Key takeaways
- PUCO’s July 9, 2025 order requires new AEP Ohio data centers to pay for 85% of subscribed power for up to 12 years, including a four-year ramp, with exit fees and proof of financial viability.1
- By February 2026 the tariff process had produced 5,642 MW of signed data center agreements, 4,842 MW of it in Central Ohio, with in-service dates by 2030.2
- PJM’s 2028/2029 capacity auction cleared at the $325/MW-day cap and came in 6,831 MW short of the reliability requirement.3
- Governor DeWine vetoed the 2025 repeal of the data center sales tax exemption, then paused new exemption requests in May 2026 while a legislative committee studies data centers.64
- HB 15 (2025) loosened rules for behind-the-meter generation, and gas plants dedicated to data centers are now being proposed in Licking County.78
- The $750 million All Ohio Future Fund supports site-ready infrastructure, including at the former Conesville power plant.910
01Why Ohio, and why Central Ohio first
Ohio’s data center market is concentrated in Central Ohio, around Columbus, New Albany, Hilliard, Dublin and western Licking County. The draw has been large flat tracts, fiber, a business-friendly incentive program and transmission in the AEP Ohio service area. Demand outran supply quickly: before AEP Ohio’s data center tariff took effect, the utility cited more than 30 GW of initial data center interest, and it had paused new Central Ohio data center agreements while the tariff was being decided.21
Ohio is also a PJM state, which means capacity and transmission costs are set in part by a regional market rather than by the state utility alone. That distinguishes Ohio from vertically integrated states like Georgia and places it alongside Virginia, Pennsylvania and Indiana. Our PJM regional guide covers the market rules that apply across all of them.
Outside AEP Ohio, the state is served by other investor-owned utilities, cooperatives and municipal systems, each with different large-load terms. Confirm the utility service territory of every parcel before comparing sites.
02AEP Ohio’s data center tariff
On July 9, 2025, the Public Utilities Commission of Ohio (PUCO) approved a stipulation backed by AEP Ohio, PUCO staff, the Ohio Consumers’ Counsel and several industrial groups, after evidentiary hearings in December 2024 and January 2025.1 Amazon, Google, Microsoft and Meta opposed the settlement and offered an alternative, which the commission rejected; PUCO found that the AEP-backed framework better assigned infrastructure costs to the customers causing them.1 The tariff targets data centers with loads above 25 MW.11
- Minimum demand: new data center customers pay for 85% of the power they subscribe to, even if they use less.1
- Term: obligations last up to 12 years, including a four-year ramp-up period.1
- Credit: owners must show they are financially viable and able to meet the obligations.1
- Exit: an exit fee applies if a project is canceled or cannot meet its obligations over the contract term.1
Fig. 1How a data center moves through AEP Ohio’s tariff
- 01
Load study request
Filed within the window, with a one-time fee.
- 02
Clustered study
AEP studies requests together by area.
- 03
Contract offer
Terms with minimum demand and collateral.
- 04
Signed agreement
85% minimum bill, up to 12 years.
- 05
Ramp
Load grows over up to four years.
The financial commitment did what it was designed to do. When the tariff took effect, developers filed formal load study requests for about 13,023 MW across 36 sites, and by a February 12, 2026 letter to PUCO, AEP Ohio reported 5,642 MW of signed data center agreements: 4,842 MW in Central Ohio and 800 MW elsewhere in its territory, with projected in-service dates by 2030.2 AEP said the modified load figures will now be used for PJM transmission planning.2
Fig. 2AEP Ohio data center demand, interest to contract
- Initial interest30,000+ MW
- Load study requests~13,023 MW
- Signed agreements5,642 MW
MW
Across all of AEP, the parent company reported 7 GW of new load agreements signed in the first quarter of 2026, mainly in Ohio and Texas, and expects incremental load to reach 63 GW by 2030.12 For site selection, the lesson is that an Ohio power request is now a balance-sheet commitment. Size the request to a realistic ramp; see load ramp schedules, utility load studies and large-load tariffs and electric service agreements.
03PJM capacity prices and what they mean for Ohio sites
On July 14, 2026, PJM reported that its 2028/2029 Base Residual Auction procured 138,318 MW of unforced capacity, clearing at $325/MW-day, the FERC-approved cap for the whole footprint and 2.5% below the prior auction’s $333.44/MW-day cap.3 It was the third consecutive auction under the price collar, and procured capacity, including Fixed Resource Requirement resources, fell 6,831 MW short of the reliability requirement.3
Fig. 3PJM 2028/2029 capacity auction
- Clearing price, at the cap
- $325/MW-day
- Unforced capacity procured
- 138,318 MW
- Shortfall vs. reliability requirement
- 6,831 MW
- Total auction value
- $16.4 billion
Capacity charges flow into retail bills for most Ohio customers, and a shortfall raises the odds of new rules that ask large loads to bring or pay for supply. When you compare an Ohio site with one in a non-PJM state, include the capacity component and the risk that it changes. Our PJM capacity prices and data center load growth and electricity rates for data centers guides go deeper.
04Behind-the-meter power under HB 15
Ohio’s House Bill 15, the 2025 omnibus energy law, loosened restrictions on behind-the-meter generation and lowered the tax burden for new power plants.7 PUCO’s chair told the House select committee on data centers in May 2026 that the law expanded the types of generation that can power businesses and allowed more flexibility when the generator is not on the same site as, or directly adjacent to, the customer.13 The chair also noted that data centers are still served within the industrial or commercial customer class rather than a class of their own.13
Developers are using the opening. A gas-fired plant of up to 120 MW has been proposed in western Licking County to serve a data center in the New Albany International Business Park.8 On-site generation adds gas supply, air permits and neighbor concerns to the site checklist. See behind-the-meter vs. front-of-the-meter power and on-site generation and bridge power.
05The sales tax exemption: vetoed repeal, then a pause
Ohio’s data center sales tax exemption is granted through the Ohio Tax Credit Authority.4 In 2025 the legislature removed the exemption in the state budget bill, HB 96, but Governor DeWine vetoed that provision, so the exemption survived.6 In March 2026, the House speaker said Republican leaders were counting votes to override the veto, but the House postponed the vote; we found no report of a completed override as of October 2026.14
On May 27, 2026, DeWine directed the Tax Credit Authority to stop considering new data center exemption requests submitted after its next meeting.4 Exemptions already approved remain in effect, and the pause does not prohibit data center development; it is tied to a joint legislative data center committee charged with reporting recommendations within six months.4
06Townships, moratoriums and water
Ohio’s township zoning gives small jurisdictions real control. In February 2026, the Licking County planning commission unanimously supported a St. Albans Township zoning change that would effectively ban data centers by removing them from conditionally permitted uses.5 In September 2026, Pierce Township trustees extended a zoning moratorium on data center uses to May 31, 2027.15 Check every township and municipality along a candidate site, not just the county, and read our moratoriums and local restrictions guide.
Water is less constraining in Ohio than in the arid West, but it is not free of limits. Columbus is evaluating non-potable reuse to support industrial growth and preserve drinking water, including a centralized facility that could produce 20–40 million gallons a day of reclaimed water for uses such as data center cooling.16 For a Central Ohio site, confirm water and sewer capacity with the provider in writing. See municipal water and sewer capacity and reclaimed water for cooling.
07Site-ready programs and former power plant sites
Ohio funds infrastructure for project-ready sites through the All Ohio Future Fund, a $750 million program launched in 2024 and administered by the Ohio Department of Development.9 Awards are mainly 0% interest, partially forgivable loans; the guidelines favor publicly owned sites, sites meeting JobsOhio certification criteria and sites of 30 acres or more, and funds cannot be used to buy land or construct buildings.9
One award shows the pattern for data centers: the state Controlling Board released $58,752,504 to the Coshocton County Port Authority for site preparation, roads, utilities and water and wastewater work at the former Conesville Power Plant, to prepare an industrial park for manufacturing, a data center and power generation.10 Retired plant sites can offer transmission and water, but bring environmental and title questions; see repurposing industrial and power plant sites and certified sites and shovel-ready programs.
08How to screen an Ohio site
- 01Identify the electric utility. In AEP Ohio territory, plan for the data center tariff’s 85% minimum demand, up to 12-year term and credit requirements.1
- 02Ask what is already contracted near the site; Central Ohio holds most of AEP Ohio’s signed data center load.2
- 03Include PJM capacity costs, and the chance they rise, in power cost models.3
- 04Check township and municipal zoning and any moratoriums before signing an option.515
- 05Model the sales tax exemption as paused for new requests.4
- 06If on-site generation is part of the plan, test gas supply and HB 15 eligibility early.713
- 07Confirm water, sewer, fiber, buildable acreage and drainage on the specific tract.
Our methodology explains how we weigh these factors, and you can get a site reviewed before you file a load study request.
Common questions
What is AEP Ohio’s data center tariff?
It is a set of terms PUCO approved on July 9, 2025 for new data centers in AEP Ohio territory. Customers pay for at least 85% of their subscribed power for up to 12 years, including a four-year ramp, must show financial viability and owe an exit fee if they cancel.1 It targets loads above 25 MW.11
How much data center load has AEP Ohio signed?
AEP Ohio reported 5,642 MW of signed data center agreements under the tariff as of February 12, 2026, including 4,842 MW in Central Ohio, with in-service dates by 2030.2 That is far below the more than 30 GW of interest the utility saw before the tariff.2
Does Ohio still have a data center sales tax exemption?
The exemption exists, because Governor DeWine vetoed its repeal in 2025.6 But in May 2026 he paused new exemption requests to the Tax Credit Authority while a legislative committee studies data centers; approved exemptions remain in effect.4
Why are PJM capacity prices important for Ohio data centers?
Ohio is in PJM, so capacity costs from PJM’s auctions are part of the delivered price of power. The 2028/2029 auction cleared at the $325/MW-day cap and fell 6,831 MW short of the reliability requirement, a sign of tight supply.3
Can an Ohio data center build its own power plant?
HB 15 (2025) loosened restrictions on behind-the-meter generation, including some flexibility when the generator is not adjacent to the customer.713 Projects still need gas supply, siting and air permits; one proposal in Licking County would serve a New Albany data center with up to 120 MW of gas generation.8
Notes
- 1.POWER Magazine, “Regulator Approves AEP Ohio’s Landmark Data Center Tariff,” 2025. powermag.com
- 2.New Project Media, “POLICY: AEP Ohio touts ‘right-sized load’ as data center pipeline shrinks further under new tariff,” 2026. newprojectmedia.com
- 3.PJM Interconnection, “PJM Capacity Auction Procures 138,318 MW of Generation Resources,” 2026. pjm.com
- 4.WSAZ, “Ohio Gov. DeWine announces a pause on data center tax exemption requests,” 2026. wsaz.com
- 5.The Reporting Project, “No data centers here: St. Albans Township officials seek to ban complexes popping up around them,” 2026. thereportingproject.org
- 6.WVXU, “Following DeWine’s veto, sales tax break for Ohio data centers survives, for now,” 2025. wvxu.org
- 7.Canary Media, “Why the solar industry is counting Ohio’s newest energy law as a win,” 2025. canarymedia.com
- 8.The Reporting Project, “Gas-fired power plant to serve data center is proposed for western Licking County,” n.d. thereportingproject.org
- 9.Tucker Ellis, “State Launches $750 Million All Ohio Future Fund for Project-Ready Sites,” 2024. tuckerellis.com
- 10.Ohio House of Representatives, “Hiner applauds approval of All Ohio Future funding for Conesville Industrial Park in Coshocton,” n.d. ohiohouse.gov
- 11.Renewable Energy World, “Ohio utility regulators approve AEP’s contested data center tariff proposal,” 2025. renewableenergyworld.com
- 12.American Electric Power, “Form 8-K, Exhibit 99.1: First Quarter 2026 Earnings Release,” 2026. sec.gov
- 13.Public Utilities Commission of Ohio, “PUCO Chair French Comments Before the Select Committee on Data Centers,” 2026. search-prod.lis.state.oh.us
- 14.Ohio Capital Journal, “Ohio House approves data center study group, delays vote on overriding tax exemption,” 2026. ohiocapitaljournal.com
- 15.FOX19, “Pierce Township trustees rule out data center, extend zoning moratorium,” 2026. fox19.com
- 16.WaterWorld, “Columbus explores water reuse to support data center growth and long-term water supply needs,” 2026. waterworld.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Related guides
More in Site selection by state
- Data Center Site Selection in Texas: Grids, SB 6, Water and Incentives
- Data Center Site Selection in Virginia: Power, GS-5, Zoning and Tax Rules
- Data Center Site Selection in Georgia: Georgia Power, PSC Rules, Water and Taxes
- Data Center Site Selection in Arizona: APS, SRP, TEP, Water and Heat
- Data Center Site Selection in Illinois: ComEd, Ameren, PJM vs. MISO and the Incentive Pause
- Data Center Site Selection in Nevada: NV Energy, Reno and Las Vegas, Water Rules and GOED Abatements
- Data Center Site Selection in Oregon
- Data Center Site Selection in Iowa
- Data Center Site Selection in North Carolina
- Data Center Site Selection in South Carolina
- Data Center Site Selection in Indiana
- Data Center Site Selection in Wisconsin
- Data Center Site Selection in Minnesota
- Data Center Site Selection in Nebraska
- Data Center Site Selection in Oklahoma
- Data Center Site Selection in Utah
- Data Center Site Selection in Washington State
- Data Center Site Selection in Louisiana
- Data Center Site Selection in Mississippi
- Data Center Site Selection in Alabama
- Data Center Site Selection in Tennessee
- Data Center Site Selection in Kentucky
- Data Center Site Selection in Missouri
- Data Center Site Selection in Kansas
- Data Center Site Selection in New Mexico
- Data Center Site Selection in Wyoming
- Data Center Site Selection in North Dakota
- Data Center Site Selection in New York: NYISO, Hydropower and the 2026 Permit Pause
- Data Center Site Selection in Michigan: DTE, Consumers, Tax Rules and Water
- Data Center Site Selection in Arkansas: Entergy, SWEPCO, 2025 Laws and Local Rules
- Data Center Site Selection in Colorado: Xcel’s Large-Load Tariff, Water and Local Rules
- Data Center Site Selection in Idaho
- Data Center Site Selection in West Virginia
- Data Center Site Selection in Maryland
- Data Center Site Selection in Montana
- Data Center Site Selection in South Dakota
- Data Center Site Selection in Florida
