Key takeaways
- Wind generated 59% of Iowa’s electricity in 2023, the highest share of any state, and Iowa ranks among the 10 states with the lowest average electricity price.1
- MidAmerican says it has invested nearly $16 billion in wind since 2004 and supplies its Iowa customers with more than 90% renewable energy on an annual basis.6
- Large loads are typically served under negotiated individual customer rates; the Iowa Utilities Commission had approved them for two Cedar Rapids data centers by late 2025.7
- The sales and use tax exemption requires at least $200 million of investment, and every data center business had to register with the Department of Revenue by January 31, 2026.45
- For data centers that begin operating on or after January 1, 2026, the electricity and backup fuel exemptions expire after 10 or 15 years, depending on location.5
- A 2026 bill to require data center tariffs and water and energy reporting failed to clear the second funnel, but the issues it raised remain live.89
01Iowa at a glance
Iowa’s case for data centers rests on power. Wind turbines generated 59% of the state’s electricity in 2023, the highest wind share of any state.1 Iowa is also among the 10 states with the highest electricity sales per capita and among the 10 with the lowest average electricity price.1 Hyperscale operators followed. Google in Council Bluffs, Meta in Altoona and Microsoft in West Des Moines built some of the largest campuses in the Midwest,1011 and Alliant Energy now serves new Google and QTS campuses in Cedar Rapids.12
Fig. 1Power and incentives in Iowa
- of Iowa electricity from wind, 2023
- 59%
- renewable energy for MidAmerican Iowa customers
- 90%+
- minimum investment for the sales tax exemption
- $200M
- initial QTS energization expected in Cedar Rapids
- 300 MW
Two investor-owned utilities serve most of the state’s large loads: MidAmerican Energy across central and western Iowa, and Alliant Energy in much of eastern Iowa. Municipal utilities and rural electric cooperatives serve the rest, so the first question for any parcel is which utility service territory it falls in. Both investor-owned utilities sit in the MISO footprint; our MISO guide explains how the regional market and transmission planning shape timing.
02Council Bluffs, the Des Moines metro and Cedar Rapids
Iowa’s data center activity sits in three clusters, each with a different utility and land profile.
Fig. 2Iowa’s main data center clusters
Western Iowa
Council Bluffs
- Google’s long-running Iowa campus
- Expansion under Google’s $7B Iowa plan
- MidAmerican territory
- Across the Missouri River from Omaha
Central Iowa
Des Moines metro
- Meta’s Altoona campus, 5M+ sq ft planned
- Microsoft campuses in West Des Moines
- MidAmerican territory
- The state’s most mature cluster
Eastern Iowa
Cedar Rapids
- Alliant Energy territory
- Google transmission service energized
- QTS seven-building campus
- Initial 300 MW expected in 2026
Council Bluffs is Google’s Iowa base. In 2025 Google announced an additional $7 billion of investment in Iowa over two years for cloud and AI infrastructure, including expansion of the Council Bluffs facility and a new data center in Cedar Rapids.10 Because Council Bluffs faces Omaha across the river, a western Iowa search often runs alongside a Nebraska site search.
In the Des Moines metro, Meta began building in Altoona in 2013, and later expansions were set to push the campus past 5 million square feet of data center space, making it Meta’s largest.11 Microsoft has built repeatedly in West Des Moines; the city described one later project as a $1.5 to $2 billion investment.13 Cedar Rapids is the newest cluster. On Alliant’s July 2026 earnings call, the company said Google had energized transmission service there and would ramp demand on its contracted schedule, and that QTS was building a seven-building campus with initial energization of 300 MW expected later in the year.12
03MidAmerican, Alliant and individual customer rates
Iowa does not have a single statewide data center tariff. Large loads are usually served under negotiated contracts that the Iowa Utilities Commission reviews. MidAmerican states that data centers and other large-load customers pay for the infrastructure and generation required to serve them.2 That generally means the customer funds dedicated substations and transmission work, an arrangement covered in our guide to contribution in aid of construction.
Pricing is usually set through individual customer rates (ICRs): rates negotiated for a single large customer and reviewed by the commission.3 Alliant told investors in late 2025 that the commission had approved ICRs for two data centers under construction in Cedar Rapids.7 Its chief executive has said those data centers will help enable a five-year rate freeze for other customers.14
Not everyone thinks the ICR approach is enough. In comments on a 2026 bill, the Midwest Energy Efficiency Alliance noted that Iowa has seen meaningful data center and cryptocurrency mining activity and that some are concerned the ICR mechanism does not go far enough given the pace of growth.3
04Wind supply and clean energy claims
Iowa’s wind build is the reason many operators chose the state. MidAmerican says it has invested nearly $16 billion in wind generation since 2004 and that it provides its Iowa customers with more than 90% renewable energy on an annual basis.6 Statewide, wind produced 59% of all generation in 2023.1
Two cautions apply. First, “annual basis” means renewable output over a year is compared with customer use over a year. It does not mean every hour is served by wind, which matters to buyers pursuing 24/7 carbon-free energy or hourly matching. Second, a utility’s system mix is not the same as a dedicated supply contract. Operators that want specific clean energy attributes still contract for them, either with the utility or through the structures covered in our guide to renewable energy procurement.
For site screening, the practical point is that wind-rich territory does not remove the need for firm transmission and substation capacity at the parcel. A site several miles from a high-voltage line can still face years of upgrades, whatever the utility’s generation mix.
05The sales and use tax exemption after HF 976
Iowa’s main state incentive is a sales tax exemption for qualifying data center businesses. Governor Kim Reynolds signed House File 976 on June 6, 2025, changing both the scope and the administration of the exemption.5 The main terms are below.
| Term | What it requires |
|---|---|
| Investment | A minimum investment of $200 million.4 |
| Facility | A physical location in Iowa of at least 5,000 square feet in aggregate used to operate and maintain the data center.4 |
| Registration | Register with the Department of Revenue through its Data Center Registration portal by January 31, 2026.45 |
| Annual report | An annual report and registration are required to renew the exemption certificate each year.5 |
| Tenants | Tenants that lease a data center may now claim the benefits.5 |
| Time limits | For operations starting on or after January 1, 2026, the electricity and backup generation fuel exemptions expire after 10 or 15 years, depending on location.5 |
Facilities that began operating before January 1, 2026 are not subject to the new expiration dates.5 For a new project, the length of the exemption depends on where the facility sits, so confirm which term applies to a specific parcel with a tax advisor before it goes into a pro forma. Property tax treatment is negotiated locally and is separate; see our guide to sales tax exemptions by state for how Iowa compares.
062026 legislation and open questions
In February 2026, Iowa lawmakers introduced House File 2447. It would have required data centers to report how much water and electricity they use and where it comes from, required utilities to create separate rates and fees for data centers, and halted data center construction until the serving utility had filed its data center rates with the state.8 The bill moved forward as House File 2690 but did not pass the second funnel deadline, so it did not advance in the 2026 session.39
The bill’s failure does not settle the questions behind it. Water use and cost allocation were the two issues raised most often, and both tend to return in later sessions in states with fast data center growth, as has happened elsewhere. Treat a separate data center tariff or mandatory water reporting as a realistic possibility over the life of a project, and check local rules too, since counties and cities can act on their own; our guide to moratoriums and local restrictions covers how to screen for them.
07How to screen an Iowa site
- 01Identify the serving utility: MidAmerican, Alliant, a municipal utility or a cooperative. Each has different large-load practices.
- 02Ask for the utility’s large-load process and what an ICR would require, including who funds substation and transmission work.2
- 03Confirm the distance to transmission and the substation capacity available in your timeframe, independent of the utility’s generation mix.
- 04Test the sales tax exemption: the $200 million threshold, registration and annual reporting, and whether the 10- or 15-year term applies at that location.45
- 05Check water supply and local zoning early, given the 2026 debate over water reporting.8
- 06Watch the 2027 session for renewed data center tariff or reporting bills.
Fig. 3Sample screen of an Iowa parcel
Illustrative- PassServing utilityInvestor-owned utility with an active large-load team.
- WatchTransmissionNearest line is 4 miles away; route not yet studied.
- WatchSubstation capacityCapacity depends on upgrades with no firm date.
- PassSales tax exemptionPlanned investment well above $200 million.
- WatchWater supplyMunicipal capacity letter not yet requested.
- FailZoningAgricultural zoning; county has no data center district.
A screen like this tells you which questions to send to the utility and county first. Our due diligence checklist covers the rest, and you can get a site reviewed if you want an outside screen of an Iowa parcel.
Common questions
Why do so many large tech companies build data centers in Iowa?
Iowa offers low electricity prices, ranking among the 10 states with the lowest average price, and the highest wind share of any state.1 It also has a sales and use tax exemption for data centers investing at least $200 million.4 Meta and Microsoft built large campuses in Altoona and West Des Moines,1113 and Google expanded in Council Bluffs.10
Does Iowa have a data center sales tax exemption?
Yes. Qualifying data center businesses must invest at least $200 million, register with the Department of Revenue and file an annual report.4 Under House File 976, signed in 2025, tenants can now claim the benefits, and new facilities starting operations from 2026 face 10- or 15-year limits on the electricity and backup fuel exemptions.5
Which utilities serve data centers in Iowa?
Most large campuses are served by MidAmerican Energy, including those in Council Bluffs and the Des Moines metro, or by Alliant Energy, which serves the Google and QTS projects in Cedar Rapids.612 Municipal utilities and rural cooperatives serve other areas. Confirm the service territory before doing other work on a parcel.
What is an individual customer rate in Iowa?
It is a negotiated rate for a single large customer, reviewed by the Iowa Utilities Commission, and it is the main way Iowa utilities price data center service today.3 The commission approved ICRs for two Cedar Rapids data centers by late 2025.7 Because terms differ by deal, a neighboring project’s ICR tells you little about your own.
Is power for Iowa data centers really renewable?
MidAmerican says it provides its Iowa customers with more than 90% renewable energy on an annual basis.6 That is an annual comparison of output and use, not an hourly match, so operators with hourly clean energy goals still need specific contracts. Wind supplied 59% of statewide generation in 2023.1
Notes
- 1.U.S. Energy Information Administration, “Iowa State Profile and Energy Estimates,” n.d. eia.gov
- 2.MidAmerican Energy, “Data center costs,” n.d. midamericanenergy.com
- 3.Midwest Energy Efficiency Alliance, “MEEA Comments on HF 2690,” 2026. mwalliance.org
- 4.Iowa Department of Revenue, “IDR Releases Guidance: Data Center Sales & Use Tax Incentives,” 2025. content.govdelivery.com
- 5.Nyemaster Goode, “Immediate Iowa Tax Law Changes for Data Centers,” 2025. nyemaster.com
- 6.MidAmerican Energy, “About our company,” n.d. midamericanenergy.com
- 7.Alliant Energy, “EEI 2025 Slides,” 2025. s201.q4cdn.com
- 8.Iowa Public Radio, “Lawmakers look to regulate utility use by data centers,” 2026. iowapublicradio.org
- 9.Sierra Club Iowa Chapter, “Transparency Needed for Data Centers,” 2026. sierraclub.org
- 10.Google, “New $7 billion investment in Iowa,” 2025. blog.google
- 11.Data Center Frontier, “Meta Adds More Data Centers in Iowa, Pushing Campus to 5 Million SF,” 2021. datacenterfrontier.com
- 12.MarketBeat, “Alliant Energy Q2 Earnings Call Highlights,” 2026. marketbeat.com
- 13.City of West Des Moines, “Microsoft to build $1.5 - $2 billion data center in West Des Moines,” n.d. wdm.iowa.gov
- 14.Corridor Business Journal, “Alliant CEO: Cedar Rapids data centers will help enable five-year rate freeze,” n.d. corridorbusiness.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Related guides
More in Site selection by state
- Data Center Site Selection in Texas: Grids, SB 6, Water and Incentives
- Data Center Site Selection in Virginia: Power, GS-5, Zoning and Tax Rules
- Data Center Site Selection in Georgia: Georgia Power, PSC Rules, Water and Taxes
- Data Center Site Selection in Arizona: APS, SRP, TEP, Water and Heat
- Data Center Site Selection in Ohio: AEP Ohio’s Tariff, PJM Costs and the Tax Pause
- Data Center Site Selection in Nevada: NV Energy, Reno and Las Vegas, Water Rules and GOED Abatements
- Data Center Site Selection in Oregon
- Data Center Site Selection in North Carolina
- Data Center Site Selection in South Carolina
- Data Center Site Selection in Pennsylvania
- Data Center Site Selection in Indiana
- Data Center Site Selection in Wisconsin
- Data Center Site Selection in Minnesota
- Data Center Site Selection in Oklahoma
- Data Center Site Selection in Utah
- Data Center Site Selection in Washington State
- Data Center Site Selection in Louisiana
- Data Center Site Selection in Mississippi
- Data Center Site Selection in Alabama
- Data Center Site Selection in Tennessee
- Data Center Site Selection in Kentucky
- Data Center Site Selection in Missouri
- Data Center Site Selection in Kansas
- Data Center Site Selection in New Mexico
- Data Center Site Selection in Wyoming
- Data Center Site Selection in North Dakota
- Data Center Site Selection in New York: NYISO, Hydropower and the 2026 Permit Pause
- Data Center Site Selection in Michigan: DTE, Consumers, Tax Rules and Water
- Data Center Site Selection in Arkansas: Entergy, SWEPCO, 2025 Laws and Local Rules
- Data Center Site Selection in Colorado: Xcel’s Large-Load Tariff, Water and Local Rules
- Data Center Site Selection in Idaho
- Data Center Site Selection in West Virginia
- Data Center Site Selection in Maryland
- Data Center Site Selection in Montana
- Data Center Site Selection in South Dakota
- Data Center Site Selection in Florida
