BlackForge Data Centers

Site selection by state

Data Center Site Selection in Oregon

Oregon is one of the most data-center-dense states in the country, with data centers using about 23% of the state’s retail electricity in 2025.1 Since 2025 the rules have tightened: the POWER Act created a separate rate class for loads of 20 MW or more,2 Portland General Electric’s Schedule 96 now requires long-term contracts and minimum demand payments,3 and new data centers lost access to enterprise zone property tax breaks in June 2026.4 Sites still work in Oregon, but power, land supply and incentive eligibility have to be confirmed early and in writing.

Last reviewed · 9 min read · BlackForge Data Centers

Key takeaways

  • Data centers used about 23% of Oregon’s retail electricity in 2025, and the researchers behind that estimate project 31–32% by 2030.1
  • PGE’s Schedule 96 applies above 20 MW, with 10- to 30-year contracts, minimum demand charges at 90% of contracted capacity and customer-paid distribution upgrades.3
  • Schedule 96 customers with 100 MW or more of allocated capacity also pay a 1 cent per kWh surcharge.5
  • New data centers are ineligible for enterprise zone property tax exemptions from June 5, 2026 until 90 days after the 2027 session ends; the Strategic Investment Program is unaffected.4
  • Hillsboro had 475.4 MW of inventory and 0.2% vacancy at the end of 2025, and efforts to add industrial land there stalled in 2026.67

01Oregon at a glance

Oregon’s data center industry grew around three things: hydro-backed power from the Columbia River system, a mild climate that suits air-side economization, and a tax structure with no state sales tax and generous local property tax deals.8 The result is a state where data centers now make up a very large share of electricity demand. A September 2026 report by ECOnorthwest and the University of Virginia found that data centers accounted for about 23% of retail electricity sales statewide in 2025.1

Fig. 1Data centers in Oregon

of Oregon retail electricity, 2025
~23%
projected share by 2030
31–32%
operating data centers
111
under construction or in planning
32
Figures from the ECOnorthwest and University of Virginia report released in September 2026; the 2030 share is a projection.1

That concentration explains the policy response. Between 2025 and 2026 the legislature, the Public Utility Commission and the governor all acted on data center costs, land and incentives. For a site buyer, Oregon is no longer a state where power and tax treatment can be assumed from what earlier projects received. Each of those has to be checked against the current rules, which are summarized below. Our Pacific Northwest regional guide covers how Oregon compares with Washington and Idaho.

02Hillsboro, The Dalles and Prineville

Oregon’s data center activity sits in a few clusters, and each has a different power and land profile.

Fig. 2Oregon’s main data center clusters

Metro

Hillsboro

  • Portland metro, served by PGE
  • 475.4 MW inventory, 0.2% vacancy (end 2025)
  • Land limited by the urban growth boundary
  • Best fit for colocation and latency-sensitive loads

Columbia Gorge

The Dalles

  • Google’s long-running campus
  • Power delivered by Northern Wasco County PUD
  • Access to Columbia River region wind and hydro
  • Hyperscale scale on industrial land

Central Oregon

Prineville

  • Meta and Apple campuses
  • High desert climate suits free cooling
  • Historically used rural enterprise zone deals
  • Grid pockets in Central Oregon are constrained
General characteristics; confirm service territory and capacity for any specific parcel.69

Hillsboro is the metro market. It ended 2025 with 475.4 MW of inventory, a 0.2% vacancy rate and roughly 1 MW of available capacity, according to CBRE.6 PGE has worked to free up capacity there: a 2025 project with GridCARE identified more than 80 MW of incremental capacity for data center load in 2026, part of more than 400 MW the utility expects to energize by 2029.10

The Dalles, in the Columbia Gorge, is home to Google’s campus. Its power is delivered by Northern Wasco County PUD, a consumer-owned utility, which in one example carries more than 100 MW of wind energy from the Leaning Juniper IIB project in Gilliam County to Google under a power purchase agreement.9 Prineville in Central Oregon hosts large campuses for Meta and Apple, built under long-term property tax arrangements with fixed annual payments to the county.11 Morrow and Umatilla counties in eastern Oregon form a further cluster of hyperscale campuses along the Columbia.

03The POWER Act and PGE’s Schedule 96

The Protecting Oregonians With Energy Responsibility (POWER) Act, House Bill 3546, became law in 2025. It directs the Public Utility Commission to create a separate classification and tariff for large energy use facilities of 20 MW or more, including data centers, and requires contracts of at least 10 years with a payment for a base level of energy use regardless of actual consumption.2 The intent is that residential and small business customers do not pay for the infrastructure built to serve these loads.2

The PUC implemented the law for PGE in Order No. 26-154, entered May 7, 2026, in docket UM 2377.3 The resulting tariff, Schedule 96, took effect June 10, 2026, and its main terms are below.3

Main terms of PGE Schedule 96 as approved in 2026
TermWhat it requires
ThresholdCustomers with demand above 20 MW take service on Schedule 96.3
Contract lengthAt least 10 years, scaling with size up to 30 years for the largest loads.3
Minimum demandGeneration and transmission demand charges billed at 90% of contracted capacity, whether used or not.3
Distribution upgradesCustomer pays 100% of the distribution network upgrades needed to serve it.3
Size surcharge1 cent per kWh for customers with 100 MW or more of allocated capacity, funding efficiency and energy burden programs.5

The new rates matter as much as the contract terms. When PGE’s updated rates took effect on July 8, 2026, data centers and other large energy users saw an average increase of about 29%, while other PGE customers saw decreases.12 The commission also directed PacifiCorp to design its own data center rate structure, so terms in Pacific Power territory may differ from PGE’s and were still being developed.5

04Transmission and supply constraints

Much of Oregon’s high-voltage transmission is owned by the Bonneville Power Administration (BPA), which publishes a list of long-term transmission system constraints that it uses when evaluating transmission service requests. That list was last updated in January 2025.13 Industry executives have described data center construction in Washington and Oregon dropping sharply because transmission has not kept pace with large-scale demand.14

Utility-level work can help. PGE’s Hillsboro project used load forecasting and flexibility, including batteries and on-site generation, to validate capacity on existing infrastructure and bring loads online earlier than the original plan.10 Even so, the state-hosted report and regional planners describe new generation and transmission as necessary to meet projected large-load growth.1

For a site, that means three separate questions: which retail utility serves the parcel, whether that utility has distribution and substation capacity in the needed timeframe, and whether the BPA or other transmission path behind it is constrained. A parcel can pass the first two and fail the third. Our guide to power timelines and interconnection queues explains how to read those risks, and flexible loads and demand response covers the flexibility tools PGE has used.

05Tax incentives after the 2026 pause

Oregon has no state sales tax, which has long been a draw for data centers because servers and equipment are bought without it.8 The other major tool was the enterprise zone program, which gives a complete property tax exemption for a set number of years in designated zones.8 Long-term rural enterprise zone deals in places like Prineville replaced most property tax with fixed annual payments.11

House Bill 4084, effective June 5, 2026, made new data centers ineligible for enterprise zone property tax exemptions. The pause lasts until 90 days after the 2027 legislative session adjourns, which could run into fall 2027 or later.4 Data centers already receiving the exemption, and projects already approved for it, keep their benefits. The Strategic Investment Program, a separate property tax incentive, was not affected.4

Supporters said the pause gives Governor Kotek’s Oregon Data Center Advisory Committee time to study data center growth and its effects on the economy, environment and energy supply before the 2027 session.4 Incentive treatment for a new project should therefore be treated as open until that session acts. Our overview of data center tax incentives explains how property and sales tax exemptions usually interact.

06Land supply and state land policy

Oregon’s land use system draws urban growth boundaries around cities, and industrial development outside them is difficult. That is the main land constraint in Hillsboro. In March 2026, Senate Bill 1586, which would have brought 373 acres into Hillsboro’s urban growth boundary and designated about 1,400 acres for future industrial use, was dropped after opposition from farmers, residents and land use advocates, much of it focused on language allowing data centers as an accessory use.7

State-owned land is also off the table for now. The governor directed agencies to pause land transactions for data center projects, including easements, rights-of-way, leases, land use permits and sales of state property, through July 1, 2027.15 A route that crosses state land for a transmission line, water line or access road can be held up by that pause even when the data center parcel itself is private.

Fig. 3Oregon data center policy changes, 2025–2027

  1. 01

    POWER Act (2025)

    New rate class for loads of 20 MW or more.

  2. 02

    Order 26-154

    May 7, 2026: PUC framework for PGE.

  3. 03

    HB 4084

    June 5, 2026: enterprise zone pause for new sites.

  4. 04

    Schedule 96

    Effective June 10, 2026.

  5. 05

    New PGE rates

    July 8, 2026: about 29% higher for large users.

  6. 06

    State land pause

    Runs through July 1, 2027.

Sequence of the main state actions affecting new data center sites.34

07How to screen an Oregon site

  1. 01Identify the retail utility. PGE, PacifiCorp and consumer-owned utilities such as PUDs operate under different rules; check the utility service territory before anything else.
  2. 02In PGE territory, price the Schedule 96 terms: contract length for the planned size, the 90% minimum demand charge and the 1 cent surcharge at 100 MW or more.35
  3. 03In PacifiCorp territory, confirm the status of its data center rate design with the utility and the PUC.5
  4. 04Ask about BPA transmission constraints behind the serving substation, not only local distribution capacity.13
  5. 05Confirm whether the parcel is inside an urban growth boundary and zoned for industrial use.7
  6. 06Check whether any access, utility route or easement crosses state land subject to the pause.15
  7. 07Treat enterprise zone eligibility as unavailable for a new project until the 2027 session acts, and test whether the Strategic Investment Program fits.4

None of these steps replaces a written answer from the utility and county. They do show early whether a parcel is worth that effort. Our due diligence checklist covers the rest of the review, and you can get a site reviewed if you want an outside screen of a specific Oregon parcel.

Common questions

Why are there so many data centers in Oregon?

Oregon combined Columbia River hydropower, a cool climate and a tax structure with no state sales tax and enterprise zone property tax exemptions.8 Those factors drew large campuses to The Dalles, Prineville and eastern Oregon, and colocation to Hillsboro. In 2025 data centers used about 23% of the state’s retail electricity.1

What is the Oregon POWER Act?

The POWER Act, House Bill 3546 of 2025, requires the PUC to create a separate rate class for facilities using 20 MW or more, such as data centers. It requires contracts of at least 10 years and payment for a base level of use regardless of actual consumption.2 PGE’s Schedule 96 is the first tariff to implement it.3

Do data centers still get tax breaks in Oregon?

Existing data centers keep their enterprise zone exemptions, and Oregon still has no sales tax.48 New data centers became ineligible for enterprise zone exemptions on June 5, 2026, until 90 days after the 2027 legislative session ends. The Strategic Investment Program remains available, subject to its own terms.4

Is there land available for data centers in Hillsboro?

Land is tight. Hillsboro is bounded by an urban growth boundary, and a 2026 bill that would have added 373 acres and designated about 1,400 more for future industrial use was dropped.7 Vacancy in existing facilities was 0.2% at the end of 2025.6 Sites inside the boundary still exist but should be checked for zoning and power.

How long does it take to get power for a data center in Oregon?

It depends on the utility and the transmission path. PGE expects to energize more than 400 MW for data centers in Hillsboro by 2029 after its capacity work with GridCARE.10 Across the Northwest, transmission limits have slowed new data center construction, so timing should be confirmed with both the retail utility and BPA.14

Notes

  1. 1.Oregon Public Broadcasting, “Oregon data centers consume a quarter of state power, report,” 2026. opb.org
  2. 2.Data Center Dynamics, “Oregon House passes bill to ensure data centers cover fair share of energy infrastructure costs,” 2025. datacenterdynamics.com
  3. 3.Oregon Public Utility Commission, “Order No. 26-154 (UM 2377),” 2026. apps.puc.state.or.us
  4. 4.Davis Wright Tremaine, “New Oregon Law Impacts Data Center Development Statewide,” 2026. dwt.com
  5. 5.KATU, “Oregon regulators move to make data centers pay more for grid expansion,” 2026. katu.com
  6. 6.CBRE, “Hillsboro data center market sees strong demand in 2025 amid record national growth,” 2026. cbre.com
  7. 7.Oregon Public Broadcasting, “Hillsboro will not get more industrial land for high tech, data centers after all – for now,” 2026. opb.org
  8. 8.Oregon Capital Chronicle, “Oregon would temporarily bar expanded tax benefits for data centers under changes to governor’s bill,” 2026. oregoncapitalchronicle.com
  9. 9.Data Center Dynamics, “Google signs PPA with Avangrid for more than 100MW of wind energy in Oregon,” n.d. datacenterdynamics.com
  10. 10.T&D World, “Portland General Electric and GridCARE Advance Data Center Power Capacity in Oregon,” 2025. tdworld.com
  11. 11.Data Center Dynamics, “Facebook gets tax deal for third Oregon data center,” n.d. datacenterdynamics.com
  12. 12.Office of the Governor of Oregon, “Governor Kotek Applauds PUC for Rate Increase on Data Centers,” 2026. apps.oregon.gov
  13. 13.Bonneville Power Administration, “System constraints,” 2025. bpa.gov
  14. 14.Bisnow, “‘Left Behind’: Power Woes Mute Data Center Growth In Northwest’s Former Boomtowns,” n.d. bisnow.com
  15. 15.Data Center Dynamics, “Oregon pauses land sales of state-owned property for data center projects through July 1, 2027,” 2026. datacenterdynamics.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Related guides

More in Site selection by state