BlackForge Data Centers

Site selection by state

Data Center Site Selection in Georgia: Georgia Power, PSC Rules, Water and Taxes

Georgia, led by metro Atlanta, is now the most active data center construction market in North America, with about 2,882 MW under construction in the first half of 2026.1 Power comes mostly through Georgia Power, whose large-load customers above 100 MW now face longer contracts and minimum bills under a 2025 PSC rule, and whose roughly 9,885 MW expansion was approved in December 2025 to serve that load.23 Local moratoriums,4 a sales tax exemption that lawmakers left intact in 2026 under heavy scrutiny,5 and rising attention to water use6 make county process and cooling design as important as the power date.

Last reviewed · 8 min read · BlackForge Data Centers

Key takeaways

  • Since January 2025, new Georgia Power customers above 100 MW can be held to contracts of up to 15 years with minimum billing, and their contracts go to the PSC for review.27
  • The PSC approved about 9,885 MW of new Georgia Power resources on December 19, 2025, roughly two-thirds of it gas-fired, mainly to serve large loads.38
  • The prospective large-load pipeline grew from about 16,000 MW in 2023 to about 69,000 MW by December 2025, roughly 80% of it data centers.8
  • The sales tax exemption for high-technology data centers runs through 2031; lawmakers left it intact in 2026 despite an estimated $2.5 billion revenue cost for the year.95
  • Coweta approved a large campus in 2026 and then extended a freeze on new applications,1011 and Douglas adopted a 90-day moratorium,4 so check for moratoriums first.
  • Water is a live issue: a proposed Coweta campus could withdraw up to 9 million gallons a day, and Atlanta is weighing closed-loop cooling rules.612

01Why Georgia draws data centers

Atlanta has moved from a secondary market to the front of the construction pipeline. CBRE’s first-half 2026 report put the market’s under-construction capacity at 2,882 MW, up 52.3% from a year earlier, making Atlanta the largest market for total construction in North America for the first time and ahead of Northern Virginia.1 Inventory stood at about 1,803 MW with only 29.5 MW available, and CBRE attributed the growth to tax incentives, labor and rural development opportunities.1

Fig. 1Georgia data center demand, 2025–2026

Atlanta capacity under construction, H1 2026
2,882 MW
Atlanta capacity available, H1 2026
29.5 MW
New Georgia Power resources approved
9,885 MW
Prospective large-load pipeline, Dec. 2025
~69 GW
Atlanta market figures from CBRE’s H1 2026 report; resource and pipeline figures from the PSC’s December 2025 decision.81

Georgia differs from Virginia and Texas in its market structure. It is not in an organized wholesale market, so a vertically integrated utility plans generation and transmission and the elected Public Service Commission sets rates and approves resources. That puts the PSC’s decisions at the center of any power date. Our Southeast guide covers the regional pattern, and regulated utility vs. competitive market sites explains how that structure changes negotiations. For comparison with a PJM state, see Virginia.

02Georgia Power’s large-load rules

Most large Georgia sites are served by Georgia Power, though electric membership cooperatives and municipal systems serve parts of the state, so confirm the utility service territory first. On January 23, 2025, the PSC unanimously approved a rule for Georgia Power’s new customers with loads above 100 MW.2 Those customers can be billed under terms beyond the standard tariff to cover the risks they create for other ratepayers.2

  • Contract terms can run up to 15 years, compared with the 5-year terms that were common before.7
  • Minimum billing requirements apply, so the customer pays for capacity built for it even if it uses less or leaves early.7
  • Beyond site-specific facilities, the customer pays for upstream generation, transmission and distribution costs as its construction progresses.2
  • Every new Georgia Power contract with a customer in the 100 MW category must be filed with the PSC for review.2

For site selection, the rule turns a power request into a long financial commitment early in the project. A developer should size the request to a realistic ramp rather than to the full master plan, and expect the PSC review of the contract to be part of the schedule. Our guides to large-load tariffs and electric service agreements and load ramp schedules cover how to structure those requests.

03The PSC’s December 2025 capacity decision

To meet projected needs from 2027–28 through 2030–31, Georgia Power asked the PSC to certify about 9,885 MW of new resources, about two-thirds of it natural gas-fired units and the rest battery storage, alone or paired with renewables.8 The PSC approved a stipulated agreement for that capacity by a 5–0 vote on December 19, 2025, with most of the new energy intended for large customers such as data centers.3

The decision included a ratepayer condition: in its next base rate case, Georgia Power must allocate enough of the portfolio’s cost to large-load customers that their incremental revenue puts at least $8.50 a month of downward pressure on a typical residential bill of 1,000 kWh for 2029 through 2031.8 PSC staff reported that the prospective large-load pipeline had grown from about 16,000 MW in 2023 to about 69,000 MW in December 2025, with about 80% of it data centers.8

Fig. 2Georgia Power prospective large-load pipeline

  • 2023~16,000 MW
  • December 2025~69,000 MW

MW

Prospective large-load projects reported by PSC staff; about 80% are data centers, and many will not be built.8

A pipeline seven times the size of the approved additions means capacity will be allocated. When you approach the utility, ask which certified resources a project would rely on, when they come online and what happens if the load arrives before them. Our guide on power timelines and interconnection queues discusses how to read those answers.

04Metro Atlanta and the exurbs: Douglas, Coweta and beyond

Large campuses have pushed outward from the city toward counties with big tracts and transmission. Coweta County shows both sides of that move. In April 2026 its commissioners approved the Project Sail rezoning by a 3–2 vote: a nine-building campus of about 4.34 million square feet on 832 acres near Newnan, roughly 45 miles south of Atlanta and near Georgia Power’s Plant Yates, presented as a potential $17 billion investment.10 The Prologis-backed project could need about 900 MW.13 Coweta has also extended a freeze on further data center applications while it weighs competing resident demands.11

Douglas County, west of Atlanta, voted 4–1 for a 90-day moratorium that blocked land use map amendments, rezonings, special use permits, variances and public hearings for data center campuses larger than 50,000 square feet.4 Moratoriums like these are usually temporary, but they can stop a project at the worst time: after land is under option and before entitlements. See data center moratoriums and local restrictions.

Fig. 3Core metro vs. exurban Georgia sites

Inside the perimeter and near-in

Core metro Atlanta

  • Dense fiber and proximity to customers
  • Little available capacity in existing inventory
  • Smaller, costlier parcels
  • City rules on water use under discussion

Douglas, Coweta and similar

Exurban counties

  • Large tracts near transmission and plants
  • Rezonings can pass on narrow votes
  • Moratoriums and freezes are common
  • Water withdrawals face public scrutiny
General patterns, not rules; county process and utility capacity vary site by site.104

In every county, check the comprehensive plan, any pending ordinance changes and the record of recent votes before relying on a zoning path. Our guide to zoning for data centers covers the mechanics.

05The sales tax exemption debate

Georgia offers a sales and use tax exemption for qualifying high-technology data centers, and in 2022 it extended that exemption to 2031.9 In 2024 the General Assembly passed HB 1192, which would have suspended new exemption certificates from July 1, 2024 through June 30, 2026, but Governor Kemp vetoed it on May 7, 2024, citing projects already under way in reliance on the extension.9 The exemption has remained in place since, though under steady pressure.14

The 2026 session tested it again. Lawmakers introduced a wave of bipartisan data center bills, including SB 34, which would bar fuel, generation and transmission costs associated with data centers from general rates.15 By the end of the session in April 2026, the General Assembly had left the tax breaks intact, even after a state report estimated they would cost about $2.5 billion in revenue in 2026, and the ratepayer bill did not pass.5

06Water and cooling

Metro Atlanta draws heavily on the Chattahoochee River system, and data center water use has become part of local approval debates. Reporting on Georgia projects has cited a Google data center in Douglas County that uses about 305 million gallons a year, and Project Sail’s proposed maximum withdrawal of 9 million gallons a day, of which about 6 million would evaporate and about 3 million would return to the river.6 In August 2026, the Atlanta City Council was weighing a rule that would stop data centers on the city’s water system from using drinking water for routine cooling and push them to closed-loop systems through permits issued by the Department of Watershed Management.12

For a Georgia site, settle the water source and cooling approach before the rezoning hearing, because neighbors and commissioners will ask. If a parcel depends on a county or city system, confirm treatment and sewer capacity in writing. Consider closed-loop cooling or reclaimed water where the utility can supply it. Our guides to municipal water and sewer capacity and closed-loop and waterless cooling go deeper.

07How to screen a Georgia site

  1. 01Identify the serving utility. For Georgia Power loads above 100 MW, plan for long contract terms, minimum bills and PSC review.27
  2. 02Ask which certified resources would serve the load and when, given the size of the large-load pipeline.38
  3. 03Check the county for moratoriums, freezes and pending ordinance changes before signing an option.114
  4. 04Define water supply and cooling early, with withdrawal and return volumes ready for public hearings.6
  5. 05Model the sales tax exemption through its 2031 horizon, with a case that assumes it changes.95
  6. 06Confirm fiber routes, transmission access and buildable acreage on the specific tract.

Our methodology describes how we weigh these factors, and you can get a site reviewed before committing to a utility request or a rezoning.

Common questions

What are Georgia Power’s rules for data centers?

Under a rule the PSC approved in January 2025, new Georgia Power customers above 100 MW can face terms beyond the standard tariff, including contracts of up to 15 years and minimum billing.27 They also pay upstream generation, transmission and distribution costs as construction progresses, and their contracts are filed with the PSC.2

Does Georgia have a data center sales tax exemption?

Yes. Qualifying high-technology data centers can receive a sales and use tax exemption that was extended to 2031.9 Lawmakers debated limiting it in 2024 and 2026, and as of the end of the 2026 session it remained intact.95

Is Atlanta a bigger data center market than Northern Virginia?

Not by inventory, but by construction. CBRE reported that Atlanta had about 2,882 MW under construction in the first half of 2026, overtaking Northern Virginia for total construction for the first time.1 Atlanta’s existing inventory was about 1,803 MW.1

Are there data center moratoriums in Georgia?

Yes, at the county level. Douglas County adopted a 90-day moratorium on data center applications for campuses over 50,000 square feet, and Coweta County extended its own freeze.114 Check the current status with the county, because these measures are often extended or replaced by new ordinances.

How much water does a Georgia data center use?

It depends on the cooling design. Reported examples range from about 305 million gallons a year at a Douglas County campus to a proposed maximum of 9 million gallons a day for Project Sail in Coweta County.6 Closed-loop designs use far less, and Atlanta is considering requiring them for data centers on city water.12

Notes

  1. 1.Data Center Frontier, “CBRE: Record Data Center Construction Fails to Ease Capacity Crunch,” 2026. datacenterfrontier.com
  2. 2.Data Center Dynamics, “Georgia PSC approves new billing rules for data centers and large load customers,” 2025. datacenterdynamics.com
  3. 3.WRDW, “State regulators OK Georgia Power plan to serve data centers,” 2025. wrdw.com
  4. 4.FOX 5 Atlanta, “Douglas County imposes 90-day halt on data centers,” n.d. fox5atlanta.com
  5. 5.The Atlanta Journal-Constitution, “Georgia lawmakers leave data center tax breaks intact, punt on energy costs,” 2026. ajc.com
  6. 6.WABE, “Data centers use a lot of water. Georgia counties and conservationists are looking for solutions,” n.d. wabe.org
  7. 7.Atlanta News First, “New Georgia Power rates approved for data centers to address ‘staggering’ energy use,” 2025. atlantanewsfirst.com
  8. 8.Perkins Coie, “Georgia Public Service Commission Approves Georgia Power’s Major Generation Expansion,” 2025. legacy.perkinscoie.com
  9. 9.Data Center Dynamics, “Georgia governor vetoes bill to pause data center tax breaks,” 2024. datacenterdynamics.com
  10. 10.Atlanta News First, “Coweta County commissioners approve rezoning for massive data center,” 2026. atlantanewsfirst.com
  11. 11.The Newnan Times-Herald, “Coweta extends data center freeze amid competing resident demands,” n.d. times-herald.com
  12. 12.Hoodline, “Atlanta weighs forcing data centers off tap water for cooling,” 2026. hoodline.com
  13. 13.Data Center Dynamics, “Prologis’ 900MW Project Sail gets the go-ahead in Coweta County, Georgia,” 2026. datacenterdynamics.com
  14. 14.Altus Group, “Data center tax exemptions in Georgia remain in place – for now,” n.d. altusgroup.com
  15. 15.Georgia Recorder, “Outrage over surge of data centers in Georgia inspires wave of bipartisan bills,” 2026. georgiarecorder.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Related guides

More in Site selection by state