Key takeaways
- Entergy Arkansas joined MISO in December 2014; SWEPCO, OG&E and Empire District are SPP members, and the generation cooperative AECC is in both.1
- The average Arkansas retail electricity price was 9.59 cents per kWh in 2024, ranking 43rd among the states.2
- Act 548 of 2025 cut the investment test for a qualified data center from $500 million to $100 million and added a multi-site large data center tier.47
- Regulators approved Entergy Arkansas’s special rate contract for Google’s West Memphis campus on January 29, 2026.8
- A 2023 law bars outright local bans, yet Pulaski, Madison, Independence and other counties have adopted moratoriums.69
01How Arkansas compares for data center siting
Arkansas offers low-cost power, in-state natural gas and a state government that has moved to attract large loads. The average retail electricity price was 9.59 cents per kWh in 2024, 43rd among the states, and natural gas is the state’s primary source of generation.2 Arkansas produces more gas than it consumes, several interstate pipelines cross it toward Midwest and Northeast markets, and gas-fired plants supplied 39% of in-state net generation in 2023.10
The market is young. After the 2025 energy law overhaul, companies announced five data center projects in the state, and two were under construction by May 2026: Google’s campus in West Memphis and a Serverfarm facility in Clarksville. Google’s planned Little Rock facility was still seeking state and federal wetlands approvals, a reminder that land conditions can set the schedule as much as power.11 For regional context, see our MISO and SPP guides and the neighboring Louisiana, Tennessee and Oklahoma pages.
Fig. 1Arkansas power system at a glance
- net summer generating capacity
- 15,907 MW
- net generation
- 61.5M MWh
- average retail price per kWh
- 9.59¢
- gas share of net generation, 2023
- 39%
02Utilities and the MISO–SPP split
The first screen in Arkansas is which utility service territory a parcel sits in, because that decides the wholesale market, the planning process and the regulator’s view of cost allocation. Entergy Arkansas, which serves a significant portion of the state, became a MISO member in December 2014. Southwestern Electric Power Company (SWEPCO), Oklahoma Gas and Electric and Empire District Electric are members of SPP, and Arkansas Electric Cooperative Corporation, the generation and transmission cooperative for the member co-ops, belongs to both RTOs.1
Fig. 2Arkansas’s two grid footprints
Entergy Arkansas
MISO side
- Entergy Arkansas joined MISO in 2014
- Serves a significant portion of the state
- Large loads served by special rate contracts
- Home of the Google West Memphis campus
SWEPCO, OG&E, Empire
SPP side
- Three investor-owned utility members
- SPP 90-day path for loads with generation
- FERC show-cause order on SPP tariff, 2026
- AECC participates in both RTOs
SPP is working through a surge of large-load requests that has outpaced its ability to study them.12 In January 2026 FERC approved an SPP process that offers an expedited 90-day review to large loads that bring their own generation or pair with existing or planned generation.13 On June 18, 2026, FERC also ordered SPP to justify or revise tariff language, citing the risk that large loads could shift costs among transmission customers, with a response due by August 17, 2026.12 Rates are politically sensitive on both sides: regulators granted SWEPCO a 23% increase for its roughly 126,000 Arkansas customers, and critics tied rising bills to data center growth.14 Our guide to data centers and electricity ratepayers covers that debate.
03The 2025 laws: Act 373 and Act 548
Act 373, the Generating Arkansas Jobs Act
Senate Bill 307, the Generating Arkansas Jobs Act of 2025, was signed on March 20, 2025, as Act 373 with an emergency clause.3 Under it, Entergy Arkansas files annual updates that let it begin recovering construction costs for new generation from ratepayers before the projects are finished. Supporters say that lowers financing costs; critics say it rewards spending, and Entergy’s rate filing proposed raising its allowed return on equity to 9.85% from 8.43%.15 For a site, the practical effect is that utilities have a quicker route to add generation for large new customers, but the cost of that generation is under close public scrutiny.
Act 548 and the data center sales tax exemption
Act 548 of 2025 (House Bill 1444) rewrote the state’s data center sales tax exemption. Its main changes are listed below; sources differ on whether they took effect on July 1 or October 1, 2025, so confirm the current rules with the Department of Finance and Administration and tax counsel.47
| Item | Qualified data center | Qualified large data center |
|---|---|---|
| Investment | $100 million (was $500 million) | $2 billion within 10 years of construction |
| Payroll | $1 million annualized; contractor pay can count | $3 million annualized in the first two years |
| Footprint | Single facility | Two or more nonadjacent sites linked by fiber |
| Administration | Department of Finance and Administration | Department of Finance and Administration |
The act also starts the five-year compliance period when construction begins rather than at occupancy, and extends the exemption to ancillary equipment and services.4 Our sales tax exemptions by state guide compares Arkansas with its neighbors.
04Entergy Arkansas and the Google West Memphis campus
Google’s $4 billion campus in West Memphis, across the Mississippi River from Memphis, is the template for how Entergy Arkansas serves a hyperscale load. It will be accompanied by a 600 MW solar project that Google is developing with Entergy Arkansas.11 The Arkansas Public Service Commission approved Entergy’s special rate contract for Google on January 29, 2026, in Docket 25-055-P, granted a certificate for the associated solar and battery facility on March 3, 2026, in Docket 25-054-U, and approved a Generating Arkansas Jobs Act rider update on June 12, 2026.8
Fig. 3Regulatory path for the West Memphis load
- 01
Special contract
Docket 25-055-P approved Jan. 29, 2026.
- 02
New generation
Solar and battery certificate, Docket 25-054-U, Mar. 3.
- 03
Cost recovery
Jobs Act rider update, Docket 26-008-TF, June 12.
The deal also shows the transparency limits: the public was asked to leave a commission hearing so confidential terms could be discussed. Customers would have paid about $2 a month more for the added capacity, but Entergy says Google agreed to rates that lower costs for other customers.11 Entergy has since proposed a new rate formula and a “Fair Share Plus” initiative meant to ensure data centers pay for the power they use, and says the Google and AVAIO projects will save customers up to $1.7 billion.5 Expect any new large load to be offered a negotiated contract with minimum bills and cost-recovery terms; our large-load tariffs guide explains the usual provisions.
05Local rules, moratoriums and the 2023 state law
Act 851 of 2023 limits local governments’ power to prohibit data centers outright, but it does not stop rules that slow or restrict projects. Cities have used that room: Fayetteville and Little Rock adopted stricter standards, and Fayetteville requires added documentation, compliance with its wastewater pretreatment rules and battery storage instead of generators as the primary backup power source.6 Little Rock’s board approved its industrial zoning changes after residents asked for a moratorium instead.11
Counties have gone further. In May 2026 the Pulaski County Quorum Court approved a yearlong moratorium but narrowly exempted AVAIO Digital’s planned data center near Wrightsville; the county attorney questioned whether the pause was legal under the 2023 law, while supporters argued a time-limited pause is not a ban.9 By August 2026 Madison County had passed a three-year moratorium, joining four other counties with pauses, and only Independence County’s pause was longer. Efforts to amend the 2023 law had not advanced, including in the April 2026 fiscal session.6
- Check county quorum court and city council minutes for any active or proposed moratorium.
- Read the city’s industrial or data center zoning standards for backup power, wastewater and documentation rules.6
- Treat the legal status of time-limited county moratoriums as unsettled and confirm it with Arkansas counsel.9
See our guide to data center moratoriums and local restrictions for how these pauses usually end.
06How to screen an Arkansas site
- 01Identify the serving utility and whether the parcel is on the MISO (Entergy Arkansas) or SPP (SWEPCO, OG&E, Empire) side.1
- 02Ask the utility whether new generation would be needed and how it would be recovered under Act 373.315
- 03On the SPP side, ask whether pairing the load with generation could qualify for SPP’s expedited 90-day review.13
- 04Test the project against Act 548’s $100 million and $2 billion investment tiers and their payroll tests.47
- 05Check for county moratoriums and city zoning rules before signing a land option.6
- 06Screen wetlands early, as Google’s Little Rock site shows.11
Two points deserve early attention. First, Arkansas large-load deals have so far been negotiated contract by contract, so a developer should expect the utility to ask for load evidence, a ramp schedule and financial commitments before it plans new generation, and should expect those terms to be reviewed in a public docket, partly in confidential session.11 Second, county politics can change faster than state law: a site that is open today can be paused by a quorum court vote within weeks, so local outreach belongs at the start of diligence, not after the power study. Our wetlands guide covers the permit track Google’s Little Rock site is working through. If you want an independent read on a specific tract, you can get a site reviewed.
Common questions
Is Arkansas in MISO or SPP?
Both. Entergy Arkansas, which serves much of the state, has been in MISO since December 2014, while SWEPCO, Oklahoma Gas and Electric and Empire District Electric are in SPP. Arkansas Electric Cooperative Corporation participates in both.1
Does Arkansas have a data center sales tax exemption?
Yes. Act 548 of 2025 lowered the investment threshold for a qualified data center to $100 million and created a large data center tier for multi-site projects investing $2 billion or more.47 Payroll and compliance tests apply, so confirm eligibility with tax counsel.
Can Arkansas cities or counties ban data centers?
A 2023 state law, Act 851, bars outright bans but allows rules that restrict or slow projects.6 Several counties have adopted moratoriums of a year or longer, and whether those are lawful has been questioned.96
Notes
- 1.Arkansas Public Service Commission, “Electric,” n.d. apsc.arkansas.gov
- 2.U.S. Energy Information Administration, “Arkansas Electricity Profile,” n.d. eia.gov
- 3.Plural Policy, “SB 307: To Create The Generating Arkansas Jobs Act Of 2025; And To Declare An Emergency,” 2025. open.pluralpolicy.com
- 4.Kutak Rock, “Expansion of the Sales and Use Tax Data Center Exemption,” 2025. kutakrock.com
- 5.Arkansas Business, “Entergy Unveils New Rate Plan Amid Power Demand,” 2026. arkansasbusiness.com
- 6.Louisiana Illuminator (Arkansas Advocate), “More Arkansas communities putting data centers on hold,” 2026. lailluminator.com
- 7.Sales Tax Institute, “Arkansas Expands Sales and Use Tax Exemptions for Data Centers,” 2025. salestaxinstitute.com
- 8.Entergy Corporation, “Regulatory and Other Information,” n.d. investors.entergy.com
- 9.Arkansas Advocate, “Arkansas’ most populous county approves data center moratorium, but with exemption,” 2026. arkansasadvocate.com
- 10.U.S. Energy Information Administration, “Arkansas State Profile and Energy Estimates: Analysis,” n.d. eia.gov
- 11.Arkansas Advocate, “Arkansas Explained: Understanding the data center boom and debate,” 2026. newsfromthestates.com
- 12.Akin Gump, “FERC Directs Southwest Power Pool to Revise Tariff to Expedite Data Center Development,” 2026. akingump.com
- 13.E&E News, “FERC approves central US grid plan for connecting AI data centers,” 2026. eenews.net
- 14.Arkansas Business, “SWEPCO Rate Hike Sparks Debate Over Energy Planning in Arkansas,” 2026. arkansasbusiness.com
- 15.Talk Business & Politics, “Entergy Arkansas rate filing outlines investments, rate hikes and decreases,” 2026. talkbusiness.net
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Neighboring states
Related guides
More in Site selection by state
- Data Center Site Selection in Texas: Grids, SB 6, Water and Incentives
- Data Center Site Selection in Virginia: Power, GS-5, Zoning and Tax Rules
- Data Center Site Selection in Georgia: Georgia Power, PSC Rules, Water and Taxes
- Data Center Site Selection in Arizona: APS, SRP, TEP, Water and Heat
- Data Center Site Selection in Ohio: AEP Ohio’s Tariff, PJM Costs and the Tax Pause
- Data Center Site Selection in Illinois: ComEd, Ameren, PJM vs. MISO and the Incentive Pause
- Data Center Site Selection in Nevada: NV Energy, Reno and Las Vegas, Water Rules and GOED Abatements
- Data Center Site Selection in Oregon
- Data Center Site Selection in Iowa
- Data Center Site Selection in North Carolina
- Data Center Site Selection in South Carolina
- Data Center Site Selection in Pennsylvania
- Data Center Site Selection in Indiana
- Data Center Site Selection in Wisconsin
- Data Center Site Selection in Minnesota
- Data Center Site Selection in Nebraska
- Data Center Site Selection in Oklahoma
- Data Center Site Selection in Utah
- Data Center Site Selection in Washington State
- Data Center Site Selection in Mississippi
- Data Center Site Selection in Alabama
- Data Center Site Selection in Kentucky
- Data Center Site Selection in Missouri
- Data Center Site Selection in Kansas
- Data Center Site Selection in New Mexico
- Data Center Site Selection in Wyoming
- Data Center Site Selection in North Dakota
- Data Center Site Selection in New York: NYISO, Hydropower and the 2026 Permit Pause
- Data Center Site Selection in Michigan: DTE, Consumers, Tax Rules and Water
- Data Center Site Selection in Colorado: Xcel’s Large-Load Tariff, Water and Local Rules
- Data Center Site Selection in Idaho
- Data Center Site Selection in West Virginia
- Data Center Site Selection in Maryland
- Data Center Site Selection in Montana
- Data Center Site Selection in South Dakota
- Data Center Site Selection in Florida
Guide 3 of 39 in Site selection by state · all 242 guides · glossary · calculators
