Key takeaways
- In Virginia’s mature markets, business personal property tax on computer equipment is the largest local revenue source from data centers, with real estate tax second.1
- Loudoun County assesses data center computer equipment as a declining percentage of original cost; for tax year 2026, equipment bought in 2025 is assessed at 60% of cost.5
- Rates and depreciation schedules are policy choices: Prince William County raised its data center equipment rate from $3.70 to $4.15 per $100 for FY2026.6
- Abatements (such as Texas Chapter 312 agreements) and PILOT structures that put title in a public body can cut the bill for years, usually in exchange for investment and payment commitments.43
- Large data center tax bases can also reduce other revenue: in Virginia, higher local property wealth lowers a locality’s share of state school funding.7
01What gets taxed: land, buildings and equipment
Property tax on a data center campus falls into three buckets, and each one behaves differently over the life of the project.
- Land: taxed as real property. Before development it may carry an agricultural or other preferential assessment; conversion can trigger rollback taxes, covered in our guide to agricultural tax status and rollback taxes.
- Buildings and fixtures: taxed as real property. Data halls, electrical rooms, cooling plants and generators may be classed as real estate or personal property depending on state law and how they are attached.
- Computer equipment: servers, storage and network gear are usually taxed as business personal property, where a state taxes it at all.
Virginia’s Joint Legislative Audit and Review Commission (JLARC) found that localities with data centers collect substantial revenue from the industry, primarily from business personal property and real property taxes.1 In Prince William County, for tax year 2024, data centers’ real property produced more than $130 million and the computer and peripherals tax nearly $124 million, out of $280.2 million in total data center tax revenue.8
The equipment bucket is what makes data centers unusual. A warehouse of the same size holds little taxable personal property. A data hall can hold equipment worth several times the building, and because operators refresh servers every few years, the taxable equipment base keeps being replaced at near-new values. Not every state taxes it: some states exempt business personal property or data center equipment, so check the state rules before modeling revenue or cost.
02How assessors value data center property
Real property: the cost approach dominates
Assessors have three standard tools: the cost approach, sales comparison and the income approach. A Vorys analysis argues that the last two fit data centers poorly, because a data center tends to trade as an operating business, so sale prices and rents mix real estate value with the value of the enterprise.9 That leaves cost less depreciation as the usual method, and it is where many disputes land: which costs count, how fast components depreciate, and whether specialized systems carry functional or economic obsolescence.9
Virginia goes further and writes the method into its budget act: data center fixtures classified as real estate are to be valued by localities using the cost approach (cost less depreciation), not the income they generate, at 100% of fair market value.10
Equipment: percent-of-cost schedules
Business personal property is usually assessed by applying a depreciation schedule to original cost. Loudoun County calculates assessments as a percentage of original cost, including shipping, installation and sales tax, and starting with tax year 2026 requires filers to report capitalized costs by year of acquisition for the latest year and the prior five years.5 After a benchmarking study by PFM Group, the county raised the factors for newer data center equipment.511
Fig. 1Loudoun data center equipment assessment, TY2026
- Bought 202560
- Bought 202445
- Bought 202330
- Bought 202215
- Bought 202110
% of original cost
The schedule matters as much as the rate. JLARC noted that a locality’s take depends on its rate and how quickly it depreciates equipment, and that some Virginia localities cut their equipment rates sharply to attract data centers, which also cut the revenue they can collect.1
03The Loudoun County example
Loudoun County, Virginia shows what the equipment tax can do to a local budget. The county’s FY2026 budget materials state that data centers generate 38% of General Fund revenues.2 Computer equipment in data centers is taxed at the county’s general business personal property rate, the same rate that applies to many other businesses,12 which the county lists at $4.15 per $100 of assessed value for tax years 2026 and 2027.13
Fig. 2Data center tax revenue in two Virginia counties
- of Loudoun General Fund revenue from data centers
- 38%
- Loudoun general personal property rate per $100
- $4.15
- Prince William data center tax revenue, TY2024
- $280.2M
- Prince William data center equipment rate, FY2026
- $3.70 → $4.15
The county treats that revenue as volatile. Its Revenue Stabilization Fund targets 10% of budgeted data center real and personal property tax revenue; the FY2026 adopted budget added $39.7 million, bringing the fund to $119.7 million.2 A short illustration of why: under the TY2026 schedule, $500 million of servers bought in 2025 would be assessed at $300 million (60%), producing about $12.5 million in tax at $4.15 per $100. The same servers drop to 45% of cost the next year, and to 10% by their fifth year, unless they are replaced.513
JLARC’s review of five mature Virginia markets found data center revenue ranging from under 1% to 31% of total local revenue, depending on market size and local tax rates.1 The lesson for other counties is that Loudoun-scale results come from a large, mature cluster, not from a single campus.
04Abatements, PILOTs and bond-lease structures
Where a state allows it, a county can reduce a data center’s property tax for a period of years. The mechanics vary by state, but most deals fall into three types.
Fig. 3Three ways counties cut a data center’s tax bill
Texas Chapter 312
Abatement
- County designates a reinvestment zone
- Exempts a share of added value
- Fixed term with investment targets
- Can cover servers and equipment
Georgia
Bond-lease PILOT
- Authority holds title, issues bonds
- Developer pays rent to authority
- Negotiated PILOT to local bodies
- Bonds repaid by the user, not taxes
Louisiana
Public-ownership PILOT
- Property conveyed to a public entity
- Exempt as public property
- Leased back to the developer
- Payment schedule set by contract
In Texas, Medina County designated a 244-acre CyrusOne site as a reinvestment zone and scheduled action on an 80% abatement.4 A Haskell County notice for a proposed data center abatement covered real and business personal property, including computer servers, with improvements estimated at over $1 billion.14
In Georgia, the Stanton Springs project used taxable revenue bonds: the developer pays rent to the joint development authority and makes PILOT payments to the four member counties, the bonds are repaid from the user’s revenues, and the authority and counties are not liable for the debt.3 In Louisiana, West Feliciana Parish’s structure has the developer donate its property to the parish, making it tax exempt, then lease it back under a PILOT; the first payment is due July 1, 2027.15
Local bodies negotiate how PILOT money is split. That split matters to schools in particular, because PILOT payments may not flow through the usual levy formulas. Read the intergovernmental agreement, not just the headline amount.
05Where the revenue goes, and what it can cost
Data center tax revenue has funded lower homeowner tax rates, reserves and capital projects in Virginia’s data center counties.21 It also has costs that are easy to miss.
- State school aid: Virginia’s Local Composite Index measures each locality’s ability to pay for schools, with the true value of real property weighted at 50%. A higher index means less state funding.7 A large data center real estate base raises local wealth on paper while adding few students.
- Volatility: equipment values fall quickly and depend on refresh cycles, which is why Loudoun sets aside a share of data center revenue in a stabilization fund.2
- Transparency: a 2026 Good Jobs First study found 14 states do not disclose revenue lost to data center tax breaks, though their programs meet the accounting definition of a tax abatement.16
- Service costs: roads, emergency services and utility extensions add local costs that belong in any net fiscal analysis.
For a county weighing a project, the useful question is net revenue over 10 to 20 years after any abatement, school-aid effects and service costs, not first-year revenue. Our guide for county officials covers the wider review.
06What landowners and developers should check
- 01Confirm how the state classifies servers, generators, cooling plant and electrical gear: real property, personal property or exempt.
- 02Get the county’s current equipment rate and depreciation schedule, and check whether either has changed recently. Prince William raised its rate for FY2026, and Loudoun changed its schedule for tax year 2026.65
- 03Model taxes across at least two server refresh cycles, not just year one.
- 04Ask whether the county or a development authority offers abatements or PILOT structures, what investment and job targets apply, and what happens if phases are delayed.3
- 05If you own the land, understand how the sale or lease will change your own tax position, including rollback taxes and any ground lease provisions on who pays.
- 06Budget for valuation questions. Assessors may lack data center experience, which can lead to inaccurate assessments that owners then appeal.9
Tax treatment rarely makes a site, but it can separate two good ones. Our incentives vs. power cost guide covers that trade-off, and you can get a site reviewed for power, land and entitlement fit before modeling taxes in detail. Confirm specific treatment with the county assessor and a tax adviser.
Common questions
Do data centers pay property taxes?
Yes. They pay real property tax on land and buildings and, in states that tax business personal property, tax on servers and other equipment. In Virginia’s data center counties, the equipment tax is usually the largest piece.1 Abatements or PILOT agreements can reduce what a specific project pays.3
How much tax revenue do data centers generate for Loudoun County?
Loudoun’s FY2026 budget materials say data centers generate 38% of the county’s General Fund revenues.2 The county sets aside 10% of budgeted data center property tax revenue in a Revenue Stabilization Fund because the revenue can swing.2
How are servers in a data center taxed?
Where states tax business personal property, servers are assessed at a declining percentage of original cost. In Loudoun County for tax year 2026, equipment bought in 2025 is assessed at 60% of cost and equipment bought in 2021 at 10%.5 The local rate is then applied to that assessed value.
What is a PILOT agreement for a data center?
A payment in lieu of taxes is a negotiated payment that replaces regular property tax, usually because a public body holds title to the property. In Georgia’s Stanton Springs deal, the developer pays rent to a development authority and PILOT payments to the member counties.3 The schedule and how the money is split are set by contract.
Does a data center raise my property taxes as a neighbor?
Not directly. A neighbor’s assessment depends on their own property’s value. Large data center revenue has let some Virginia counties lower or hold residential rates, which is a policy choice by the local board.1
Notes
- 1.Joint Legislative Audit and Review Commission (Virginia), “Data Centers in Virginia,” 2024. jlarc.virginia.gov
- 2.Loudoun County, Virginia, “Budget Story FY 2026,” 2025. prcsinfo.loudoun.gov
- 3.The Covington News, “Court approves bond issue for Stanton Springs data center near Social Circle,” n.d. covnews.com
- 4.Devine News, “Cyrus One… County schedules action on 80% tax abatement supporting another new data center proposal,” 2025. devinenews.com
- 5.Loudoun County, Virginia, “Business Personal Property Tax Assessment Schedules,” n.d. loudoun.gov
- 6.Prince William Times, “Prince William County supervisors raise taxes on data centers, homeowners in new budget,” 2025. princewilliamtimes.com
- 7.Cardinal News, “State formula says a rural county where half the kids live in poverty has more ability to pay for schools than some affluent suburbs. How can this be?,” 2024. cardinalnews.org
- 8.WTOP, “Prince William County’s data center tax revenue jumps nearly 70% to $280 million,” 2025. wtop.com
- 9.Vorys, Sater, Seymour and Pease LLP, “Evaluator Industry Spotlight: Data Centers,” n.d. vorys.com
- 10.Virginia General Assembly, Legislative Information System, “Budget Bill HB29 (Chapter), Item 3-5.21,” 2026. budget.lis.virginia.gov
- 11.Blue Ridge Leader, “Loudoun Business Tax Assessment Schedule Changes Effective Jan. 1,” 2025. blueridgeleader.com
- 12.Loudoun County, Virginia, “Frequently Asked Questions,” n.d. loudoun.gov
- 13.Loudoun County, Virginia, “Data Centers in Loudoun County,” n.d. loudoun.gov
- 14.Haskell County, Texas, “2nd Amended Notice of Consideration of Tax Abatement Agreement,” 2025. haskellcountytx.gov
- 15.WBRZ, “West Feliciana Parish approves schedule for distributing data center payments,” 2026. wbrz.com
- 16.Data Center Dynamics, “More than a quarter of US states do not properly disclose revenue lost to data center tax abatements: report,” 2026. datacenterdynamics.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Land & site fundamentals
- How Much Land Does a Data Center Need?
- Data Center Site Selection Criteria: The Complete Checklist
- Parcel Assembly for Data Center Campuses
- Gross vs. Buildable Acreage: How Much of a Site You Can Use
- Site Shape, Access and Frontage for Data Centers
- Can My Land Host a Data Center? A Landowner’s Guide
- Greenfield vs. Brownfield Data Center Sites: Which Is Better?
- Can a Retired Power Plant or Industrial Site Become a Data Center?
- Mineral Rights and Easements: How They Affect Data Center Land
- Title Review and ALTA Surveys for Data Center Land
- Can Farmland Be Converted to a Data Center?
- Data Center Land Option Agreements: Key Terms for Landowners
- Ground Leases for Data Centers: Terms, Rent, Financing and Reversion
- What Drives Data Center Land Value? Power, Timing, Entitlements and Size
- Topographic Surveys and LiDAR for Data Center Site Selection
- Heavy-Haul Routes and Construction Access for Data Centers
- Certified Sites and Shovel-Ready Programs: What They Mean for Data Centers
- Eminent Domain and Transmission Line Easements: A Landowner’s Guide
- Federal Land for AI Data Centers: DOE Sites, BLM and Military Bases
- Conservation Easements and Deed Restrictions on Data Center Land
- Subdivision, Platting and Lot Consolidation for Data Center Sites
Guide 19 of 23 in Land & site fundamentals · all 242 guides · glossary · calculators