BlackForge Data Centers

Site selection by state

Data Center Site Selection in Indiana

Indiana now has some of the most developed large-load rules in the country: Indiana Michigan Power’s 2025 settlement sets minimum terms and bills for data centers,1 NIPSCO serves new megaloads through a separate generation affiliate,2 and a 2025 law requires large-load customers to cover at least 80% of the costs of generation built for them.3 Those rules sit alongside a sales tax exemption that can run up to 50 years for the largest projects,4 and two marquee campuses, Amazon in New Carlisle and Google in Fort Wayne, both in I&M territory.56

Last reviewed · 9 min read · BlackForge Data Centers

Key takeaways

  • Coal still fueled about 42% of Indiana’s net generation in 2024, and wind about 11%, so supply additions for data centers are a live regulatory issue.7
  • I&M’s large-load settlement applies at 70 MW per site or 150 MW in aggregate, with a 12-year minimum term, an 80% minimum monthly billing demand and an exit fee.1
  • NIPSCO’s GenCo affiliate was approved in September 2025, and the IURC approved its Amazon special contract and power purchase agreement on June 17, 2026.28
  • HEA 1007 (2025) created an expedited approval path for generation that serves large loads, with the customer reimbursing at least 80% of the cost.3
  • The state sales tax exemption runs 25 years, or up to 50 years when investment exceeds $750 million; Google’s Fort Wayne award was 35 years on $800 million.46
  • Local approval is the swing factor: Google withdrew a 468-acre Indianapolis rezoning in 2025 ahead of an expected council denial.9

01Indiana at a glance

Indiana sits between the Chicago, Columbus and Louisville markets and has a generation fleet still weighted toward fossil fuels. Coal fueled 42% of the state’s net generation in 2024, wind supplied 11%, and solar, hydropower and biomass together supplied about 4%.7 Indiana was also the nation’s second-largest coal consumer after Texas.7 That mix matters for site selection because much of the new supply that data centers need will be new gas, storage and renewables, and the state has written rules about who pays for it.

Fig. 1Indiana power and data center demand

of Indiana net generation from coal, 2024
42%
of Indiana net generation from wind, 2024
11%
I&M Indiana peak expected by 2030
7,000+ MW
NIPSCO deliveries to Amazon by end of 2032
2.4 GW
Generation shares from EIA;7 the I&M load forecast as reported at the settlement approval;1 the NIPSCO delivery schedule from Utility Dive.10

Four investor-owned utilities matter most for large campuses: NIPSCO in the north, Indiana Michigan Power (I&M) in the South Bend and Fort Wayne areas, AES Indiana in Indianapolis, and Duke Energy Indiana across much of the rest of the state. Municipal utilities and rural cooperatives serve other pockets, so start by confirming the parcel’s utility service territory. I&M is in PJM, while NIPSCO, AES Indiana and Duke Energy Indiana are in MISO, which affects capacity costs and transmission planning; see our PJM guide and MISO guide.

02I&M’s large-load settlement

I&M’s settlement is the template most people mean when they talk about Indiana’s data center rules. It was filed in November 2024 by I&M, the Indiana Office of Utility Consumer Counselor, Amazon, Google, Microsoft, the Data Center Coalition and the Citizens Action Coalition.11 The Indiana Utility Regulatory Commission (IURC) approved it in Cause No. 46097 in February 2025 with one modification.1 I&M expects its Indiana peak load to exceed 7,000 MW by 2030, up from about 2,800 MW.1

Main terms of I&M’s large-load settlement, as approved in 2025[^1]
TermWhat it requires
Who it coversNew or expanded load of at least 70 MW at one site, or 150 MW in aggregate.
Contract lengthA minimum term of 12 years.
Minimum billAt least 80% of contracted demand billed each month.
Credit supportIncreased collateral requirements.
Exit feeEqual to the minimum charges, capped at five years.
IURC modificationMutually agreed cuts of more than 20% of contracted capacity need IURC review and approval.

The settlement does not set a cost allocation method for large loads; those questions were deferred to later proceedings such as a rate case or tracker filing.1 It also contemplated a Clean Transition Tariff filing and a discussion of demand response for large customers.1 For a developer, the practical effect is that an I&M site needs a credit-worthy end user willing to commit to a long, take-or-pay style contract, not just a land position. Our guide to large-load tariffs compares these terms with other states, and minimum bills and load factor are worth modeling before signing.

03NIPSCO and the GenCo model

NIPSCO took a different route. Rather than adding data center supply to the regulated utility’s rate base, its parent NiSource created NIPSCO Generation (GenCo), an affiliate that builds generation and sells it to NIPSCO under contracts tied to specific large customers. The IURC approved the strategy in September 2025, and NiSource describes it as a way to shield existing retail customers from the costs of serving new data centers.2 GenCo’s first deal is with Amazon, to serve its planned data centers in northern Indiana: up to 3 GW of gas-fired generation and battery storage, with NIPSCO building transmission, at a combined expected cost of about $7 billion.10 The contract calls for NIPSCO to begin supplying Amazon by January 1, 2027, rising to as much as 2.4 GW by the end of 2032.10

On June 17, 2026, the IURC fully approved the settlement, the Amazon special contract and the related power purchase agreement, and a separate order approved the combined-cycle gas and battery resources.8 NIPSCO estimates the 15-year Amazon contract will save other customers about $1 billion, credited on their bills; those are utility estimates, not audited results.8

Fig. 2Three Indiana approaches to large loads

PJM

I&M tariff terms

  • Applies at 70 MW per site or 150 MW total
  • 12-year minimum term
  • 80% minimum monthly demand
  • Exit fee and added collateral

MISO

NIPSCO GenCo

  • Affiliate builds new generation
  • Special contract per megaload
  • PPAs need IURC approval
  • Amazon deal approved June 2026

MISO

AES Indiana

  • Resources planned in the IRP
  • Second tranche only after a contract
  • Up to 700 MW gas, 820 MW storage
  • No signed hyperscale deal cited
Simplified from the approved settlement, NiSource’s filings and AES Indiana’s 2025 IRP; confirm current terms with each utility.112

04Duke Energy Indiana, AES Indiana and HEA 1007

Outside I&M and NIPSCO territory, the rules are less settled. AES Indiana’s 2025 integrated resource plan splits new supply into two sets: one added regardless of data center demand, and a second, of up to 700 MW of natural gas and up to 820 MW of battery storage, added only after a large-load customer signs a contract.12 The filing says early analysis shows no negative rate impact on existing customers from serving data centers.12 Duke Energy reported 7.8 GW of signed electric service agreements with data centers company-wide on its second-quarter 2026 call, and said most of its late-stage large-load pipeline is in Florida and Indiana.13 We did not find an Indiana-specific large-load tariff order for Duke as of October 2026, so ask Duke directly what contract terms it is offering.

State law now frames all of these negotiations. House Enrolled Act 1007 (2025) created an expedited approval process for generation built to serve large-load customers such as data centers, along with cost recovery mechanisms, and requires “significant and meaningful financial assurances” from the customer, including reimbursing at least 80% of costs.3 Regulators have also signaled impatience: in March 2026 IURC Chairman Andy Zay told reporters the industry needs to do more and that Hoosiers have lost trust in it.14 Expect detailed questions about who pays, and plan for contribution in aid of construction on dedicated substations and lines.

05New Carlisle, Fort Wayne and Indianapolis

Indiana’s two flagship campuses are both in I&M territory. In April 2024 Amazon Web Services announced an $11 billion data center campus near New Carlisle, west of South Bend, with at least 1,000 jobs.5 Local incentives later approved included a 10-year, 50% real property tax abatement on three parcels totaling 870 acres, for a plan of 16 data center shells of about 200,000 square feet each.15 The site is inside the Indiana Enterprise Center, a large master-planned industrial area in St. Joseph County.15

In Fort Wayne, Google announced a $2 billion data center in April 2024, with up to 200 jobs, and said it would work with I&M to bring clean energy resources to the local grid.6 The IEDC committed a 35-year sales tax exemption on a minimum of $800 million of eligible capital, with five more years for each additional $800 million, up to 50 years.6

Indianapolis shows the other side. Google withdrew its rezoning request for a 468-acre data center in Franklin Township on September 22, 2025, ahead of a City-County Council vote it was expected to lose, even though the Metropolitan Development Commission had voted 8-1 in favor.9 Residents raised water and power use, flooding, noise, tax breaks and nondisclosure agreements.9 Our guides on moratoriums and local restrictions and confidentiality and project code names cover how to manage those risks.

06The sales tax exemption and 2026 changes

Indiana exempted qualified data centers from its 7% sales tax in 2019.16 The IEDC administers the program, which covers qualifying data center equipment and energy purchases.4 The base award runs 25 years, and the IEDC may extend it up to 50 years when investment exceeds $750 million.4 Minimum investment thresholds vary by county population and must be met within a set period after the exemption certificate is issued; confirm the threshold for your county with the IEDC.4

Fig. 3Indiana sales tax exemption terms

  • Base exemption term25
  • Google Fort Wayne ($800M)35
  • Maximum (over $750M)50

years

Program limits from the IEDC,4 and the Google Fort Wayne award as announced in 2024.6 Terms for any project are negotiated.

The 2026 session tried to give local governments a share. As passed by the House, HB 1333 would have charged data centers a 1% sales tax directed to the approving local government; the final language cut that to an optional payment of not more than one cent per dollar of the exempted tax, applying only to data centers that gain local approval after June 30, 2026 and excluding those that already hold an exemption certificate.16 The Indiana Capital Chronicle estimated that a large data center could have owed at least $5 million a year under the Senate version but no more than $350,000 under the final deal.16 Property tax abatements remain local and separate; see our guides to property taxes and sales tax exemptions by state.

07How to screen an Indiana site

  1. 01Identify the serving utility and its market: I&M (PJM) or NIPSCO, AES Indiana or Duke Energy Indiana (MISO), or a municipal or cooperative utility.
  2. 02In I&M territory, model the 12-year term, 80% minimum bill, collateral and exit fee against the tenant’s credit.1
  3. 03In NIPSCO territory, ask whether service would run through GenCo and a special contract, and how long IURC approval took for Amazon.28
  4. 04In AES Indiana or Duke territory, ask what new generation the utility would need and how HEA 1007’s 80% cost commitment would apply.123
  5. 05Confirm the county’s sales tax exemption threshold with the IEDC and whether a local payment under the 2026 law could apply.416
  6. 06Test local politics early: water, noise, flooding and nondisclosure agreements drove the Franklin Township withdrawal.9

Indiana is a strong state for power-hungry campuses when the utility path is clear, and a slow one when it is not. If you want an independent read on a specific parcel’s power, water, zoning and buildable acreage, you can get a site reviewed, or start with our site screening tools. Neighboring options are covered in our Ohio, Illinois, Michigan and Kentucky guides.

Common questions

Which utility serves data centers in Indiana?

It depends on the parcel. NIPSCO serves northern Indiana, Indiana Michigan Power serves the South Bend and Fort Wayne areas, AES Indiana serves Indianapolis and Duke Energy Indiana serves much of the rest, with municipal utilities and cooperatives in between. Each has a different large-load approach, from I&M’s settlement terms to NIPSCO’s GenCo contracts.12

What is the I&M large-load tariff settlement?

It is a 2025 IURC-approved agreement that sets terms for new I&M loads of at least 70 MW at one site or 150 MW in aggregate. Customers sign at least 12-year contracts, pay at least 80% of contracted demand each month, post more collateral and owe an exit fee capped at five years of minimum charges.1

Does Indiana have a data center sales tax exemption?

Yes. Qualified data centers can be exempt from Indiana’s 7% sales tax on qualifying equipment and energy for 25 years, or up to 50 years for investments over $750 million.416 A 2026 change lets approving local governments seek a capped payment from data centers approved after June 30, 2026.16

Do Indiana data centers pay for new power plants?

Increasingly, yes. HEA 1007 (2025) requires large-load customers to reimburse at least 80% of the costs of generation built for them under its expedited process,3 and NIPSCO’s GenCo structure assigns new generation to specific megaload contracts such as Amazon’s.10

Why did Google withdraw its Indianapolis data center rezoning?

Google withdrew the Franklin Township rezoning in September 2025 before a City-County Council vote it was expected to lose. It did not give a reason, but residents and the district councilor had cited water and power use, flooding, noise, tax breaks and a nondisclosure agreement.9

Notes

  1. 1.Renewable Energy World, “Midwest utility gets regulatory approval for large load tariff settlement,” 2025. renewableenergyworld.com
  2. 2.NiSource, “NiSource Achieves IURC Regulatory Approval for GenCo Strategy,” 2025. nisource.com
  3. 3.Indiana Capital Chronicle, “Bill to boost energy generation and nuclear manufacturing advances to Indiana governor,” 2025. indianacapitalchronicle.com
  4. 4.Indiana Economic Development Corporation, “Data Center Sales Tax Exemption,” n.d. iedc.in.gov
  5. 5.Indianapolis Business Journal, “Amazon Web Services to build $11 billion data center campus near South Bend,” 2024. ibj.com
  6. 6.Indiana Economic Development Corporation, “Gov. Holcomb Announces Google Is Building a $2B Data Center in Northeast Indiana,” 2024. iedc.in.gov
  7. 7.U.S. Energy Information Administration, “Indiana Profile Overview,” n.d. eia.gov
  8. 8.NiSource (Business Wire), “Regulatory Approvals Underscore Strength of NiSource’s Customer Focused Data Center Strategy Supporting Growth in Indiana,” 2026. businesswire.com
  9. 9.Data Center Dynamics, “Google withdraws rezoning proposal for 468-acre data center project in Franklin Township, Indianapolis,” 2025. datacenterdynamics.com
  10. 10.Utility Dive, “NIPSCO to supply 3 GW to Amazon data centers in northern Indiana,” 2025. utilitydive.com
  11. 11.American Electric Power, “I&M and Stakeholders File Large Load Settlement to Advance Grid Reliability and Support Economic Growth,” 2024. aep.com
  12. 12.AES Indiana (Indianapolis Power & Light), filed with the Indiana Utility Regulatory Commission, “IPL 2025 IRP Vol I,” 2025. in.gov
  13. 13.Nasdaq, “Duke Energy Q2 Earnings Call Highlights,” 2026. nasdaq.com
  14. 14.Axios Indianapolis, “Indiana regulators question energy companies on costs and data centers,” 2026. axios.com
  15. 15.Inside Indiana Business, “Incentives approved for $11 billion Amazon data center project,” 2024. insideindianabusiness.com
  16. 16.Indiana Capital Chronicle, “That 1% incentive to encourage data center approvals? Final deal watered it down,” 2026. indianacapitalchronicle.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Related guides

More in Site selection by state