Key takeaways
- Grant PUD serves eight data center operators that used about 280 average megawatts in 2025, and its 2024 queue showed 1,578 MW of interest in the Quincy area alone.15
- New large loads at Grant PUD are served under a separate schedule, and staff proposed new high-density computing rate classes for 2027 in September 2026.67
- Chelan PUD evaluates each data center request under a 2024 framework and takes every large-load deal to its board for approval.2
- The rural sales tax exemption needs at least 20,000 square feet of server space in a rural county; since 2022 there is no cap on certificates for new data centers.4
- SB 6231 (2026) removed the exemption for replacing servers at existing data centers starting July 1, 2026, while keeping it for new facilities.8
- Washington’s Clean Energy Transformation Act requires carbon-neutral retail electricity by 2030 and 100% clean by 2045, which shapes how utilities price new supply.9
01Where Washington’s data centers are
Most of Washington’s large data center capacity is east of the Cascades, in three counties along the Columbia River. Grant County, with Quincy at its center, is the largest cluster: Grant PUD serves eight data center operators, which accounted for about 280 average megawatts of load in 2025.1 Across the river, Douglas County hosts campuses in East Wenatchee, including Sabey’s, and a Microsoft load of 180 MW served under a 2023 agreement with Douglas County PUD.103 In Chelan County, home to Wenatchee, the PUD reported in 2024 that a Microsoft data center was under construction in the Malaga area.2
The common thread is the serving utility. All three counties are served by public utility districts that own large hydroelectric projects on the Columbia, rather than by an investor-owned utility. Each PUD is governed by an elected commission, sets its own rates and decides for itself how to treat large new loads. That makes a central Washington site screen a utility-by-utility exercise. Our Pacific Northwest guide covers the regional system, and the hydropower guide explains what dam-backed supply can and cannot offer a new campus.
West of the Cascades, the Seattle area has enterprise and colocation capacity close to fiber and customers, but land costs are higher and the sales tax exemption is limited to rural counties, which leaves out the most populous metro areas.4 Large campuses therefore cluster where both the exemption and PUD power are available. For a comparison with the Columbia River sites on the other side of the state line, see our Oregon guide.
02Grant, Chelan and Douglas PUDs: hydropower with conditions
Central Washington’s low-cost reputation comes from PUD-owned dams, but the PUDs have spent more than a decade separating new large loads from that legacy supply. In 2015, Chelan PUD modified a pause on new large loads so that it applied only to customers using 250 kWh per square foot or more per year, rather than to every applicant for 1 MW or more, and proposed a separate high-density load rate for server farms.11 Douglas County PUD’s 180 MW Microsoft agreement runs from January 2023 to December 31, 2029, timed to finish before Washington’s 2030 clean energy requirements take hold.3
Fig. 1How the three central Washington PUDs handle large loads
Largest cluster
Grant PUD
- Eight data center operators, about 280 aMW in 2025
- New large loads served on a separate schedule
- High-density computing rate classes proposed for 2027
Chelan PUD
- 2024 framework to evaluate each request
- Market supply, customer-procured power or negotiated contract
- Every large-load deal goes to the board
Douglas County PUD
- Separate reserve power deal for Sabey’s campus
- 180 MW Microsoft agreement through 2029
- Customer paid for the substation built to serve it
Chelan PUD’s 2024 framework is the clearest statement of how a PUD now thinks about data centers. Its guiding principles are a neutral-to-positive impact on other customers, reliability, stable and predictable rates, local control, and protection of the PUD’s existing hydropower marketing strategy. It offers three paths: short-term market supply, power the customer procures itself, or a negotiated contract that may include PUD generation, and each arrangement goes to the board for approval.2 Staff also noted that a typical large data center could more than double the existing load in Chelan PUD’s territory.2
The logic is the same across the three PUDs. Hydro output already serves existing customers and supports wholesale sales that help hold down local rates, and Chelan PUD lists protecting that marketing strategy as a guiding principle.2 A new campus is therefore priced at what new or market supply costs, not at the cost of the dam.
03Grant PUD’s queue and large-load rates
Grant PUD is the utility most site seekers call first, and its queue shows why central Washington is now a constrained market. As of August 2024, the PUD had 75 applications for new and expanding power service, and the Quincy area alone accounted for 1,578 MW of requested load.5 Compare that with the roughly 280 average megawatts its eight data center operators used in 2025.1
Fig. 2Grant PUD data center load and demand
- Data center operators served in 2025
- 8
- Data center load in 2025
- ~280 aMW
- Large-load applications, August 2024
- 75
- Requested load in the Quincy area
- 1,578 MW
The rate structure separates existing industrial customers from new large loads. Grant PUD’s Rate Schedule 15, Large Industrial, applies to industrial customers with billing demand of 10 MW or more and took effect for meter readings after April 1, 2025, with a demand charge of $6.03 per kW of billing demand. But any load that is or becomes a New Large Load under the PUD’s customer service policies is served under Rate Schedule 94 instead.6 Read the definition of a New Large Load closely: an expansion of an existing account can trigger it.
Rates are still moving. At a September 15, 2026 workshop, staff proposed new rate classes for 2027: a Tier 2 group including Rate 20, High Density Compute, and Rate 21, Large High-Density Compute, would see an average increase of 12.5%, against 9.5% for the Tier 1 industrial classes.7 As of October 2026 these were proposals, not adopted rates. Our guide to large-load tariffs and electric service agreements covers the contract terms to expect.
04Why new supply is tight
Three forces make new power scarce in central Washington. First, the hydro is spoken for: PUD output already serves existing customers and wholesale sales, so new load means buying or building new supply.2 Second, regional demand is rising fast. The Northwest Power and Conservation Council’s 2025 forecast found that electricity demand in the Northwest could double over the next 20 years, with data centers a main driver of near-term growth.12
Third, state law limits what that new supply can be. The Clean Energy Transformation Act required utilities to stop serving Washington customers with coal-fired power by the end of 2025, requires carbon-neutral electricity by 2030, and requires all retail electricity to come from renewable or non-carbon sources by 2045.9 For a data center, that means new gas generation is a harder fit than in states such as Louisiana or Texas, and contracts for new clean resources carry the cost of new projects. Douglas County PUD timed its Microsoft agreement to end before the 2030 requirements take effect.3
Transmission adds a fourth limit. A parcel near a dam does not automatically have access to its output, and new substation and line work can set the energization date. Ask the PUD what upgrades your load would trigger and whether it would be served from an existing substation. Douglas County PUD, for example, added 18 MW of reserve power for Sabey’s East Wenatchee campus through its Pangborn Substation under an interconnection and service agreement.10
05The rural data center sales tax exemption
Washington’s data center sales tax exemption, in RCW 82.08.986 and 82.12.986, is the main state incentive, and it is limited by geography. According to the Department of Revenue, a computer data center qualifies if it is in a rural county as defined in RCW 82.14.370, has at least 20,000 square feet dedicated to housing working servers, and begins construction after March 31, 2010 and before July 1, 2035 (excluding July 1, 2011 through March 31, 2012).4 The exemption covers eligible server equipment and the labor to install it, plus eligible power infrastructure.4
| Element | Rule |
|---|---|
| Location | Rural county under RCW 82.14.3704 |
| Size | At least 20,000 sq ft for working servers4 |
| Construction start | After March 31, 2010 and before July 1, 20354 |
| Covered | Server equipment, power infrastructure and installation labor4 |
| Certificates | No limit for new data centers since June 10, 20224 |
| Server replacement | Exemption removed for existing data centers from July 1, 20268 |
The exemption has been reviewed before. JLARC’s 2016 review recommended continuing it, finding that the goals of higher rural property values and property taxes from data center investment were being met, while urging the Legislature to check periodically whether the benefits exceed the long-term cost.13 In 2025, Gov. Bob Ferguson’s data center work group debated a draft recommendation that would have tied the tax break to clean power sourcing while extending it to data centers statewide; it was the one draft recommendation of nine expected to be left out of the final report.14
In 2026, the Legislature narrowed the incentive instead. SB 6231 removes the exemption for replacing server equipment at existing data centers starting July 1, 2026, while preserving it for new facilities; the Department of Revenue estimated $63.1 million in added revenue in the current biennium and $143.9 million in 2027–29.8 A broader bill, HB 2515, which would have regulated data center electricity rates and environmental impacts, did not pass after Microsoft came out against it.15 Expect the debate to return, and confirm eligibility with a Washington tax advisor. Our sales tax exemptions by state guide compares Washington with other states.
06Water in a dry basin: the Quincy reuse model
Quincy shows both the water problem and one answer to it. The city gets about 7.8 inches of rain a year, and five groundwater wells supply all of its residential, commercial and industrial water.16 The local groundwater is high in total dissolved solids, which causes problems in data center cooling equipment.16
The city’s Water Reuse Utility, built with Microsoft at a cost of about $31 million, treats cooling water from Microsoft’s data center and returns it for reuse. It includes 10 treatment systems linked by more than 30 miles of pipe across Quincy’s industrial area, concentrates salts in lined brine ponds and does not discharge to the environment or the city’s wastewater plant. EPA’s case study reports a demand offset of 138 million gallons per year.16
For a new site, the lesson is that water in central Washington is an infrastructure question as much as a supply question. Ask the city or water district whether a reuse or industrial water system can serve the parcel, what the discharge path is for cooling blowdown, and whether a closed-loop design would avoid the issue. Water rights in Washington follow prior appropriation; our guides to water rights and groundwater and reclaimed water for cooling go further.
07How to screen a Washington site
Fig. 3Washington policy windows that affect a project
- Exemption construction windowStart construction before July 1, 2035
- Douglas PUD Microsoft agreementJanuary 2023 to December 31, 2029
- CETA carbon-neutral period100% clean retail electricity by 2045
- 01Confirm the serving PUD and whether the parcel is in a rural county that qualifies for the exemption.4
- 02Ask the PUD which large-load schedule or framework applies, and whether your ramp would make the account a new large load.62
- 03Ask where the request would sit in the queue and which substation and transmission upgrades it would need.5
- 04Plan for supply that meets state clean energy rules after 2030, and price it as new supply, not legacy hydro.9
- 05Map the water source and discharge path, and check whether a reuse system is available.16
- 06Confirm tax eligibility for the actual owner and equipment, including the 2026 change for server replacement.8
Central Washington still has what made it attractive: PUD-owned hydro, a dry climate and an established workforce around existing campuses. What has changed is that power is allocated deal by deal. Our methodology explains how we weigh utility, water and incentive questions together, and you can get a site reviewed to test a specific parcel.
Common questions
Why are there so many data centers in Quincy, Washington?
Quincy combines Grant PUD power from Columbia River dams, a dry climate, available industrial land and the state’s rural sales tax exemption.14 The Quincy area accounted for 1,578 MW of requested load in Grant PUD’s 2024 queue.5
Does Washington have a data center sales tax exemption?
Yes, but only in rural counties. Qualifying data centers need at least 20,000 square feet of server space and must start construction before July 1, 2035.4 Since July 1, 2026, the exemption no longer covers replacing servers at existing data centers.8
Can a new data center get cheap hydropower in central Washington?
Not usually at legacy rates. Grant PUD serves new large loads under a separate schedule, and Chelan PUD offers market supply, customer-procured power or a negotiated contract approved by its board.62
How does the Clean Energy Transformation Act affect data centers?
CETA requires carbon-neutral retail electricity by 2030 and 100% renewable or non-carbon electricity by 2045.9 New supply for a data center has to fit those rules, which favors clean resources over new gas.
Notes
- 1.Grant PUD, “Data Center FAQs,” n.d. grantpud.org
- 2.Chelan PUD, “Commissioners consider framework to evaluate future data center requests,” 2024. chelanpud.org
- 3.Talk 106.7 (Wenatchee), “Douglas County PUD, Microsoft enter power delivery agreement,” n.d. talk1067.com
- 4.Washington State Department of Revenue, “Sales and use tax exemption for rural data centers expanded,” 2022. dor.wa.gov
- 5.Grant PUD, “Commission Recap 8-27-2024,” 2024. grantpud.org
- 6.Grant PUD, “Rate Schedule 15: Large Industrial,” 2025. grantpud.org
- 7.Columbia Basin Herald (Source One), “Grant PUD eyes new rate changes for data centers, public buildings,” 2026. yoursourceone.com
- 8.Bloomberg Tax, “Washington to End Data Center Tax Break for Replacing Servers,” 2026. news.bgov.com
- 9.PV Tech, “Washington state reveals rules to guide utilities to carbon-free generation by 2045,” n.d. pv-tech.org
- 10.The Wenatchee World, “Douglas County PUD releases reserve power to East Wenatchee data center,” n.d. wenatcheeworld.com
- 11.Clearing Up (via Chelan PUD), “Chelan PUD extends large load pause,” 2015. chelanpud.org
- 12.Washington State Standard, “Electricity demand in Northwest could double in next 20 years, forecast finds,” 2025. washingtonstatestandard.com
- 13.Joint Legislative Audit and Review Committee, “2016 Tax Preferences: Data Center Equipment,” 2016. leg.wa.gov
- 14.OPB, “Should Washington’s data centers generate their own clean energy to get tax breaks?,” 2025. opb.org
- 15.GeekWire, “Big tech dodged Washington state’s data center rules but didn’t escape a sales tax bill,” 2026. geekwire.com
- 16.U.S. Environmental Protection Agency, “Water Reuse Case Study: Quincy, Washington,” n.d. 19january2025snapshot.epa.gov
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Related guides
More in Site selection by state
- Data Center Site Selection in Texas: Grids, SB 6, Water and Incentives
- Data Center Site Selection in Virginia: Power, GS-5, Zoning and Tax Rules
- Data Center Site Selection in Georgia: Georgia Power, PSC Rules, Water and Taxes
- Data Center Site Selection in Arizona: APS, SRP, TEP, Water and Heat
- Data Center Site Selection in Ohio: AEP Ohio’s Tariff, PJM Costs and the Tax Pause
- Data Center Site Selection in Illinois: ComEd, Ameren, PJM vs. MISO and the Incentive Pause
- Data Center Site Selection in Nevada: NV Energy, Reno and Las Vegas, Water Rules and GOED Abatements
- Data Center Site Selection in Iowa
- Data Center Site Selection in North Carolina
- Data Center Site Selection in South Carolina
- Data Center Site Selection in Pennsylvania
- Data Center Site Selection in Indiana
- Data Center Site Selection in Wisconsin
- Data Center Site Selection in Minnesota
- Data Center Site Selection in Nebraska
- Data Center Site Selection in Oklahoma
- Data Center Site Selection in Utah
- Data Center Site Selection in Louisiana
- Data Center Site Selection in Mississippi
- Data Center Site Selection in Alabama
- Data Center Site Selection in Tennessee
- Data Center Site Selection in Kentucky
- Data Center Site Selection in Missouri
- Data Center Site Selection in Kansas
- Data Center Site Selection in New Mexico
- Data Center Site Selection in Wyoming
- Data Center Site Selection in North Dakota
- Data Center Site Selection in New York: NYISO, Hydropower and the 2026 Permit Pause
- Data Center Site Selection in Michigan: DTE, Consumers, Tax Rules and Water
- Data Center Site Selection in Arkansas: Entergy, SWEPCO, 2025 Laws and Local Rules
- Data Center Site Selection in Colorado: Xcel’s Large-Load Tariff, Water and Local Rules
- Data Center Site Selection in Idaho
- Data Center Site Selection in West Virginia
- Data Center Site Selection in Maryland
- Data Center Site Selection in Montana
- Data Center Site Selection in South Dakota
- Data Center Site Selection in Florida
