BlackForge Data Centers

Site selection by state

Data Center Site Selection in Pennsylvania

Pennsylvania generates far more electricity than it uses, from gas and nuclear plants, and sent more power to neighboring states in 2020 than any other state.1 In May 2026 the Public Utility Commission adopted a nonbinding model tariff for loads above 50 MW,2 PPL reported a 31.8 GW data center pipeline in advanced planning,3 and the state’s marquee projects sit beside the Susquehanna nuclear plant and on former industrial sites such as Homer City.45

Last reviewed · 9 min read · BlackForge Data Centers

Key takeaways

  • Gas supplied about 52% and nuclear 33% of Pennsylvania’s generation in 2020, and the state delivered nearly 78 million MWh to its neighbors.1
  • The PUC’s May 2026 model tariff covers customers above 50 MW individually or 100 MW in aggregate and assigns “but for” upgrade costs to them; utility-specific tariffs come later.2
  • PPL’s approved rate settlement created a large-load class with service commitments of at least 10 years and minimum usage requirements.6
  • After FERC rejected an expanded behind-the-meter deal at Susquehanna, Talen and Amazon restructured it as a 1,920 MW front-of-the-meter contract running through 2042.74
  • Certified data centers can buy computer equipment free of sales and use tax if they meet investment, job and payroll tests within four years.89

01Pennsylvania at a glance

Pennsylvania is one of the country’s largest power producers. It generated more than 230 million MWh in 2020, behind only Texas and Florida, and delivered nearly 78 million MWh to neighboring states, more than any other state.1 Natural gas overtook nuclear as the leading source in 2019 and supplied about 52% of generation in 2020, up from 15% in 2010.1 Nuclear supplied 33%, the second-highest nuclear output of any state after Illinois.1

Fig. 1Pennsylvania electricity generation by source, 2020

  • Natural gas52
  • Nuclear33
  • Coal10
  • Renewables4

percent of generation

Gas and nuclear produced 85% of in-state generation in 2020; coal had fallen to 10%.1

Fuel is close at hand. Pennsylvania is the second-largest natural gas producer after Texas, with 7.5 trillion cubic feet in 2022, and it has 49 underground gas storage sites, more than any other state.10 That combination of surplus generation, in-state gas and an established transmission network is why developers look at Pennsylvania for both grid-served campuses and on-site generation.

The whole state is in PJM, so wholesale capacity costs and PJM’s interconnection rules apply everywhere. Our PJM regional guide covers the market; this guide covers what is specific to Pennsylvania.

02Utilities and the PUC’s large-load model tariff

Pennsylvania’s grid is delivered by electric distribution companies (EDCs), chiefly PPL Electric in the east and northeast, PECO around Philadelphia, FirstEnergy’s operating companies across much of the center and west, and Duquesne Light in Pittsburgh. Customers can buy energy from a licensed retail supplier while the EDC delivers it, a structure the Susquehanna deal relies on.4 For a site screen, the EDC determines the interconnection process, the upgrade costs and, increasingly, the large-load contract terms.

On May 13, 2026, the Public Utility Commission issued a final order establishing a model tariff framework for large-load customers, following an April 30 vote.2 Its main elements:

  • It applies to customers above 50 MW individually or 100 MW in aggregate, with no reduction for behind-the-meter generation.2
  • Large-load customers should bear the cost of upgrades that would not have been needed “but for” their request.2
  • Customers that terminate before the utility recovers its investment would pay exit fees, and large loads would contribute to universal service programs.2
  • Existing large-load customers are grandfathered under current terms but may opt in.2

The model is nonbinding. Each EDC must file its own tariff, and the commission will decide key terms case by case in each utility’s docket.2 PPL already has terms in place: the commission voted 5–0 to approve a PPL rate settlement that creates a large-load class with service commitments of at least 10 years and minimum usage requirements, plus a non-bypassable charge expected to direct $11 million a year to low-income assistance starting in 2027.6 Check whether PECO, FirstEnergy and Duquesne have filed. Our guide to large-load tariffs explains how minimum bills and exit fees work.

03PPL territory and the size of the pipeline

PPL Electric’s service area in eastern and central Pennsylvania has become one of the busiest large-load territories in PJM. PPL reported 31.8 GW of data center projects in advanced stages of planning in the second quarter of 2026, with more than 11 GW under signed electric service agreements and more than 6.5 GW under construction.3

Fig. 2PPL Electric data center pipeline, Q2 2026

In advanced stages of planning
31.8 GW
Under signed electric service agreements
11+ GW
Under construction
6.5+ GW
As reported by PPL; advanced-stage projects are not all certain to be built.3

A pipeline that large changes the question for a new request. The issue is less whether PPL wants the load than where it would fall in the study sequence and what transmission upgrades it would trigger under the “but for” principle.2 Ask for the study queue position in writing, and see our guides to the large-load interconnection process and transmission upgrade cost allocation.

04Nuclear colocation and the Susquehanna deal

The Talen–Amazon arrangement at the Susquehanna nuclear plant in Luzerne County is one of the most closely watched tests of colocating a data center with a power plant. In November 2024 FERC, by a 2–1 vote, rejected an amended interconnection service agreement that would have raised the co-located load served behind the meter from 300 MW to 480 MW, finding PJM had not justified its nonstandard terms.7 FERC denied rehearing on April 10, 2025, and Susquehanna appealed to the Fifth Circuit.11

On June 11, 2025, Talen announced a restructured deal. The co-located behind-the-meter model became a grid-connected, front-of-the-meter retail arrangement: Talen acts as Amazon’s licensed retail supplier, PPL delivers the power, and the output of the two-unit, 2.5 GW plant flows into PJM.4 The contract covers 1,920 MW through 2042, worth about $18 billion at full quantity.4

The rules have since moved. On December 18, 2025, FERC found PJM’s tariff unjust and unreasonable because it lacked clear rates, terms and conditions for co-located load, and directed PJM to offer new transmission services priced on a co-located load’s net withdrawals from the grid, with compliance filings due in early 2026.12 How PJM implements that order will decide whether future Pennsylvania colocation deals can avoid full network service.

Fig. 3Talen–Amazon delivery ramp at Susquehanna

  • By 2029840–1,200 MW
  • By 20321,680–1,920 MW
05001,0001,5002,000MW
Contracted delivery ranges depend on Amazon’s development pace; the contract runs through 2042.4

The lesson for site selection is that proximity to a nuclear plant does not by itself mean cheaper or faster power. Moving from behind the meter to front of the meter put the load back on the grid, with delivery charges and the utility’s upgrades. Our guides to behind-the-meter versus front-of-the-meter service and nuclear siting cover the trade-offs.

05Former coal and industrial sites

Pennsylvania’s industrial history has left large sites with transmission, water and heavy-industrial zoning already in place. The Homer City project in Indiana County is the largest example: a former coal plant site of more than 3,200 acres planned around a roughly 4.5 GW gas-fired plant.5 The developers kept the legacy plant’s transmission links to PJM and NYISO, its substations and its water access, and ordered seven GE Vernova 7HA.02 turbines, with Kiewit as the construction contractor.13

Even with that head start, the schedule moved. The 2025 announcement targeted power by 2027,13 while a March 2026 update put first generation in early 2028 and completion by 2029, with about 3,700 MW earmarked for data centers and 700–800 MW for the grid.14 Vertical construction began with a “first steel” milestone in April 2026.5

Amazon’s Pennsylvania plan uses both models. In June 2025 Governor Josh Shapiro announced at least $20 billion of Amazon investment, starting with a campus at the Keystone Trade Center in Falls Township, Bucks County, once the site of one of the world’s largest steel mills, and one beside the Susquehanna plant in Salem Township.15 Our guides to repurposing industrial and power plant sites and brownfield liability protections cover what to check on land like this.

06PJM capacity costs in a Pennsylvania pro forma

Every Pennsylvania load pays for PJM capacity, and that price has now hit its cap in three straight auctions. The 2028/2029 Base Residual Auction, announced July 14, 2026, cleared at the $325 per MW-day cap; PJM estimated the price would have been $554.72 without the cap and floor, which were extended to cover four auctions through 2029/2030.16 Cleared capacity fell 6,831 MW short of the reliability requirement.16

Two site-level consequences follow. Capacity cost is a large, volatile line in the power budget that a buyer should model for several delivery years, and the shortfall strengthens the case for flexible operation or on-site generation that can reduce peak demand. Our guide to PJM capacity prices covers the auction mechanics and the price collar.

07The computer data center equipment exemption

Act 25 of 2021 created Pennsylvania’s sales tax exemption program for data centers. Since January 1, 2022, computer data center equipment sold to or used in a certified data center by an owner, operator or qualified tenant holding a Department of Revenue certificate is exempt from sales and use tax.8 It replaced an earlier refund model.8

Pennsylvania computer data center exemption, per Department of Revenue guidelines
TermRequirement
Smaller counties (250,000 or fewer residents)At least $75 million of new investment and 25 new jobs by the fourth anniversary of certification.9
Larger counties (over 250,000 residents)At least $100 million of new investment and 45 new jobs by the fourth anniversary.9
PayrollAt least $1 million of annual compensation at the site in each year of certification.9
Term25 full calendar years after the year of application.9

The county population split matters in site comparisons, because a rural county lowers both the investment and job thresholds.9 Confirm eligibility with a tax advisor, and compare terms with other states in our guide to sales tax exemptions by state.

08How to screen a Pennsylvania site

  1. 01Identify the EDC and whether it has filed a large-load tariff under the PUC’s model framework.2
  2. 02In PPL territory, ask where the request sits in a 31.8 GW advanced-stage pipeline.3
  3. 03Model minimum usage, contract term and exit fees against a realistic ramp schedule.6
  4. 04For colocation, check where PJM’s compliance with FERC’s December 2025 co-location order stands before assuming anything other than front-of-the-meter delivery.124
  5. 05For former plant sites, verify which transmission, substation and water rights actually transfer.13
  6. 06Model PJM capacity costs at or near the $325 per MW-day cap, and test what happens after the collar ends.16
  7. 07Check the county population tier for the equipment exemption.9

Written answers from the EDC, the county and tax counsel remain the real test, but these steps show quickly whether a parcel deserves that work. Our due diligence checklist covers the rest, our Ohio guide covers a neighboring PJM state, and you can get a site reviewed if you want an outside screen of a Pennsylvania parcel.

Common questions

Does Pennsylvania have a large-load tariff for data centers?

The PUC adopted a nonbinding model tariff in May 2026 for customers above 50 MW individually or 100 MW in aggregate, and each utility must file its own version.2 PPL’s approved settlement already created a large-load class with commitments of at least 10 years and minimum usage requirements.6

Does Pennsylvania give data centers a sales tax exemption?

Yes. Certified data centers can buy computer data center equipment free of sales and use tax.8 They must reach $75 million and 25 jobs in counties of 250,000 or fewer residents, or $100 million and 45 jobs in larger counties, within four years, and pay at least $1 million a year in payroll.9

What happened with the Amazon data center at the Susquehanna nuclear plant?

FERC rejected an expanded behind-the-meter arrangement in November 2024 and denied rehearing in April 2025.711 Talen and Amazon then signed a 1,920 MW front-of-the-meter contract running through 2042, with PPL delivering the power.4

Can old coal plant sites in Pennsylvania become data centers?

Yes, and Homer City is the largest example, reusing a former coal plant’s transmission links, substations and water access for a gas-powered campus.13 Its first generation slipped from 2027 to early 2028, a reminder that reuse shortens but does not remove the development timeline.1314

Why do PJM capacity prices matter for a Pennsylvania site?

Pennsylvania is entirely in PJM, and the 2028/2029 auction cleared at the $325 per MW-day cap, the third straight auction to clear at the cap, while still falling short of the reliability requirement.16 That cost belongs in any power budget for a Pennsylvania campus, along with a view on prices once the collar expires.

Notes

  1. 1.U.S. Energy Information Administration, “Today in Energy: Pennsylvania electricity generation and interstate deliveries, 2020,” 2022. eia.gov
  2. 2.Pennsylvania Public Utility Commission, “PUC Releases Final Order Establishing First-of-Its-Kind Large Load Model Tariff Framework,” 2026. puc.pa.gov
  3. 3.PPL Corporation, “PPL Corporation Delivers Solid Second-Quarter 2026 Earnings; Reaffirms Guidance and Long-Term Growth Outlook,” 2026. finviz.com
  4. 4.POWER Magazine, “Talen, Amazon Launch $18B Nuclear PPA: A Grid-Connected IPP Model for the Data Center Era,” 2025. powermag.com
  5. 5.FracTracker Alliance, “Homer City AI campus and gas power construction,” 2026. fractracker.org
  6. 6.Pennsylvania Public Utility Commission, “PUC Issues Decision in PPL Electric Rate Proceeding,” 2026. puc.pa.gov
  7. 7.Data Center Dynamics, “FERC blocks plan for Susquehanna nuclear plant interconnection to Amazon data center,” 2024. datacenterdynamics.com
  8. 8.Pennsylvania Department of Revenue, “Computer Data Center Equipment Program,” n.d. pa.gov
  9. 9.Pennsylvania Department of Revenue, “Computer Data Center Equipment Exemption Program Guidelines,” n.d. revenue.pa.gov
  10. 10.U.S. Energy Information Administration, “Pennsylvania Profile Overview,” 2023. eia.doe.gov
  11. 11.American Nuclear Society, “FERC denies Talen-Amazon agreement, again,” 2025. ans.org
  12. 12.Beveridge & Diamond, “FERC Orders PJM to Create Clear Rules for Co-Located Data Centers and Large Loads,” 2025. bdlaw.com
  13. 13.American Public Power Association, “Companies unveil largest natural gas-powered data center campus in U.S.,” 2025. publicpower.org
  14. 14.Axios Pittsburgh, “Homer City power plant, the grid and data centers,” 2026. axios.com
  15. 15.WHYY, “Gov. Shapiro announces $20B Amazon AI investment, including development of data center in Bucks County,” 2025. whyy.org
  16. 16.PJM Interconnection, “PJM Capacity Auction Procures 138,318 MW of Generation Resources,” 2026. pjm.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Related guides

More in Site selection by state