 2026

2026 edition

  • New Item 20: summary of observed conditions
  • Write-in items move to 21(a), 21(b)
  • Aerial imagery item (15) reworded
  • No major new mandatory items
Selected changes only. Confirm item numbers against the current official Table A.810

The new Item 20 table lists observed conditions such as potential encroachments without interpreting them or settling ownership, so the buyer’s attorney still decides what each one means.3 Items aimed at existing buildings, such as building dimensions, heights and parking counts, matter less on raw land but matter on industrial reuse sites. A careful scope saves time on a 500-acre survey, where each extra item can add field work.

05Title and survey for assembled, multi-parcel sites

Many data center campuses combine several parcels from different owners. Each parcel has its own title history, and the combined site has to work as one. The approach described in our guide to parcel assembly depends on getting this right.

  • One survey of the whole site, showing each parcel and the combined boundary.
  • A check for gaps (gores) and overlaps between adjoining legal descriptions, which are common in older rural records.
  • Contiguity confirmed on the survey and, where available, insured by an ALTA 19 series endorsement.6
  • Consistent treatment of easements that cross parcel lines.
  • Interior roads or rights-of-way that would split the site and may need to be vacated.

Combining parcels often also means a replat or lot consolidation before site plan approval, which our guide to subdivision and platting covers. The survey and the plat should use the same boundary.

Fig. 3Sample title and survey review

Illustrative
  • PassVestingAll three sellers match Schedule A on their parcels.
  • WatchContiguityA 6-foot gore between parcels 2 and 3 needs a quitclaim.
  • PassAccessParcel 1 fronts a county road; ALTA 17 requested.
  • WatchEasementsBlanket electric easement on parcel 2 to be fixed in place.
  • WatchMinerals1950s reservation; mineral title search ordered.
  • FailCovenantsRecorded restriction bars non-farm use on parcel 3.
Illustrative sample for a hypothetical three-parcel assembly. Not a real site.

06Policies and endorsements worth asking about

The buyer usually receives an owner’s policy, and any lender receives a loan policy. Endorsements extend coverage to specific risks. Availability and pricing vary by state, so ask the title company which apply.

  • Access: ALTA 17 covers loss if the land lacks physical access to a public right-of-way, and 17.1 covers indirect access over an easement for land not touching a public road.6
  • Contiguity: ALTA 19 for multiple parcels and 19.1 for a single parcel.6
  • Same as survey: ALTA 25 ties the policy’s legal description to the survey.6
  • Restrictions, encroachments and minerals: the ALTA 9 series, with separate forms for unimproved and improved land.6
  • Minerals and subsurface: the ALTA 35 series, including a 35.3 form for land under development with planned improvements.1112
  • Zoning coverage, sometimes tied to a specific use; confirm the use classification with the county as described in zoning for data centers.

When we assemble diligence on a site, we read the commitment and the survey together and map every exception that touches a likely building, substation or utility corridor. That list, more than the policy amount, tells you how clean the site really is. If you want a second look before the objection deadline, get a site reviewed.

CalculatorLand for a load →CalculatorGross to buildable →CalculatorLand option payments →

Common questions

What is the difference between Schedule B-I and Schedule B-II?

Schedule B-I lists requirements: the things that must happen before the title insurer will issue the policy, such as paying off mortgages, recording releases, delivering authority documents and recording the deed.1 Schedule B-II lists exceptions: matters the policy will not cover, such as recorded easements, restrictions, reservations and leases. Requirements get satisfied and disappear. Exceptions remain unless removed or modified, and become risks the buyer accepts.

Do I need an ALTA survey for data center land?

For a purchase of any size, almost always. Lenders and title insurers typically require one to remove standard survey exceptions and issue extended coverage, and some lenders publish their own Table A requirements.5 For data center sites, the survey also confirms boundaries, plots easements against planned buildings and substations, verifies access, and checks contiguity on assembled parcels. A simpler boundary survey may suffice for early screening but not for closing.

What changed in the 2026 ALTA/NSPS standards?

The 2026 standards took effect February 23, 2026, and replaced the 2021 edition.2 The main Table A change is a new optional Item 20, a summary table of observed potential encroachments, setback and access issues, with write-in items moved to Item 21.38 Commentators describe the rest as clarification and renumbering rather than added scope.

What are Table A items on an ALTA survey?

Table A items are optional additions to the ALTA/NSPS minimum standard that the client chooses and negotiates with the surveyor.4 They include things such as monuments, flood zone classification, gross land area, topography, zoning setbacks, utility locations and adjoining owners. Numbering changes between editions, so describe the items you need and confirm them against the current standard.

How long does title and survey work take on a large site?

It varies with acreage, the number of parcels, the age and quality of county records, terrain and the surveyor’s workload. A single clean parcel can move quickly, while a multi-owner rural assembly with old records and severed minerals can take much longer. Order title first, then send the commitment and exception documents to the surveyor promptly, and set diligence deadlines with that sequence in mind.

Notes

  1. 1.Stewart Title Guaranty Company, “Guidelines: Commitment - ALTA Commitment for Title Insurance 6-17-06 Revised (08-01-16),” 2016. assets.stewart.com
  2. 2.McGuireWoods, “Updated ALTA/NSPS Land Title Survey Standards Take Effect Feb. 23,” 2026. mcguirewoods.com
  3. 3.ALTA Land Survey, “Understanding the New Table A Item 20 in the 2026 ALTA/NSPS Standards,” 2026. altalandsurvey.com
  4. 4.National Society of Professional Surveyors, “2026 ALTA/NSPS Fillable Table A,” 2026. cdn.ymaws.com
  5. 5.Protective Life, “Survey Specifications: 2021 ALTA/NSPS Table A,” 2021. protective.com
  6. 6.Chicago Title, “ALTA Endorsements Used in Commercial Title Insurance A to Z,” n.d. commercialpartners.ctic.com
  7. 7.American Land Title Association, “Why the ALTA/NSPS Land Title Survey Standards Matters,” n.d. alta.org
  8. 8.ALTA Land Survey, “Key Changes Between the 2021 and 2026 ALTA/NSPS Standards,” 2026. altalandsurvey.com
  9. 9.NV5, “2021 ALTA Survey Requirements: Delineation of Wetlands Eliminated,” 2021. nv5.com
  10. 10.ArentFox Schiff, “ALTA/NSPS Update the Land Title Survey Standards,” n.d. afslaw.com
  11. 11.Stewart Title Guaranty Company, Virtual Underwriter, “PA 1360 ALTA 35.3-06 Minerals and Other Subsurface Substances-Land Under Development 10-1-17,” 2017. virtualunderwriter.com
  12. 12.Stewart Title Guaranty Company, “Guideline: ALTA Endorsement 35.1-06 (Minerals and Other Subsurface Substances - Improvements),” 2012. assets.stewart.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Terms in this guide

Related guides

More in Land & site fundamentals

Guide 10 of 23 in Land & site fundamentals · all 242 guides · glossary · calculators