Key takeaways
- Start with the service territory: Entergy Mississippi, Mississippi Power and TVA’s local power companies each have different processes, rate structures and generation plans.
- The standard data center incentive requires MDA approval, at least $20 million of investment and 20 jobs paying 125% of the state average wage.6
- Amazon’s Madison County project used a 2024 special-session package, and the 2024 law let Entergy build for the project without advance Public Service Commission approval.75
- In TVA territory, new or expanding data center loads above 5 MW face a capacity commitment charge from October 1, 2026, and loads above 100 MW need TVA board approval.89
- On-site gas generation is possible but contested: xAI’s 41-turbine permit in Southaven drew unanimous opposition at its public hearing, was approved in March 2026 and was appealed in April.1011
01Three power systems in one state
Mississippi does not have a single power market. A parcel’s utility service territory determines who studies the load, who builds the generation and which rules apply. Entergy Mississippi serves much of the central and western state and operates within MISO, the regional market covered in our MISO site selection guide. Mississippi Power, part of Southern Company, serves the southeastern counties, including Meridian, where it agreed to supply about 500 MW to the Compass campus under a special contract approved by the Mississippi PSC.12 Across the north, the Tennessee Valley Authority sells wholesale power to local power companies; Northcentral Electric Cooperative, for example, distributes TVA power in eastern DeSoto County and nearby parts of Marshall, Tate and Lafayette counties.4
Electric cooperatives and municipal systems serve other rural areas and towns. A site that looks attractive on a map can sit a few miles inside the wrong territory, so confirm the serving utility and its wholesale supplier before anything else.
Fig. 1Mississippi’s main utility paths for large loads
Central and west
Entergy Mississippi
- Investor-owned utility in the MISO market
- Serves the Amazon projects around Jackson
- Also serves AVAIO’s Rankin County project
- 2024 law removed advance PSC approval for Amazon-related spending
Southeast
Mississippi Power
- Southern Company subsidiary
- About 500 MW committed to Compass in Meridian
- PSC approved the Compass special contract
- Serves Meridian and the Gulf Coast region
North
TVA local power companies
- Co-ops and municipal utilities buy TVA power
- Loads over 100 MW need TVA board approval
- Data center rate class effective October 2026
- Includes DeSoto County near Memphis
02Central Mississippi: Madison County, Ridgeland and Clinton
The Jackson metro became the state’s first hyperscale cluster in January 2024, when Amazon Web Services committed $10 billion to two hyperscale data centers at two industrial parks in Madison County, with about 1,000 jobs expected.7 Entergy Mississippi supplies the power.13 AWS broke ground later in 2024.14
The cluster has kept growing. In April 2026 Amazon announced another $12 billion, with $11 billion to extend operations in Ridgeland and $1 billion for a new presence in Clinton.15 The Clinton project retrofits the former Delphi plant and is projected to add about 100 jobs, and a separate $3 billion project in Vicksburg was announced in November 2025, bringing Amazon’s planned Mississippi total to about $25 billion.151 That pattern, reusing large industrial buildings with existing utility service, is covered in our guide to repurposing industrial and power plant sites.
For other developers, the Amazon cluster cuts both ways. Entergy’s chief executive has described the utility as building to serve data centers it powers, which signals a utility willing to build for large loads.13 It also means a meaningful share of near-term capacity and transmission work in the Jackson area is already spoken for, so ask Entergy where new loads would fit in its build plan and on what ramp schedule.
03Megaproject deals and the regulator’s role
The biggest Mississippi projects have been negotiated as packages with the Legislature. Lawmakers approved the Amazon incentives in a special session in January 2024.7 The package included $44 million in state incentives, $32 million of it for job training, and let Madison County borrow $215.1 million from the state for roads and water and sewer extensions, to be repaid from the company’s fees in lieu of taxes.7
A 2024 state law limits the Public Service Commission’s power over the Entergy–Amazon contract, and Entergy’s spending and construction for the project do not need the commission’s prior approval; the contract’s length is not public.5 Entergy says the Amazon load will save its other customers money, while a Synapse Energy Economics report argues the projects have likely already raised residential rates.165
For site selection this matters in two ways. A megaproject path can move fast once state leaders commit, but it depends on a project large enough to justify a special session. And the public debate over data centers and electricity ratepayers is active in Mississippi, so expect questions about who pays for new generation at any public hearing.
04The statutory data center incentive
Mississippi’s standing data center tax exemption does not require special legislation.6 To qualify, a company must be approved by the Mississippi Development Authority, invest at least $20 million and create at least 20 full-time jobs paying 125% of the average annual state wage.6 Benefits include a ten-year exemption from sales and use tax on certain construction materials and equipment, plus income and franchise tax exemptions.6
The Legislature lowered these thresholds in 2019, from $50 million of investment, 50 jobs and 150% of the average wage, at MDA’s request; critics now argue the $20 million floor was set for a far less capital-intensive industry.6 Compass Datacenters’ Meridian certification shows how the program applies in practice: ten-year state income and franchise tax exemptions and a sales and use tax exemption covering construction materials, equipment, and software and hardware replacements.12 Refresh cycles for servers make that replacement coverage valuable over a project’s life. Compare it with other states in our sales tax exemptions by state guide.
| Feature | Statutory data center program | Megaproject package |
|---|---|---|
| Approval | MDA certification | Special legislation, e.g., a special session |
| Entry threshold | $20 million and 20 jobs at 125% of average wage | Negotiated project by project |
| Typical benefits | Ten-year sales/use, income and franchise tax exemptions | Training funds, local infrastructure loans and tax exemptions |
| Example | Compass Datacenters, Meridian | Amazon Web Services, Madison County |
05East Mississippi: Meridian and Mississippi Power
Compass Datacenters’ Lauderdale County campus is the clearest Mississippi Power example. The plan calls for an eight-building campus built over about eight years, with Mississippi Power supplying roughly 500 MW.212 The $10 billion headline figure is counted at full occupancy and includes tenants’ IT equipment, not only the developer’s spending, and Mississippi Power is investing in a substation for the I-20/59 Industrial Park.12
Fig. 2Compass Meridian campus at a glance
- data center buildings
- 8
- headline investment at full occupancy
- $10B
- supply from Mississippi Power
- ~500 MW
- planned buildout period
- 8 years
Two lessons carry over to other sites. First, an eight-year, building-by-building plan is a phased buildout, and the utility will want a firm load ramp to plan generation and substations around. Second, headline investment numbers in announcements often bundle tenant equipment, so use MW and buildings, not dollars, when comparing what a utility actually committed to serve.
06North Mississippi: DeSoto County, xAI and TVA rules
DeSoto County, just south of Memphis, is now part of the region’s AI computing cluster. In January 2026 xAI announced a $20 billion data center in Southaven, which Governor Tate Reeves called the largest private investment in state history, as its third data center in the greater Memphis area.3 Its nearby Southaven power plant site supplies xAI’s Colossus 2 data center across the state line in Memphis.10
The permit shows how air permitting can become the critical path. The Mississippi Department of Environmental Quality held a public hearing in Southaven in February 2026, where speakers were unanimously opposed, and the MDEQ Permit Board then unanimously approved a construction permit for xAI affiliate MZX Tech to install 41 gas turbines on March 10, 2026, replacing 27 unpermitted units already on site.10 On April 9, 2026, the Southern Environmental Law Center announced an appeal of the permit on behalf of community groups.11 Anyone planning bridge power or permanent on-site generation should read our guide to air permits for data center generators and budget for organized opposition.
Grid service in north Mississippi runs through TVA’s local power companies.4 On August 20, 2026, the TVA board approved a wholesale rate class for data centers. From October 1, 2026, new or expanding data center loads above 5 MW pay a capacity commitment charge, with an average bill impact of about 10% phased in over three fiscal years, and requests above 100 MW require board approval.8 The Tennessee guide covers the TVA side of the Memphis market.
Fig. 3Announced Mississippi data center investments
- AWS Madison County (2024)10
- AWS expansion (Ridgeland, Clinton)12
- Compass, Meridian10
- xAI, Southaven20
billion dollars
07How to screen a Mississippi site
The projects above share a pattern: a willing utility with a generation plan, a state incentive path matched to project size, and either industrial land or an existing building near strong transmission. A practical first pass looks like this:
- 01Confirm the serving utility and, for co-ops and municipal systems, the wholesale supplier. In TVA territory, model the new data center rate and the 100 MW board approval step.8
- 02Ask the utility how new load fits its generation build plan and what the large-load interconnection process and collateral look like.
- 03Decide early whether the project fits the statutory incentive or needs a negotiated package with MDA.6
- 04If on-site generation is part of the plan, scope the air permit, public hearing and possible appeal before closing on land.10
- 05Check water supply, floodplain mapping and wetlands, which are common constraints in the Delta and along rivers; see our floodplain guide.
Neighboring markets are worth comparing, especially Louisiana and Alabama. If you want an outside read on a specific parcel, you can get a site reviewed.
Common questions
What incentives does Mississippi offer data centers?
Mississippi’s standing program gives MDA-approved data centers ten-year exemptions from sales and use tax on certain construction materials and equipment, plus income and franchise tax exemptions.6 Projects must invest at least $20 million and create 20 jobs paying 125% of the state average wage.6 Very large projects have also received custom packages through special legislation.7
Which utilities serve data centers in Mississippi?
Entergy Mississippi serves the Amazon projects around Jackson,13 Mississippi Power serves the Compass campus in Meridian,12 and TVA-supplied local power companies serve much of north Mississippi.4 Cooperatives and municipal utilities serve other areas, so confirm the territory for each parcel.
Does the Public Service Commission approve power deals for data centers?
It depends on the project. For Amazon, a 2024 law limits the PSC’s power over the Entergy contract and removes the need for prior approval of Entergy’s project spending, and the contract’s length is not public.5 Other projects may go through ordinary regulatory review, so ask the utility which path applies.
How do TVA’s new data center rates affect north Mississippi sites?
From October 1, 2026, new or expanding data center loads above 5 MW in TVA territory pay a capacity commitment charge, and TVA expects an average bill impact of about 10% phased in over three fiscal years.8 Loads above 100 MW also require TVA board approval, which adds a step to the schedule.9
Can a data center in Mississippi build its own gas power plant?
It can, subject to state air permits. xAI received MDEQ Permit Board approval in March 2026 for 41 gas turbines in Southaven after a contentious public hearing, and environmental groups appealed the permit in April 2026.1011 Expect permitting scrutiny and public comment for any large on-site plant.
Notes
- 1.Trade & Industry Development, “MS: Amazon Continues Mississippi Expansion With Plans to Invest $25 Billion Across State,” 2026. tradeandindustrydev.com
- 2.Data Center Dynamics, “Compass Datacenters breaks ground on $10bn campus in Meridian, Mississippi,” 2025. datacenterdynamics.com
- 3.ABC News (Associated Press), “Elon Musk’s xAI to build $20 billion data center in Mississippi,” 2026. abcnews.go.com
- 4.Tennessee Valley Authority, “Northcentral Electric Cooperative,” n.d. tva.com
- 5.Mississippi Today, “Amazon data centers electric bills,” 2026. mississippitoday.org
- 6.Mississippi Today, “Data centers incentives Mississippi,” 2026. mississippitoday.org
- 7.Mississippi Free Press, “Mississippi Approves $44 Million in Incentives for Amazon Project in Madison County,” 2024. mississippifreepress.org
- 8.WSMV, “TVA approves 10% rate spike for data centers to protect household rate payers,” 2026. wsmv.com
- 9.Yahoo News, “TVA keeps an eye on data center proposals,” n.d. yahoo.com
- 10.Mississippi Free Press, “Mississippi permit board grants xAI’s request for 41 Southaven gas turbines to power Memphis data center,” 2026. mississippifreepress.org
- 11.Southern Environmental Law Center, “Groups appeal air permit for xAI’s personal power plant,” 2026. selc.org
- 12.Mississippi Business Journal, “Compass Datacenters to Invest $10 Billion in Lauderdale County,” 2025. msbusinessjournal.com
- 13.Mississippi Today, “Entergy Mississippi CEO Fisackerly answers questions on data centers and electricity rates,” 2025. mississippitoday.org
- 14.Office of Governor Tate Reeves, “Amazon Web Services Breaks Ground on Largest Economic Development Project in Mississippi History,” 2024. governorreeves.ms.gov
- 15.Mississippi Public Broadcasting, “Amazon announces additional $12 billion for data centers in central Mississippi,” 2026. mpbonline.org
- 16.Mississippi Free Press, “Entergy says Amazon data centers will help Mississippians save on power, some experts fear otherwise,” n.d. mississippifreepress.org
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Related guides
More in Site selection by state
- Data Center Site Selection in Texas: Grids, SB 6, Water and Incentives
- Data Center Site Selection in Virginia: Power, GS-5, Zoning and Tax Rules
- Data Center Site Selection in Georgia: Georgia Power, PSC Rules, Water and Taxes
- Data Center Site Selection in Arizona: APS, SRP, TEP, Water and Heat
- Data Center Site Selection in Ohio: AEP Ohio’s Tariff, PJM Costs and the Tax Pause
- Data Center Site Selection in Illinois: ComEd, Ameren, PJM vs. MISO and the Incentive Pause
- Data Center Site Selection in Nevada: NV Energy, Reno and Las Vegas, Water Rules and GOED Abatements
- Data Center Site Selection in Oregon
- Data Center Site Selection in Iowa
- Data Center Site Selection in North Carolina
- Data Center Site Selection in South Carolina
- Data Center Site Selection in Pennsylvania
- Data Center Site Selection in Indiana
- Data Center Site Selection in Wisconsin
- Data Center Site Selection in Minnesota
- Data Center Site Selection in Nebraska
- Data Center Site Selection in Oklahoma
- Data Center Site Selection in Utah
- Data Center Site Selection in Washington State
- Data Center Site Selection in Alabama
- Data Center Site Selection in Kentucky
- Data Center Site Selection in Missouri
- Data Center Site Selection in Kansas
- Data Center Site Selection in New Mexico
- Data Center Site Selection in Wyoming
- Data Center Site Selection in North Dakota
- Data Center Site Selection in New York: NYISO, Hydropower and the 2026 Permit Pause
- Data Center Site Selection in Michigan: DTE, Consumers, Tax Rules and Water
- Data Center Site Selection in Arkansas: Entergy, SWEPCO, 2025 Laws and Local Rules
- Data Center Site Selection in Colorado: Xcel’s Large-Load Tariff, Water and Local Rules
- Data Center Site Selection in Idaho
- Data Center Site Selection in West Virginia
- Data Center Site Selection in Maryland
- Data Center Site Selection in Montana
- Data Center Site Selection in South Dakota
- Data Center Site Selection in Florida