BlackForge Data Centers

Site selection by state

Data Center Site Selection in Virginia: Power, GS-5, Zoning and Tax Rules

Virginia hosts the world’s largest data center market, with about 80% of the state’s industry in Loudoun, Prince William and Fairfax counties, but power and local approval now set the pace more than demand does.1 Dominion Energy reports more than 53 GW of data center capacity in some stage of contracting, and from January 1, 2027, customers of 25 MW or more move into a new GS-5 rate class with 14-year minimum payment commitments.23 Loudoun ended by-right approvals in 2025,4 a court voided the Prince William Digital Gateway rezonings in 2026,5 and the state kept its sales tax exemption while adding a per-kWh electricity tax,6 so a Virginia site screen now turns on utility terms, local process and tax exposure together.

Last reviewed · 9 min read · BlackForge Data Centers

Key takeaways

  • Dominion reports more than 53 GW of data center capacity in contracting stages, with about 12 GW under electric service agreements, so a realistic power date is the first screening question.2
  • The SCC’s GS-5 class for customers of 25 MW or more takes effect January 1, 2027, with 14-year minimum bills of 85% of contracted transmission and distribution demand and 60% of generation demand.3
  • Loudoun County now requires a special exception, with public hearings, for every new data center.4
  • The sales tax exemption requires $150 million of investment and 50 jobs ($70 million and 10 jobs in distressed localities) and runs to 2035, but a new electricity consumption tax of $0.011 per kWh applies to data centers.76
  • Executive Order 22, signed September 18, 2026, signals tighter state rules on transparency, water, energy efficiency and local approval.8
  • Richmond and parts of Southside Virginia offer land and a different local posture, but they draw on the same Dominion supply constraints.910

01Why Virginia works differently from other states

Most states are still courting their first hyperscale campus. Virginia is managing the consequences of hosting the largest data center market in the world. The Joint Legislative Audit and Review Commission (JLARC) counted about 150 data center sites holding around 340 buildings in 2024, with about 80% of the industry concentrated in Loudoun, Prince William and Fairfax counties.1 JLARC also found that data centers are the main driver of a forecast doubling of statewide electricity demand over the next 10 years, and that building enough generation and transmission to meet even half of unconstrained demand by 2040 would be difficult.1

That concentration changes the screening order. In a new market, land, fiber and incentives are often the first filters. In Virginia, fiber and buyers are abundant near Ashburn, so the binding constraints are the serving utility’s ability to deliver power on a date, the county’s approval process and the state’s evolving tax and regulatory terms. Virginia is in PJM, so wholesale capacity prices also matter; our guides to PJM site selection and PJM capacity prices cover the regional layer, and the Northern Virginia market guide covers leasing and absorption.

Fig. 1Virginia data centers by the numbers

of Virginia’s industry in three NoVA counties1
~80%
data center capacity in Dominion contracting2
53 GW+
under Dominion electric service agreements2
~12 GW
sales tax exemption cost, fiscal 202511
$1.6B+
Industry concentration from JLARC (2024), Dominion’s pipeline as reported in July 2026 and the exemption’s cost in fiscal 2025.

02Dominion Energy, the large-load pipeline and the GS-5 rate class

Most large Virginia sites are in Dominion Energy Virginia’s territory, and Dominion’s pipeline is the clearest measure of the queue a new project joins. On its July 2026 earnings call, Dominion reported more than 53 GW of data center capacity in various stages of contracting, about 12 GW of it under electric service agreements, and more than 5 GW of new data center contracts since the end of 2025.2 Nine of the Dominion Zone’s 10 highest all-time peak-demand days occurred in 2026.2 A parcel near a substation is not the same as a parcel with capacity, and a will-serve conversation should start with where a new request would sit behind that backlog.

The rules for large customers also changed. In its November 25, 2025 final order in Dominion’s biennial review, the State Corporation Commission created a GS-5 rate class for customers with demand of 25 MW or more, effective January 1, 2027.3 GS-5 customers must sign 14-year commitments to pay for at least 85% of contracted transmission and distribution demand and at least 60% of contracted generation demand, even if they use less.3 The same order approved base rate increases of $565.7 million for 2026 and $209.9 million for 2027, about half of what Dominion requested.12

GS-5 terms that change site economics
TermWhat the SCC order requiresWhy it matters for siting
ThresholdDemand of 25 MW or more3Nearly every new campus qualifies
Effective dateJanuary 1, 20273Applies to projects energizing now
Contract length14 years3Long tail of committed payments
T&D minimum85% of contracted demand3Oversized requests become costly
Generation minimum60% of contracted demand3Ramp schedules need to be realistic

For site selection, the practical effect is that contracted megawatts become a long financial commitment. A request sized for a full build that ramps slowly carries minimum bills from the start, so a credible ramp schedule matters. Our guide to large-load tariffs and electric service agreements explains how these provisions are usually structured.

03Reliability lessons from the 2024 load-loss event

Virginia also produced the event that made grid operators treat data centers as a reliability issue. On July 10, 2024, a lightning arrester failed on a 230 kV line, and the line’s auto-reclosing scheme produced six successive faults in 82 seconds.13 About 1,500 MW of data center load, spread across 60 points of interconnection and 25 substations, dropped off the grid at once in a customer-initiated load loss that operators had not anticipated.13 NERC found that the resulting voltage rise did not threaten bulk system reliability but warned planners that similar events should not reach intolerable levels.13

For a new campus, expect utilities and PJM to ask more about ride-through settings, UPS transfer logic and how load returns after a disturbance. A campus that drops hundreds of megawatts in a fraction of a second behaves, from the grid’s point of view, like a large generator tripping in reverse, and planners now study that case. Those questions belong in early design, not commissioning, and our guide to NERC reliability and large loads tracks the standards work that followed.

04Local zoning: Loudoun, Prince William and the end of by-right

Virginia counties control land use, and the core counties have tightened. On March 18, 2025, the Loudoun County Board of Supervisors adopted a comprehensive plan amendment and a zoning ordinance amendment that eliminated by-right data center development.4 New data centers now need a special exception, with public hearings before both the Planning Commission and the Board of Supervisors.4 Applications already under review as of February 12, 2025 were grandfathered only if they were more than 500 feet from residential areas and did not change substantially.14

Prince William County shows the litigation risk of large rezonings. The Prince William Digital Gateway, about 23 million square feet on roughly 2,100 acres next to Manassas National Battlefield Park, was approved on a 4–3 vote after a 27-hour hearing in December 2023.5 On March 31, 2026, the Virginia Court of Appeals unanimously affirmed a ruling that voided the rezonings because the county’s public notice for the hearing violated state law and its own ordinance.5 The lesson for any parcel is procedural as much as political: a rezoning is only as durable as the record behind it.

05State tax policy and Executive Order 22

Virginia’s retail sales and use tax exemption for data center equipment requires at least $150 million of capital investment and at least 50 new jobs paying at least 150% of the local prevailing average wage. In a distressed locality, the thresholds fall to $70 million and 10 jobs.7 The exemption is large: Virginia forwent more than $1.6 billion in fiscal 2025, up 118% from the prior year, and JLARC found data centers received 53% of state incentive spending over the past decade.11

The exemption survived a serious challenge in 2026. The House budget would have kept the 2035 sunset but added environmental and efficiency conditions, while the Senate budget would have ended the exemption on January 1, 2027.15 The 2026–2028 budget enacted on June 29, 2026 kept the exemption but imposed an electricity consumption tax of $0.011 per kWh on electricity used by data centers, capped at $600 million a year statewide.6 For a 100 MW campus at a high load factor, that tax is a material operating cost, so run the sales tax exemption and the new tax together in any pro forma.

Further change is likely. On September 18, 2026, Governor Spanberger signed Executive Order 22, creating a Data Center Accountability Framework built on transparency, environmental protection, affordability, clean energy and grid reliability, and workforce benefits; it bars state agencies from entering into or requiring nondisclosure agreements for data center projects.8 The framework also calls for ending by-right approval and requiring local approval for data centers using more than 25 MW, ending state site-development subsidies for data centers, and setting state standards for energy efficiency, water use and land impacts.16 Many of those items would need legislation, so treat them as direction, not law, and see state data center legislation trends.

06Beyond Northern Virginia: Richmond and Southside

Development has moved south along I-95 and into Southside. The Richmond market added about 720 MW of colocation inventory in the first half of 2025, more than any other U.S. market, as demand spilled out of the Ashburn and Sterling corridor.9 In Pittsylvania County, the Board of Supervisors unanimously rezoned a 946-acre tract in Ringgold to heavy industrial use for a proposed data center campus valued at $1 billion or more.10

Fig. 2Northern Virginia vs. Central and Southern Virginia

Loudoun, Prince William, Fairfax

Northern Virginia

  • Deepest fiber, buyers and labor
  • Special exception now required in Loudoun
  • Highest land prices and community scrutiny
  • Longest wait behind existing power commitments

Richmond region, Southside

Central and Southern Virginia

  • Larger, cheaper tracts are available
  • Fast-growing Richmond colocation market
  • Distressed-locality thresholds may apply
  • Fiber diversity and labor need closer checks
General patterns, not rules; confirm the serving utility and county process for each parcel.49

The trade-off is real but narrower than it looks. Moving south can mean more land, lower prices and, in a distressed locality, a lower bar for the sales tax exemption.7 It does not escape Dominion’s system-wide supply position or the GS-5 terms, and each county sets its own zoning path. Southside tracts can also sit far from the substations that already serve large industrial load, which lengthens the line and substation work a utility must plan. Rural sites also need careful checks of route diversity, water and sewer capacity, and transmission access.

07How to screen a Virginia site

  1. 01Identify the serving utility and ask where a request of your size would fall behind Dominion’s contracted pipeline.2
  2. 02Size the request to a realistic ramp; GS-5 minimum bills apply to contracted demand for 14 years.3
  3. 03Confirm the county process: special exception, rezoning or existing approval, and whether any approval is final and unappealed.45
  4. 04Test eligibility for the sales tax exemption, including distressed-locality status, and add the $0.011 per kWh electricity tax.76
  5. 05Plan for ride-through and load-transfer studies as part of the interconnection review.13
  6. 06Track Executive Order 22 and 2027 legislation on water, efficiency and local approval.816

Fig. 3Sample screen of a Virginia parcel

Illustrative
  • WatchServing utilityDominion territory; power date depends on pipeline position.
  • WatchZoningSpecial exception needed; nearest home 900 feet away.
  • PassTransmission230 kV line crosses the parcel’s west edge.
  • PassSales tax exemptionInvestment and job thresholds met in the base plan.
  • WatchFiber diversityOne long-haul route nearby; second path unconfirmed.
Illustrative sample. Not a real parcel.

Our methodology explains how we weigh these factors, and you can get a site reviewed before committing to a utility request or a rezoning.

Common questions

What is Dominion’s GS-5 rate class?

GS-5 is a rate class the Virginia SCC created in November 2025 for Dominion customers with demand of 25 MW or more, effective January 1, 2027.3 Customers sign 14-year contracts with minimum payments of 85% of contracted transmission and distribution demand and 60% of generation demand.3

Can you still build a data center by right in Loudoun County?

Generally no. Since March 2025, new data centers in Loudoun need a special exception with public hearings before the Planning Commission and Board of Supervisors.4 Some applications under review by February 12, 2025 were grandfathered if they were more than 500 feet from residential areas.14

Does Virginia still offer a data center sales tax exemption?

Yes. The 2026–2028 budget kept the exemption, which is scheduled to run through 2035, but added an electricity consumption tax of $0.011 per kWh on data centers, capped at $600 million a year.6 Eligibility requires $150 million of investment and 50 jobs, or $70 million and 10 jobs in a distressed locality.7

What happened to the Prince William Digital Gateway?

In March 2026 the Virginia Court of Appeals affirmed a ruling voiding the project’s rezonings because the county’s hearing notice did not meet legal requirements.5 The project covered about 2,100 acres next to Manassas National Battlefield Park.5

Is Southern Virginia a good alternative to Northern Virginia?

It can be for land-intensive campuses. Richmond added more colocation inventory than any other U.S. market in the first half of 2025, and Southside counties have rezoned large tracts.910 Power availability still depends on the serving utility, so screen each parcel on its own.

Notes

  1. 1.Joint Legislative Audit and Review Commission, “Data Centers in Virginia (Report 598),” 2024. jlarc.virginia.gov
  2. 2.Nasdaq, “Dominion Energy Q2 Earnings Call Highlights,” 2026. nasdaq.com
  3. 3.Loudoun Now, “SCC Approves New Data Center Rate Class for Dominion,” 2025. loudounnow.com
  4. 4.Holland & Knight, “Loudoun County, Virginia, Eliminates By-Right Data Center Development,” 2025. hklaw.com
  5. 5.Virginia Lawyers Weekly, “Virginia Appeals Court upholds block on Prince William Digital Gateway project,” 2026. valawyersweekly.com
  6. 6.Hunton Andrews Kurth, “Virginia Adds Electricity Consumption Tax but Stops Short of Repealing Data Center Sales Tax Exemption,” 2026. hunton.com
  7. 7.Spotsylvania County, “Data Center Retail Sales & Use Tax Exemption Eligibility Requirements,” n.d. spotsylvania.va.us
  8. 8.Beveridge & Diamond, “Virginia Launches Data Center Accountability Framework,” 2026. bdlaw.com
  9. 9.WYDaily, “Report: Richmond leads nation in data center growth,” 2025. wydaily.com
  10. 10.Virginia Business, “$1 billion data center campus moves forward in Pittsylvania,” n.d. virginiabusiness.com
  11. 11.Data Center Dynamics, “Virginia missed more than $1.6bn in tax revenue due to data center exemptions in 2025,” 2025. datacenterdynamics.com
  12. 12.Cardinal News, “Regulators approve Dominion Energy rate increase,” 2025. cardinalnews.org
  13. 13.American Public Power Association, “NERC Incident Review Examines Risks, Challenges Tied to Integration of Large Loads,” 2025. publicpower.org
  14. 14.Loudoun Now, “By-Right Data Centers Eliminated in Loudoun, Existing Applications Grandfathered,” 2025. loudounnow.com
  15. 15.DLA Piper, “Virginia General Assembly proposes to eliminate sales and use tax exemption for data centers,” 2026. dlapiper.com
  16. 16.Holland & Knight, “Virginia’s New Data Center Accountability Framework,” 2026. hklaw.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Related guides

More in Site selection by state