Key takeaways
- Natural gas fueled about 75% of Florida’s net generation in 2024 and nuclear about 11%; Florida produces more electricity than any state except Texas.1
- FPL’s LLCS-1 and LLCS-2 tariffs, approved in the November 2025 rate settlement, apply to new loads of 50 MW or more with a minimum 20-year term and a 70% minimum demand charge.67
- SB 484, signed in May 2026,8 requires investor-owned utilities to file large-load tariffs,9 lets water management districts deny harmful data center water uses4 and keeps local land-use authority.8
- The sales and use tax exemption now requires at least 100 MW of critical IT load within five years, up from 15 MW, with applications open until June 30, 2037.5
- Florida has taken about 40% of all U.S. hurricane landfalls, and Miami-Dade and Broward counties sit in the code’s High-Velocity Hurricane Zone.1011
01Why Florida is on data center shortlists now
Florida has long been a colocation and connectivity market, centered on Miami’s role as a gateway to Latin America, but it has rarely shown up on hyperscale shortlists. That is changing because of scale on the power side. Florida is the nation’s second-largest producer of electricity after Texas, and in 2024 natural gas fueled about three-quarters of its net generation, with nuclear supplying about 11% and renewables and coal nearly all the rest.1
Fig. 1Florida’s power system at a glance
- of net generation from natural gas
- ~75%
- of net generation from nuclear
- ~11%
- U.S. state for electricity production
- #2
- FPL large-load forecast by 2032
- 8 GW
The demand signal is real. In 2026 NextEra Energy raised its large-load forecast for its Florida subsidiary, Florida Power & Light, to 8 GW by 2032, with hyperscale data centers as the main driver.2 Most of the state’s large campus proposals so far sit in Central Florida, especially Polk County between Tampa and Orlando, where land is cheaper than on either coast and inland sites sit farther from storm surge.1213
Florida also differs from its neighbors. Georgia and Alabama are anchored by Southern Company’s large utilities, while Florida splits large loads among FPL, Duke Energy Florida, Tampa Electric and municipal utilities such as JEA in Jacksonville. For the regional comparison, see Southeast site selection and the Georgia guide.
02FPL’s LLCS large-load tariffs
FPL is Florida’s largest utility, and its rules for big loads changed in its 2025 rate case. In November 2025 the Florida Public Service Commission unanimously approved a settlement that lets FPL collect an additional $6.9 billion over four years and creates large-load tariffs that hold heavy users to long-term contracts, with penalties for early exit.6
A July 2026 Columbia County briefing packet, reproducing FPL’s summary, laid out the approved structure.7 Both tariffs apply to new or incremental load of 50 MW or more at a single location with a load factor of at least 85%. LLCS-1 covers up to 3 GW of new demand along portions of FPL’s 500 kV system; LLCS-2 covers other qualifying loads. Customers pay a minimum demand charge of 70% of contract demand, sign for at least 20 years from the in-service date (including the ramp) and owe an exit fee tied to accelerated payment of the remaining incremental generation charges if they leave early.7 FPL adds that large customers must fund an engineering study and pay 100% of the cost of the new generation needed to serve them.3
Fig. 2FPL’s two large-load tariffs
500 kV corridors
LLCS-1
- Up to 3 GW of new demand in total
- Sites along portions of the 500 kV system
- Incremental generation charge of $11.67/kW
- 50 MW+ and 85%+ load factor
Everywhere else
LLCS-2
- All other qualifying large loads
- Incremental generation charge to be calculated
- Lower demand charge than LLCS-1
- 50 MW+ and 85%+ load factor
The practical effect is that a parcel near FPL’s 500 kV backbone may have a clearer, better-defined price than one that is not. A 20-year take-or-pay style commitment also shifts risk onto the end user, so speculative developers should expect FPL to want a credible tenant before it commits capacity. Our guide to large-load tariffs and electric service agreements explains minimum bills, collateral and exit fees, and contract demand and load factor are defined in the glossary.
03SB 484, Duke Energy Florida, TECO and JEA
Gov. Ron DeSantis signed SB 484 on May 7, 2026.8 The governor’s office describes it as preventing data center costs, including electricity costs, from being passed on to other customers, and requires public utilities to offer minimum tariffs and service requirements for these customers, with the Public Service Commission carrying them out.144 Every investor-owned electric utility had to file a compliant large-load tariff by October 1, 2026.9
Duke Energy Florida, which serves much of Central Florida and the Gulf Coast north of Tampa Bay, was the first test. At an August 2026 hearing the Office of Public Counsel argued that Duke’s proposal did not meet the law’s basic requirements; commissioners heard about five hours of testimony and took no vote, with a written order to follow post-hearing filings.9 Tampa Electric filed its plan around October 1, 2026. It says it serves no large-load customers today and expects a commission decision late in 2026 or early 2027.15
| Utility | Main territory | Large-load status |
|---|---|---|
| FPL | East coast, South, Southwest and Northwest Florida | LLCS-1 and LLCS-2 approved in the 2025 settlement67 |
| Duke Energy Florida | Central Florida and the Nature Coast | Proposal heard in August 2026; order pending9 |
| Tampa Electric | Hillsborough and parts of nearby counties | Plan filed around October 1, 2026; no large loads today15 |
| JEA and other municipals | Jacksonville and city systems | Outside the investor-owned utility filing mandate9 |
Jacksonville is the main market where the investor-owned rules do not set the terms. JEA is a city-owned utility, so a site there means negotiating directly with JEA and the city rather than relying on a PSC-approved tariff. The same is true of other municipal systems and electric cooperatives, which is why confirming the utility service territory comes first on any Florida parcel.
04The sales tax exemption after 2025
Florida has offered a sales and use tax exemption for data centers for years, but the 2025 tax package rewrote it. The law raised the minimum capacity, measured as critical IT load, from 15 MW to 100 MW, and that threshold must be met within five years of construction. It also moved the deadline for certificates from June 30, 2027 to June 30, 2037. Businesses apply to the Florida Department of Revenue for a temporary tax exemption certificate.5
The change cuts both ways for site selection. It keeps the incentive alive for a decade for hyperscale and AI campuses, but it removes it for most enterprise and colocation projects below 100 MW. Greenberg Traurig warned that, as drafted, the language would end the exemption for existing data centers below 100 MW as of August 1, 2025, that the loss of the exemption on electricity purchases could disrupt landlord leases, and that it was unclear whether lawmakers intended that result.16 For how Florida compares with other states, see data center sales tax exemptions by state and the glossary entry on sales tax exemptions.
05Hurricanes, wind design and flood
Storm risk is the issue every Florida buyer raises first. Florida has been hit by about 40% of all U.S. hurricanes in NOAA’s records, and 88% of major hurricane strikes have hit either Florida or Texas.10 Risk is not uniform: coastal parcels face surge and wind, while inland Central Florida trades surge exposure for wind and heavy rain.
The Florida Building Code sets wind loads by location and risk category. Miami-Dade and Broward counties are defined as the High-Velocity Hurricane Zone (HVHZ), where a single design wind speed applies across each county for each risk category.11 Under the 2010 code maps, Miami-Dade used 175 mph for Risk Category II buildings and 185 mph for Categories III and IV.11 Owners of mission-critical facilities often design to a higher risk category than the code minimum, which raises structural, roofing and equipment-anchoring costs.
Fig. 3HVHZ design wind speeds, 2010 code maps
- Miami-Dade, Risk Cat. I165
- Miami-Dade, Risk Cat. II175
- Miami-Dade, Risk Cat. III–IV185
- Broward, Risk Cat. I156
- Broward, Risk Cat. II170
- Broward, Risk Cat. III–IV180
mph
Flood is the second test. Low relief, high water tables and intense rainfall mean much of the state has mapped Special Flood Hazard Areas, and stormwater ponds can take a large share of a parcel. See our guides to hurricane and storm surge risk, floodplain sites and stormwater management.
06Water permits and local approval
SB 484 put water on the same footing as power. Data centers need a consumptive use permit to tap state water resources, water management districts must deny an application if the use would harm local resources, and reclaimed water must be used when it is available.4 That makes reclaimed water for cooling and closed-loop designs more than a sustainability choice in Florida.
The law also kept local control. The governor’s office says local governments keep the authority to reject data center development, and Florida Phoenix reports that the law preserves local land development regulation, lets companies keep expansion plans confidential for a year, requires public meetings to cover water use and utility impacts, and orders a state OPPAGA study due July 1, 2027.148
Polk County shows both sides. In April 2026 Fort Meade approved a 20-year development agreement for a 1,300-acre data center campus that reserves city water and wastewater capacity for the project, but the water supply still needs separate approval from the Southwest Florida Water Management District.12 In August 2026 nearby Lakeland voted 4–3 for a one-year moratorium on data center development after opposition to a proposed facility of up to 100 MW.13 Read our guides to data center moratoriums and community engagement before choosing a jurisdiction.
07How to screen a Florida site
Fig. 4A Florida screening sequence
- 01
Utility and tariff
Which utility, and is the site near FPL’s 500 kV system?
- 02
Load and term
Can the tenant sign for 50 MW+, 85% load factor, 20 years?
- 03
Tax threshold
Will the build reach 100 MW of critical IT load in five years?
- 04
Water permit
Reclaimed water available? District permit path?
- 05
Storm and flood
Wind zone, surge, flood zone and stormwater area.
- 06
Local approval
Zoning path, moratoriums and public hearing risk.
- 01Confirm the serving utility and ask whether the load would fall under FPL’s LLCS-1 or LLCS-2,7 or the current Duke or Tampa Electric large-load filing.915
- 02Test the tenant’s commitment against a 20-year term, a 70% minimum demand charge and an exit fee before marketing the site as powered.7
- 03Model the sales tax exemption only if the campus reaches 100 MW of critical IT load within five years.5
- 04Map reclaimed water sources and talk to the water management district early.4
- 05Check the county and city for moratoriums and pending ordinances, and confirm the zoning district allows a data center by right or through a rezoning.
Expect the rules to keep moving. Duke Energy Florida’s and Tampa Electric’s large-load filings were still before the commission in early October 2026, so ask each utility for its current terms, study steps and timeline rather than relying on an earlier summary.915 If you are weighing a Florida parcel, our methodology explains how we score power, water, flood and entitlement risk, and you can get a site reviewed.
Common questions
Does Florida have a sales tax exemption for data centers?
Yes, but since August 2025 it requires at least 100 MW of critical IT load, reached within five years, up from 15 MW. Applicants seek a temporary certificate from the Department of Revenue, and certificates can be issued until June 30, 2037.5 Smaller projects should assume they do not qualify.
What is FPL’s LLCS tariff?
Large Load Contract Service is FPL’s rate for new loads of 50 MW or more with a load factor of at least 85%. It comes in two versions, LLCS-1 for up to 3 GW along parts of the 500 kV system and LLCS-2 for other sites, both with a minimum 20-year term.7 FPL says the customer pays for the new generation built to serve it.3
What does Florida’s 2026 data center law do?
SB 484 requires utilities to offer large-load tariffs so data center costs are not shifted to other customers, and investor-owned utilities had to file them by October 1, 2026.149 It also tightens water permitting, requires reclaimed water where available and keeps local land-use authority.48
Is hurricane risk a dealbreaker for Florida data centers?
Not by itself, but it shapes where and how you build. Florida has absorbed about 40% of U.S. hurricane strikes, and South Florida’s High-Velocity Hurricane Zone carries the code’s highest design wind speeds.1011 Inland, elevated sites outside surge zones and designs to a higher risk category reduce the exposure.
Notes
- 1.U.S. Energy Information Administration, “Florida Profile,” 2025. eia.gov
- 2.Data Center Dynamics, “NextEra raises data center forecast to 8GW by 2032 at Florida subsidiary FPL,” 2026. datacenterdynamics.com
- 3.Florida Power & Light, “Q&A with FPL President on expected data center growth and the company’s new customer protections,” n.d. newsroom.fpl.com
- 4.FOX 35 Orlando, “DeSantis signs bill regulating costs, water use tied to large-scale data centers in Florida,” 2026. fox35orlando.com
- 5.Forvis Mazars, “Significant Tax Changes Enacted in Florida,” 2025. forvismazars.us
- 6.E&E News, “PSC unanimously approves Florida Power & Light rate hike settlement,” 2025. eenews.net
- 7.Columbia County Board of County Commissioners, “BCC Special Meeting Agenda (data center discussion), July 2026,” 2026. wwals.net
- 8.Florida Phoenix, “Florida has a new law regulating AI data centers,” 2026. floridaphoenix.com
- 9.Florida Trib, “New state law to protect consumers from data center costs faces its first test,” 2026. floridatrib.org
- 10.FOX 35 Orlando, “Florida has been hit by more hurricanes than any other state, here are the 5 most devastating,” n.d. fox35orlando.com
- 11.Florida Building Commission, “Florida Building Code 2010 wind speed maps (flyer),” 2012. floridabuilding.org
- 12.Data Center Dynamics, “Plans to build 1,300-acre data center in Fort Meade, Florida, get go-ahead from officials,” 2026. datacenterdynamics.com
- 13.Bay News 9, “Lakeland city officials approve vote on data center moratorium,” 2026. baynews9.com
- 14.Executive Office of the Governor of Florida, “Governor Ron DeSantis Signs Law to Protect Floridians from Subsidizing Data Centers,” 2026. flgov.com
- 15.Bay News 9, “Tampa Electric files plan to protect customers from data center costs,” 2026. baynews9.com
- 16.Greenberg Traurig, “Florida Legislature Passes Bill to End Sales Tax Exemption for Sub-100 MW Data Centers,” 2025. gtlaw.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Related guides
More in Site selection by state
- Data Center Site Selection in Texas: Grids, SB 6, Water and Incentives
- Data Center Site Selection in Virginia: Power, GS-5, Zoning and Tax Rules
- Data Center Site Selection in Arizona: APS, SRP, TEP, Water and Heat
- Data Center Site Selection in Ohio: AEP Ohio’s Tariff, PJM Costs and the Tax Pause
- Data Center Site Selection in Illinois: ComEd, Ameren, PJM vs. MISO and the Incentive Pause
- Data Center Site Selection in Nevada: NV Energy, Reno and Las Vegas, Water Rules and GOED Abatements
- Data Center Site Selection in Oregon
- Data Center Site Selection in Iowa
- Data Center Site Selection in North Carolina
- Data Center Site Selection in South Carolina
- Data Center Site Selection in Pennsylvania
- Data Center Site Selection in Indiana
- Data Center Site Selection in Wisconsin
- Data Center Site Selection in Minnesota
- Data Center Site Selection in Nebraska
- Data Center Site Selection in Oklahoma
- Data Center Site Selection in Utah
- Data Center Site Selection in Washington State
- Data Center Site Selection in Louisiana
- Data Center Site Selection in Mississippi
- Data Center Site Selection in Alabama
- Data Center Site Selection in Tennessee
- Data Center Site Selection in Kentucky
- Data Center Site Selection in Missouri
- Data Center Site Selection in Kansas
- Data Center Site Selection in New Mexico
- Data Center Site Selection in Wyoming
- Data Center Site Selection in North Dakota
- Data Center Site Selection in New York: NYISO, Hydropower and the 2026 Permit Pause
- Data Center Site Selection in Michigan: DTE, Consumers, Tax Rules and Water
- Data Center Site Selection in Arkansas: Entergy, SWEPCO, 2025 Laws and Local Rules
- Data Center Site Selection in Colorado: Xcel’s Large-Load Tariff, Water and Local Rules
- Data Center Site Selection in Idaho
- Data Center Site Selection in West Virginia
- Data Center Site Selection in Maryland
- Data Center Site Selection in Montana
- Data Center Site Selection in South Dakota
