Data Center Site Selection in Louisiana

Louisiana has become a gas-backed, utility-built data center market: the Public Service Commission approved three Entergy Louisiana gas plants for Meta’s Richland Parish campus in August 2025 and, in December 2025, created a “Lightning” fast-track that lets utilities skip competitive bidding for new generation serving large loads.12 A 2024 law, Act 730, rebates state and local sales tax for certified data centers that commit to at least 50 jobs and $200 million of investment.3 The open questions for a new site are how long the PSC’s fast-track review takes, what share of new plant costs the customer carries, and whether the serving utility can build in time.45

Last reviewed · 8 min read · BlackForge Data Centers

Key takeaways

  • The PSC voted 4-1 on August 20, 2025 to approve three 754 MW gas-fired combustion turbine plants, 2,262 MW in total, plus a 500 kV line and substation for Meta.1
  • The Lightning directive, adopted 4-1 on December 17, 2025, waives competitive bidding for generation serving large loads that sign service agreements of at least 15 years.26
  • Entergy filed in March 2026 for seven more gas plants and about 240 miles of transmission for Meta; the PSC fast-tracked the case, with a final vote expected in late 2026.57
  • Act 730 (2024) rebates sales and use tax on equipment and construction for certified data centers investing $200 million and creating 50 jobs between July 2024 and July 2029.3
  • Northwest Louisiana is a separate market: Amazon’s Caddo and Bossier campuses are served by SWEPCO, with Amazon paying for new grid infrastructure.89

01Where Louisiana’s data center projects are

Louisiana’s data center market changed in December 2024, when Meta announced a $10 billion AI data center on the state-owned Franklin Farm site in Richland Parish, a 2,250-acre megasite about 30 miles northeast of Monroe.10 Meta projected 500 or more direct jobs and a construction workforce of about 5,000 at peak.10 In July 2026, Gov. Jeff Landry announced that Meta would invest $40 billion more to expand the Hyperion campus.11

Other large projects followed. Hut 8 selected Entergy Louisiana to supply an initial 330 MW for an AI data center campus in southeast Louisiana, with total investment of up to $10 billion.12 In northwest Louisiana, Amazon announced $12 billion of data center campuses in Caddo and Bossier parishes in February 2026, and in August 2026 added a third facility at Resilient Tech Park in Shreveport, bringing the total to $18 billion.89

Fig. 1Louisiana’s two main data center power markets

Most of the state

Entergy Louisiana areas

  • Serves Meta in Richland Parish and Hut 8 in the southeast
  • New gas plants approved and proposed for Meta
  • Large requests reviewed by the PSC, often under Lightning

Shreveport and Bossier

SWEPCO area, northwest

  • Serves Amazon’s Caddo and Bossier campuses
  • Amazon pays for new energy infrastructure and upgrades
  • Initial load met with existing generation and contracts
Simplified from public filings and reporting on the largest announced projects; confirm the serving utility for any parcel.18

The pattern is large, utility-built supply for a few very large customers, rather than many mid-sized colocation campuses. For a site screen, the first question is which utility’s service territory the parcel sits in, because that decides who builds the generation and how the PSC reviews it. Our guide to ISOs, RTOs and utility territories explains why that matters.

02Meta Hyperion and the 2025 gas plant approval

The Richland Parish campus is the reference case for how Louisiana powers a hyperscale load. On August 20, 2025, the PSC voted 4-1 to approve a settlement covering three 754 MW gas-fired combustion turbine plants, 2,262 MW in total, along with a new 500 kV transmission line, a new substation and equipment upgrades. Two of the plants are to be built next to the data center.1 Commissioner Davante Lewis cast the only no vote.1

The vote came about two months earlier than originally scheduled, so Meta could move forward.1 Supporters pointed to the size of the investment. Critics, including consumer and environmental groups, argued the process was rushed and raised questions about rates, water use and air pollution; reporting on the approval noted that Meta will cover the plants’ cost for the first 15 years, after which costs could fall to other ratepayers.4

The campus then grew. In March 2026, Entergy asked the PSC to approve seven more gas plants for Meta, which would bring the order to 10 plants and, by Entergy’s count, more than 7 GW of capacity.7 The application is tied to a 20-year contract with Evest, LLC, a Meta subsidiary, and reporting put the deal at about $21 billion.5 The PSC voted 4-1 in April 2026 to fast-track it; the package also includes about 240 miles of new transmission and nuclear uprates, which Entergy says Meta will pay for.13

Fig. 2Gas generation planned for Meta in Louisiana

  • Approved 2025 (3 plants)2,262 MW
  • Total if 2026 request approved7,000+ MW

MW

Capacity approved in August 2025 and the total Entergy described after its 2026 request for seven more plants; the 2026 request was pending as of October 2026.17

For other developers, the takeaway is that Entergy Louisiana can and will build dedicated generation for a large customer, but on a long contract, with substantial customer cost responsibility and a public fight. Our guide to on-site generation and bridge power covers the generation choices.

03The PSC’s Lightning fast-track

On December 17, 2025, the PSC adopted a directive proposed by Commissioner Jean-Paul Coussan, by a 4-1 vote, that lets utilities serving new large-load customers skip the competitive bidding requirement for new generation that the commission set decades ago.2 Reporting refers to it as the Lightning directive or Lightning amendment; it supports Gov. Landry’s Louisiana Lightning Speed Initiative executive order of September 16, 2025.6

Fig. 3A large-load supply case under Lightning

  1. 01

    Service agreement

    Customer signs an agreement of at least 15 years.

  2. 02

    LED letter

    Signed letter from the economic development secretary.

  3. 03

    Utility filing

    Generation and transmission, no competitive bid.

  4. 04

    Hearings record

    Record compiled without an ALJ recommendation.

  5. 05

    PSC vote

    Commission decides on the full application.

Simplified from reporting on the December 2025 directive and the first case filed under it; confirm current PSC rules and procedures before relying on any step.65

To qualify, projects must meet standards that include a signed electric service agreement of at least 15 years and a signed letter from the Louisiana Economic Development secretary.6 In the first major case, Entergy asked the PSC’s Administrative Hearings Division to compile the record without issuing a formal recommendation from an administrative law judge.5 Entergy asked for a final vote on November 18, 2026, while other reporting said a vote was set for December; check the docket for the current schedule.513

The directive is contested. The Union of Concerned Scientists argues it can shift costs to other customers because a gas plant does not fully depreciate over a 15-year contract and nothing in the directive requires utility shareholders to share in the costs.14 Consumer groups also raised the lack of a clear definition of a large-load project and the limited room for stakeholder input.2 In 2026, advocates appealed to state court after the PSC let Meta keep withholding information on investment, jobs and electricity load that an administrative law judge had ordered it to disclose.15 Our guide to large-load tariffs and electric service agreements explains the contract terms that sit underneath these cases.

04Northwest Louisiana and SWEPCO

Amazon’s campuses around Shreveport and Bossier City are served by Southwestern Electric Power Company (SWEPCO), not Entergy, so they follow a different supply path. For Amazon’s campuses, Amazon says it will pay 100% of the costs for new energy infrastructure and grid upgrades needed to serve the data centers, and SWEPCO has said it intends to meet the initial load with existing SWEPCO and AEP-owned generation and power purchase agreements with third parties.8

Water is part of the deal as well. Amazon says it will invest up to $400 million in public water infrastructure, use only verified surplus water, and cool mostly with outside air, using water mainly in peak summer heat.8 For a developer looking at northwest Louisiana, that sets a public expectation: a project that needs municipal water will likely be asked to pay for the system capacity it uses. Our guide to municipal water and sewer capacity covers the questions to ask.

Northwest Louisiana also borders Texas and Arkansas, so a site screen there often compares parcels across state lines. See our Texas guide and the Arkansas guide, and the Mississippi guide for Entergy’s neighboring service area to the east.

05Act 730: the data center sales tax rebate

Louisiana’s main state incentive for data centers is a sales tax rebate created by HB 827 of the 2024 Regular Session, enacted as Act 730.3 It is a rebate, not a point-of-sale exemption: certified data centers recover state and local sales and use taxes they pay.

Act 730 data center rebate at a glance (as of October 2026)
ElementRule
CertificationLouisiana Economic Development certifies approved data center facilities3
JobsSworn attestation of at least 50 new direct, permanent jobs3
InvestmentAt least $200 million of new capital investment, July 1, 2024 to July 1, 20293
CoveredSales and use tax on eligible equipment and on construction, expansion and renovation3
MechanismDirect payment number; rebate paid annually3
2026 changeExecutive order directs a ratepayer and community protection framework for eligibility16

The rules around the rebate are tightening. In July 2026, Gov. Landry issued an executive order directing the economic development secretary to create a ratepayer and community protection framework with mandatory conditions that data center developers must meet to qualify for and keep state tax incentives, reportedly including funding the grid upgrades needed to protect utility customers.16 Confirm current eligibility and any framework conditions with Louisiana Economic Development and a tax advisor. Our sales tax exemptions by state guide compares Louisiana with other states.

06How to screen a Louisiana site

  1. 01Confirm the serving utility (Entergy Louisiana, SWEPCO or another provider) and ask how it would supply the load and over what timeline.18
  2. 02Decide whether the project can sign a service agreement of 15 years or more and obtain an LED letter, which the Lightning path requires.6
  3. 03Ask the utility what share of new generation and transmission costs the contract would assign to the customer, and for how long.414
  4. 04Check access to gas pipelines and high-voltage transmission if new generation would be sited on or near the parcel.1
  5. 05Map water supply and expect to fund public water infrastructure if the project relies on it.8
  6. 06Test Act 730 eligibility against the 50-job and $200 million thresholds and the 2029 investment window.3

Large, flat, dry parcels with nearby transmission and gas are the strongest candidates, but in a state with extensive wetlands and floodplains, buildable acreage should be checked early. Our methodology explains how we screen land, power and water together, and you can get a site reviewed to test a specific Louisiana parcel.

Common questions

Who supplies power to Meta’s Louisiana data center?

Entergy Louisiana. The PSC approved three Entergy gas plants totaling 2,262 MW for the campus in August 2025, and Entergy filed in 2026 for seven more.17

What is the Louisiana PSC Lightning directive?

Adopted in December 2025, it lets utilities serving qualifying large loads skip competitive bidding for new generation.2 Projects need a service agreement of at least 15 years and a letter from the Louisiana Economic Development secretary.6

Does Louisiana have a data center tax incentive?

Yes. Act 730 (2024) rebates state and local sales and use tax for certified data centers that commit to 50 new jobs and $200 million of investment between July 2024 and July 2029.3 A July 2026 executive order directs new eligibility conditions to protect ratepayers.16

Will data centers raise electricity bills in Louisiana?

Utilities and customers say the data center pays for its new infrastructure,13 but critics argue costs can shift to other ratepayers after contracts end.14 The answer depends on each contract’s terms and the PSC’s review.

Where is Amazon building data centers in Louisiana?

In Caddo and Bossier parishes in northwest Louisiana, including a third facility at Resilient Tech Park in Shreveport announced in August 2026; total announced investment is $18 billion.89

Notes

  1. 1.KPLC, “La. regulators approve Entergy power plants for Meta’s AI data center,” 2025. kplctv.com
  2. 2.E&E News, “Louisiana adopts ‘lightning speed’ process to power data centers,” 2025. eenews.net
  3. 3.Louisiana State Legislature, “HB 827, 2024 Regular Session (Act 730),” 2024. legis.la.gov
  4. 4.Straight Arrow News, “Louisiana moves ahead with contentious gas power plants for Meta data center,” 2025. san.com
  5. 5.WWNO, “Entergy wants to fast-track $21B Meta deal as PSC commissioner, advocates sound alarm,” 2026. wwno.org
  6. 6.Louisiana Illuminator, “Louisiana creates fast track to approve power plants for data centers, big electricity users,” 2025. lailluminator.com
  7. 7.The Lens, “Meta triples order of gas-fired power plants for its AI campus in Louisiana,” 2026. thelensnola.org
  8. 8.Louisiana Illuminator, “Amazon says it will limit water use, pay for power at $12 billion NW Louisiana data centers,” 2026. lailluminator.com
  9. 9.Louisiana Illuminator, “Amazon’s data center network in northwest Louisiana is going to get bigger,” 2026. lailluminator.com
  10. 10.Louisiana Illuminator, “Meta plans $10B data center with 500 jobs in NE Louisiana: Details of the deal,” 2024. lailluminator.com
  11. 11.WRKF, “Meta is investing $40B more to expand Richland Parish data center project,” 2026. wrkf.org
  12. 12.T&D World, “Hut 8 Selects Entergy, Southeast Louisiana for $10 Billion Artificial Intelligence Data Center,” n.d. tdworld.com
  13. 13.WAFB, “Public service commission approves Entergy’s new energy investment proposal to power Richland Parish Meta Center,” 2026. wafb.com
  14. 14.Union of Concerned Scientists, “Louisiana’s New Policy Allows Even More Data Center Costs to be Passed to Ratepayers,” 2025. blog.ucs.org
  15. 15.Earthjustice, “Advocates appeal Louisiana PSC’s “arbitrary and capricious” decision to let Meta off the hook for its data center project,” 2026. earthjustice.org
  16. 16.Bloomberg Tax, “Louisiana Governor Issues Order for Data Center Tax Exemption Framework,” 2026. news.bloombergtax.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.