Data Center Site Selection in Nevada: NV Energy, Reno and Las Vegas, Water Rules and GOED Abatements

Nevada had about 713 MW of operating data center capacity and more than 5,900 MW planned as of early 2026, and NV Energy now expects peak demand to rise nearly 40% in five years.12 New large loads face long-term NV Energy service agreements with minimum payments,3 and Southern Nevada has banned evaporative cooling in new development.4 GOED abatements of up to 20 years remain available,5 but Reno has paused new data center applications through August 2027,6 and a legislative committee has requested a 2027 bill to scale back the breaks.7

Last reviewed · 8 min read · BlackForge Data Centers

Key takeaways

  • NV Energy’s 2026 resource plan proposes about 4,500 MW of new renewables, more than 5,400 MW of storage and 1,200 MW of new gas, driven largely by large customers such as data centers.2
  • NV Energy’s Large Load Electric Service Agreement, for customers typically above 25 MW, requires long-term energy commitments, minimum usage payments and financial security, with PUCN review of each contract.3
  • GOED can abate 75% of personal property tax and cut the sales and use tax rate to 2% for 10 or 20 years, with job, wage and capital thresholds.5
  • Southern Nevada has barred evaporative cooling in new development since 2023, so new data centers there are designed around closed-loop or air cooling.4
  • Reno extended its moratorium on new data center applications through August 31, 2027; Henderson chose development agreements instead of a pause.68
  • NV Energy’s Greenlink transmission program is now estimated at about $4.2 billion, and two of its lines are reported to end at the Tahoe-Reno Industrial Center.910

01Why Nevada, and where the capacity is

Nevada’s data center market has two poles: Las Vegas and Henderson in the south, and Reno, Sparks and the Tahoe-Reno Industrial Center (TRIC) in the north. A January 2026 report from the Desert Research Institute put the state’s operating data center capacity at 713 MW, with more than 5,900 MW planned, and noted that NV Energy’s 2024 resource plan alone covered 12 proposed data centers adding 25,590 GWh of load by 2033.1

Fig. 1Nevada data center load at a glance

Operating data center capacity
713 MW
Planned data center capacity
5,900+ MW
NV Energy projected peak growth in 5 years
~40%
Capacity figures from the Desert Research Institute; peak growth from NV Energy’s 2026 resource plan.12

The draws are well known: a low-tax state, large industrial parks with entitled land, and proximity to California users. The constraints are just as clear. Water is scarce, most power comes from one utility holding company, and both state and local politics have turned more skeptical in 2026. For the wider regional view, see our Mountain West and Desert Southwest guide and compare with Arizona and Utah.

02NV Energy and the terms for large loads

NV Energy serves both Las Vegas and Reno, so its planning and tariffs set the pace almost everywhere a data center would go. Its 2026 Integrated Resource Plan came a year ahead of the normal three-year cycle because of rising projected demand, and it forecasts nearly a 40% increase in peak demand over five years, mainly from large industrial customers including data centers.2 The plan is a proposal reviewed by the Public Utilities Commission of Nevada (PUCN), not an approved build list.2

Fig. 2NV Energy 2026 IRP: proposed new resources

  • Battery storage5,400+ MW
  • Renewables~4,500 MW
  • Natural gas1,200 MW

MW

Approximate nameplate additions proposed in the plan, mostly through power purchase agreements; subject to PUCN review.2

NV Energy also states that many proposed data centers may never be built, and the plan models scenarios from no new data center development to partial and full buildout.11 The gas portion is contested: Vote Solar has intervened over the plan’s reliance on long-lived fossil infrastructure, and the Nevada Conservation League has asked regulators to shield customers from about $6 billion in gas plant costs.12

For an individual project, the key document is the Large Load Electric Service Agreement (LLESA), proposed alongside the IRP. NV Energy describes it as a framework for customers whose needs typically exceed 25 MW and require new generation or transmission: the customer makes long-term energy commitments, pays minimum usage levels and posts financial security, and the PUCN reviews and approves each agreement.3 Ask for the specific term, ramp and security amounts early, because they set how much capital is committed before the first server is installed. Our large-load tariffs guide explains how those terms compare with other utilities, and our ramp schedule guide covers how to size the request.

Clean energy procurement has its own path. In 2025 the PUCN approved NV Energy’s Clean Transition Tariff, which lets a large customer such as Google pay for new clean resources, in that case 115 MW of enhanced geothermal from Fervo, rather than passing the cost to other ratepayers.13 See geothermal power for data centers and 24/7 carbon-free energy.

03Reno, Sparks and the Tahoe-Reno Industrial Center

Northern Nevada’s growth has centered on TRIC in Storey County, east of Sparks, along with sites in Reno and the surrounding valleys. Transmission is the gating item. NV Energy’s Greenlink program, now estimated at about $4.2 billion, will be recovered over more than 70 years and partly offset by wholesale transmission customers; the utility says it is not being built specifically for data centers, though large users may take power through it.9 Data Center Knowledge reported that two Greenlink lines terminate at TRIC and a third runs to Reno to serve load growth in the Truckee Meadows.10

Water at TRIC has been addressed partly with reuse. A 16-mile pipeline was planned to carry about 4,000 acre-feet of treated effluent from the Truckee Meadows Water Reclamation Facility in Sparks to the industrial center, which Switch said would supply its campus there.14 If a site depends on reclaimed water, get the allocation in writing; it is a contract right, not a given.

Jurisdiction matters. In June 2026 the Reno City Council voted 6–1 to extend its pause on new data center applications through August 31, 2027, unless new data center regulations are adopted sooner; existing facilities and those under construction were not affected.6 Sites in Storey County or Washoe County outside Reno city limits fall under different rules, so confirm the governing body before relying on the moratorium’s reach.

04Las Vegas, Henderson and Southern Nevada water limits

Southern Nevada depends heavily on the Colorado River, and its water authority has moved against consumptive cooling. The Southern Nevada Water Authority implemented a ban on evaporative cooling in new development in 2023, so new data centers in its service area are planned around closed-loop cooling or air cooling.4 Facilities built before the rule, such as Google’s Henderson campus, still use evaporative systems.4

That changes the design brief more than the site list. Closed-loop and air-cooled designs usually trade water for higher electricity use, so the cooling choice feeds back into the power request. Our closed-loop and waterless cooling and water stress and drought risk guides cover the trade-off, and WUE is the metric local officials increasingly ask about.

Fig. 3Northern vs. Southern Nevada for data centers

North

Reno and TRIC

  • Greenlink lines terminate at TRIC
  • Reclaimed effluent pipeline to TRIC
  • Reno pause on new applications to Aug. 2027
  • County rules differ outside Reno

South

Las Vegas and Henderson

  • No new evaporative cooling
  • Colorado River supply drives water rules
  • Henderson uses development agreements
  • Clark County drafting regulations
General patterns from the sources cited in this guide; confirm current rules with each jurisdiction.94

Local policy is in motion. In July 2026 Clark County commissioners signaled they would develop data center regulations, though they were not expected to adopt a moratorium.4 Henderson considered a pause and instead chose to require strict development agreements.8

05GOED tax abatements

Nevada’s data center abatements are approved by the Governor’s Office of Economic Development (GOED). A qualifying data center and its co-located tenants can receive a 75% abatement of personal property tax and a reduction of the sales and use tax rate to 2%, for 10 or 20 years; the rate reduction requires a two-thirds vote of the GOED board.5

Thresholds to be met within the first five years, per GOED’s program summary; confirm current terms with GOED.[^5]
TermNevada employeesWagesCapital investment
10 years10 full-timeAt least 100% of statewide averageAt least $25 million
20 years50 full-timeAt least 100% of statewide averageAt least $100 million

Other conditions include a minimum two-year occupancy agreement and Nevada business license for tenants, maintaining the business in Nevada for 10 years, and a paid family and medical leave policy once the company reaches 50 employees.5 The governor’s office has said projects must keep meeting the requirements to stay eligible, with clawback provisions if they fail to comply.15

The program’s future is uncertain. In 2026 the chair of the Legislature’s interim committee on revenue requested a bill for the 2027 session that would repeal parts of the law allowing data center tax abatements and impose a moratorium on new or expanded data centers; it is a bill request, not law.7 Run the project case with and without abatements; our data center tax incentives guide explains how to weigh them.

06How to screen a Nevada site

  1. 01Confirm the utility and ask NV Energy for its current large-load process, LLESA terms and a realistic service date.3
  2. 02Map the site against Greenlink and existing high-voltage corridors, and ask which upgrades the load would trigger.910
  3. 03Choose the cooling approach early. In Southern Nevada, assume no evaporative cooling; in the north, secure water or reclaimed effluent in writing.144
  4. 04Identify the land-use authority (city, county or industrial park) and check for moratoriums or pending code changes.615
  5. 05Model taxes with and without GOED abatements, given the 2027 bill request.57
  6. 06Check whether the land is federal, private or state-managed, since federal parcels add a disposal or lease process.

Our moratorium screening guide and methodology describe how we check these items. If you want a parcel looked at, get a site reviewed.

Common questions

Who provides power to data centers in Nevada?

Mostly NV Energy, which serves both the Las Vegas and Reno areas and is planning large additions of storage, renewables and gas to meet growth driven by data centers.2 New large loads are expected to sign long-term service agreements with minimum bills and credit support.3

Can a data center in Las Vegas use evaporative cooling?

Not for new projects in the Southern Nevada Water Authority’s service area, which has banned evaporative cooling in new development since 2023, so new data centers use closed-loop or air cooling.4 Facilities built before the rule may keep their evaporative systems.4

What tax abatements does Nevada offer data centers?

GOED can approve a 75% personal property tax abatement and a 2% sales and use tax rate for 10 or 20 years, if the project meets employee, wage and capital investment thresholds.5 A bill requested for the 2027 session would scale back these breaks, so confirm status before relying on them.7

Is Reno still approving data centers?

The City of Reno extended a pause on new data center applications through August 31, 2027, unless it adopts regulations sooner; existing and under-construction facilities are not affected.6 Areas outside the city, such as TRIC in Storey County, are governed separately.

Is Greenlink being built for data centers?

NV Energy says Greenlink is not being built specifically for data centers, though large users may receive power through it.9 Two of its lines are reported to terminate at the Tahoe-Reno Industrial Center.10

Notes

  1. 1.Desert Research Institute, “Data Center Water and Electricity Consumption in Nevada,” 2026. dri.edu
  2. 2.NV Energy, “Integrated Resource Plan (IRP) Fact Sheet,” 2026. nvenergy.com
  3. 3.NV Energy, “Large Load Electric Service Agreement (LLESA) Fact Sheet,” 2026. nvenergy.com
  4. 4.The Nevada Independent, “Nevada’s largest county to consider data center regulations, but likely not a moratorium,” 2026. thenevadaindependent.com
  5. 5.Nevada Governor’s Office of Economic Development, “Data Center 2026,” 2025. goed.nv.gov
  6. 6.KOLO-TV, “Moratorium on data centers extended through August of 2027,” 2026. kolotv.com
  7. 7.KTNV Las Vegas, “Nevada lawmakers plan to introduce bill to scale back data center tax breaks,” 2026. ktnv.com
  8. 8.Las Vegas Sun, “Henderson council opts for strict development agreements,” 2026. lasvegassun.com
  9. 9.NV Energy, “Greenlink Fact Sheet,” 2026. nvenergy.com
  10. 10.Data Center Knowledge, “Data Centers to Northern Nevada: No Signs of Slowing,” n.d. datacenterknowledge.com
  11. 11.NV Energy, “Data Centers Fact Sheet,” 2026. nvenergy.com
  12. 12.This Is Reno, “Amid data center push, proposed gas plants in NV under scrutiny,” 2026. thisisreno.com
  13. 13.Latitude Media, “The Clean Transition Tariff won approval in Nevada. What’s next for Fervo?,” 2025. latitudemedia.com
  14. 14.Data Center Frontier, “Switch Will Support Reno Data Center Campus with Reclaimed Water,” n.d. datacenterfrontier.com
  15. 15.Office of the Governor of Nevada, “Governor Lombardo responds to Rep. Titus letter on Boulder City data center,” n.d. gov.nv.gov

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.