BlackForge Data Centers

Site selection by state

Data Center Site Selection in Kansas

Senate Bill 98, signed in April 2025, gives data centers that invest at least $250 million a 20-year sales tax exemption,1 and Evergy’s Kansas utilities must apply a large-load tariff to new customers of 75 MW or more.2 Wind supplied about 52% of the state’s electricity in 2024,3 and Kansas sits inside the Southwest Power Pool, which is building a 765 kV backbone and won FERC acceptance of a fast-track study path for large loads in January 2026.45 Water rights, county moratoriums and the 80% minimum bill are the main things to check before signing.

Last reviewed · 10 min read · BlackForge Data Centers

Key takeaways

  • SB 98 exempts construction, equipment and installation labor from state and local sales tax for qualifying data centers that reach $250 million of investment and 20 jobs.6
  • The Kansas Corporation Commission (KCC) approved Evergy’s large-load power service tariff 3–0 on November 6, 2025, with an 80% minimum demand charge, two years of collateral and a 12-year minimum term plus an optional ramp of up to five years.27
  • Evergy reported five signed data center service agreements totaling about 2.5 GW of steady-state peak load in its first-quarter 2026 results.8
  • Digital Realty’s planned De Soto campus has an Evergy agreement for 600 MW by early 2028, scalable to 2 GW.9
  • Cooling water is an industrial use in Kansas, so a site needs a public water supplier, a new permit or a purchased and converted water right.10
  • Several counties, including Saline, Sedgwick and Harvey, have adopted data center moratoriums.11

01SB 98: Kansas’s data center sales tax exemption

Gov. Laura Kelly signed Senate Bill 98 on April 24, 2025.12 It creates a sales tax exemption for building, enlarging or remodeling a qualified data center and for buying its equipment, with a minimum investment of $250 million.12 The Kansas exemption runs for 20 years and covers both state and local sales tax.1

To qualify, a business must reach $250 million of eligible data center costs in aggregate by its fifth year of operations and create and maintain at least 20 new jobs at the facility within two calendar years after operations begin.16 The exemption covers property and services bought to construct or remodel the facility, the sale and installation of machinery and data center equipment, and the labor to install, repair and maintain that equipment.6 It applies to qualifying purchases made on or after July 1, 2025, and is claimed with a project exemption certificate given to contractors.6

Fig. 1SB 98 headline terms

minimum eligible investment by year 5
$250M
new jobs within two years of operation
20
state and local sales tax exemption
20 yrs
to begin construction after approval
10 yrs
Summary of the 2025 statute and practitioner summaries. Confirm current requirements with the Kansas Department of Commerce and Department of Revenue.16

There are limits worth reading closely. Telecommunications, wireless and video service providers are excluded, and a qualified business must begin construction within 10 years of state approval.6 Projects also go through a cybersecurity and critical-infrastructure risk review by the Kansas Intelligence Fusion Center.6 The same bill bars utilities from offering discounted economic development electric rates to new or expanded data centers, so the tax break and the power price are deliberately kept separate.12

The $250 million floor means SB 98 is aimed at hyperscale and large colocation campuses, not small enterprise rooms. Compare it with neighboring programs in our sales tax exemptions by state guide, and remember that local property tax abatements are negotiated separately.

02Evergy’s large-load power service tariff

Evergy’s Kansas utilities serve many of the state’s largest announced projects, so the KCC’s 2025 decision on Evergy’s large-load power service (LLPS) tariff sets the commercial terms for much of the state’s pipeline.89 On November 6, 2025, the commission voted 3–0 to adopt a settlement creating LLPS rates for Evergy’s Kansas utilities, for customers whose peak load is reasonably expected to reach a monthly maximum demand of 75 MW or more.2 Existing businesses that add 75 MW of new load also come under the tariff.2

The settlement was filed in August 2025 by Evergy, KCC staff, the Citizens’ Utility Ratepayer Board, the Data Center Coalition, Sierra Club, NRDC and Google, among others.213 The Sierra Club says its intervention helped lower the size threshold from 100 MW to 75 MW and lengthen the minimum term.13

  • Minimum bill: customers pay at least 80% of their contracted demand, even in months they use less.2
  • Collateral: security equal to two years of minimum bills.2
  • Term: a minimum of 12 years plus an optional load ramp of up to five years, so up to 17 years in total.7
  • Cost recovery: the rules let Evergy recover the cost of new lines, transformers, substations and generation built to serve the load.2

KCC Chair Andrew French said the deal protects existing customers while providing “a pathway for economic development.”2 For a landowner or developer, the practical effect is a long take-or-pay obligation that should be modeled at full contracted load and matched to a realistic ramp schedule. Our large-load tariffs guide explains how these contracts are underwritten.

03Kansas City, De Soto and Evergy’s pipeline

The Kansas side of the Kansas City metro holds the state’s largest announced campus. Digital Realty bought about 1,400 acres in Astra Enterprise Park in De Soto, a large business park on the grounds of the former Sunflower Army Ammunition Plant.9 It holds an energy service agreement with Evergy for 600 MW by early 2028 that can scale to 2 GW, and the first phase is estimated at about $4 billion before data center equipment.9 Former military and industrial tracts like this can offer scale and existing infrastructure, but they need careful environmental and title review.

Evergy’s broader book is growing. In its first-quarter 2026 results, the company said it had signed a new agreement with a developer for a data center in its Kansas Central service territory, bringing its data center service agreements to five with about 2.5 GW of steady-state peak load, and said it was in advanced discussions for another 1.5–3 GW of large loads after 2030.8

That load needs new generation. In July 2025 the KCC approved Evergy Kansas Central’s plan to co-own, at 50%, two 710 MW combined-cycle gas plants, Viola in Sumner County and McNew in Reno County, along with the Kansas Sky solar facility in Douglas County.14 Kansas Central customers were expected to see bills rise about 8.6% to build them, and the commission said it was “troubled by the frequency and magnitude of rate cases.”14 That tension is why the LLPS tariff exists, and it is a reason to expect regulators to keep scrutinizing who pays. Our guide to data centers and ratepayers covers the debate.

The metro spans the state line, and Missouri has its own tariff and incentive rules. Compare both sides with our Missouri guide before choosing a parcel near the line.

04SPP wind, transmission and large-load studies

Kansas is a wind state. Wind supplied 52% of in-state net generation in 2024, a lead it has held over coal since 2019, while coal supplied 22%.3 For buyers that want renewable supply, that mix makes clean energy procurement more practical than in coal-heavy states, though the hourly profile still requires firm resources behind it. See our renewable procurement guide for how that affects siting.

Fig. 2Kansas electricity generation by source, 2024

  • Wind52
  • Coal22
  • All other sources26

% of net generation

Wind and coal shares from EIA; “all other” is the remainder and includes nuclear, natural gas and other sources.3

Moving that wind to load is the job of the Southwest Power Pool. SPP’s 2025 Integrated Transmission Plan approved about $8.6 billion of new transmission, including 949 miles of new 765 kV line, as the start of a regional 765 kV backbone.4 Projects of that scale take years to permit and build, so treat future lines as upside, not as the basis for an energization date.

SPP also has a dedicated path for big loads. On January 14, 2026, FERC accepted SPP’s high impact large load (HILL) rules, which define a HILL as a new load of 10 MW or more at a single site connected at 69 kV or below, or 50 MW or more at higher voltages.5 The package includes an optional generation-pairing assessment with a 90-day study target and a conditional service option that lets a load connect on a curtailable basis until firm service is available.5 Our SPP guide explains the study process, and the interconnection studies entry covers the vocabulary.

05Water rights and the Ogallala

Kansas manages water under a permit system administered by the Kansas Department of Agriculture’s Division of Water Resources (DWR). Its 2026 data center FAQ treats water used for cooling as an industrial use, which requires a permit unless the water comes from a public water supplier such as a city or rural water district.10 New groundwater permits are available only in areas still open to appropriation, subject to safe-yield limits and well spacing rules that protect existing users.10

Fig. 3Three ways to secure cooling water in Kansas

No DWR permit

Public water supplier

  • City or rural water district serves the site
  • Capacity depends on the supplier’s own rights
  • Needs a service agreement and plant capacity

New appropriation

  • Only in areas open to new appropriation
  • Subject to safe-yield limits
  • Well spacing protects existing users

Closed areas

Buy and convert a right

  • Purchase land or a facility with a right
  • Change from irrigation to industrial use
  • Capped at historical consumptive use
Simplified from DWR’s data center FAQ; confirm with the local DWR field office and groundwater district.10

In closed or fully appropriated areas, the route is to buy an existing right, which transfers with the land, and change its use. When an irrigation right is converted, the new quantity is limited to the historical consumptive use of the original right, so that the change does not increase net depletions.10 That matters because irrigation accounts for about 85% of consumptive water use in Kansas on average.15

In western Kansas the question is sharper. Backers of a proposed AI data center in Finney County argue it could use less water than the irrigated farming it replaces, while the Ogallala Aquifer beneath it has been in steep decline.16 Closed-loop or air-cooled designs reduce the problem but shift load onto the power side. See our guide to water rights and groundwater for the general framework.

06County approvals and moratoriums

Kansas zoning is largely a city and county matter, and in 2026 several counties paused data center development while they wrote rules. The Saline County Commission voted 4–0 for a three-year moratorium on data centers, nuclear power and hydrogen-based energy facilities in unincorporated areas, joining Sedgwick and Harvey counties, which had also adopted data center moratoriums.11

Leavenworth County shows how quickly the picture can change. After debate over a proposed hyperscale campus near Tonganoxie, the county commission lifted its data center moratorium on a 3–2 vote in August 2026.17 A pause can end, be extended or turn into a permanent ordinance with setbacks, noise limits and other conditions, and new commissioners can change the vote count.

For a seller, the safest assumption is that any unincorporated parcel may need a rezoning or special use permit, with public hearings. Build that time into the option term, and read our guides to moratoriums and local restrictions and community engagement. Central and western Kansas sites should also be screened for tornado and high-wind exposure.

07How to start a Kansas site screen

  1. 01Confirm the serving utility (Evergy, a cooperative or a municipal system) and whether the LLPS tariff applies at your planned load.
  2. 02Model the 80% minimum bill, collateral and contract term at full contracted demand.
  3. 03Ask the utility where new generation and transmission sit relative to your ramp, and whether an SPP large-load study is needed.
  4. 04Check the county’s current status: moratorium, pending ordinance or existing data center zoning.
  5. 05Identify the water source and whether the area is open to new appropriation.
  6. 06Map the SB 98 investment and job deadlines against your construction and hiring schedule.

Fig. 4Sample screen of a Kansas parcel

Illustrative
  • PassServing utilityEvergy territory; LLPS tariff applies above 75 MW.
  • WatchTransmission345 kV line 3 miles away; new substation needed.
  • WatchWaterArea closed to new rights; must buy and convert one.
  • FailCounty zoningMoratorium in place until rules are adopted.
  • PassSB 98 fitPlanned phase one exceeds $250 million.
Illustrative sample. Not a real parcel; criteria reflect the issues discussed in this guide.

Kansas’s advantages are real: abundant wind, open land and a clear tax exemption. The constraints are mostly about timing and terms, from generation build-out to county hearings to water rights. Ask the utility and county for written answers before paying for a long option. Our due diligence checklist and will-serve letter guide expand on these steps. If you have Kansas land and want an independent read, get a site reviewed.

Common questions

What is the Kansas data center sales tax exemption?

Senate Bill 98, signed in April 2025, exempts qualifying data centers from state and local sales tax for 20 years on construction, equipment and related labor.16 Projects must reach $250 million of investment by their fifth year and create 20 jobs within two years of opening.6

Does Evergy have a data center tariff in Kansas?

Yes. The KCC approved Evergy’s large-load power service tariff in November 2025 for customers expected to reach 75 MW or more.2 It requires an 80% minimum demand charge, collateral equal to two years of minimum bills and a contract of at least 12 years after an optional ramp of up to five years.27

Is Kansas in SPP?

Yes. Kansas sits in the Southwest Power Pool, whose 2025 transmission plan includes new 765 kV lines and which received FERC approval in January 2026 for its high impact large load study process.45

Do Kansas data centers need a water permit?

Cooling water is treated as an industrial use, so a permit is required unless the water comes from a city or rural water district.10 In closed areas, a project usually has to buy an existing right and convert it, limited to its historical consumptive use.10

Are there data center moratoriums in Kansas?

Yes. Saline County adopted a three-year moratorium in 2026, and Sedgwick and Harvey counties also adopted moratoriums.11 Leavenworth County lifted its moratorium in August 2026.17 Check the county’s current status before committing.

Notes

  1. 1.Husch Blackwell, “Kansas Enacts 20-Year Sales Tax Exemption for Data Centers,” 2025. huschblackwell.com
  2. 2.Renewable Energy World (Kansas Reflector), “New Kansas rules set guidelines for data centers, big power users to protect smaller customers,” 2025. renewableenergyworld.com
  3. 3.U.S. Energy Information Administration, “Kansas State Profile and Energy Estimates: Analysis,” 2025. eia.gov
  4. 4.Southwest Power Pool, “2025 ITP Fact Sheet,” 2025. spp.org
  5. 5.Wright & Talisman, “The HILLs Have Ayes: FERC Unanimously Approves SPP’s High Impact Large Load Study Process and High Impact Large Load Generation Assessment Process,” 2026. wrightlaw.com
  6. 6.Sales Tax Institute, “Kansas Offers Data Center Tax Exemption to Attract High-Tech Investment,” 2025. salestaxinstitute.com
  7. 7.Kansas Corporation Commission, “News Release, November 6, 2025,” 2025. kcc.ks.gov
  8. 8.Yahoo Finance, “Evergy (EVRG) Q1 2026 earnings,” 2026. finance.yahoo.com
  9. 9.Ingram’s, “Digital Realty Wants to Build 600MW Data Center Campus in De Soto,” n.d. ingrams.com
  10. 10.Kansas Department of Agriculture, Division of Water Resources, “Data Center FAQ,” 2026. agriculture.ks.gov
  11. 11.Yahoo News, “Kansas county puts moratorium on data centers and nuclear, hydrogen plants,” 2026. yahoo.com
  12. 12.Kansas Legislature, “SB 98,” 2025. kslegislature.gov
  13. 13.Sierra Club, “Sierra Club Supports KCC Approved Plan to Protect Customers,” 2025. sierraclub.org
  14. 14.Kansas Reflector, “Kansas regulators approve Evergy natural gas plants, solar plant despite rate concerns,” 2025. kansasreflector.com
  15. 15.Kansas Department of Agriculture, “Water Use Reporting,” n.d. agriculture.ks.gov
  16. 16.High Plains Public Radio, “An AI data center project for western Kansas might use less water than irrigation farming,” 2026. hppr.org
  17. 17.The Mirror (Tonganoxie), “Leavenworth County Commission lifts moratorium on data center by 3-2 vote,” 2026. tonganoxiemirror.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Related guides

More in Site selection by state