Key takeaways
- ComEd’s large-load pipeline exceeds 28,000 MW across more than 75 projects, about 1.2 times its highest-ever peak, and the ICC approved larger deposits for these customers in March 2026.2
- Northern Illinois (ComEd) is in PJM; most of downstate (Ameren Illinois) is in MISO Zone 4, with separate capacity markets and prices.47
- The state’s 2025 resource adequacy study projects shortfalls in ComEd’s territory by 2029 and in Ameren’s by 2031.84
- Governor Pritzker directed DCEO to stop accepting new Data Center Investment Program applications as of July 1, 2026, after the General Assembly did not act.56
- The Climate and Equitable Jobs Act targets a zero-emission power sector by 2045, which shortens the useful life of new gas plants built to serve data centers.910
- Elk Grove Village remains the state’s densest cluster, while cities such as Bloomington have weighed moratoriums.1112
01Why Illinois, and why the Chicago suburbs first
Illinois’ data center market is centered on the Chicago suburbs. The draw has been dense fiber, a large enterprise and financial customer base, flat industrial land and, until 2026, a state tax incentive program. Supply is tight. CBRE reported Chicago vacancy of 1.9% in the second half of 2025, with no contiguous block of 5 MW or more available, and 2.2% in the first quarter of 2026, when Chicago posted the largest rent increase of the major U.S. markets at 14.7%.113
Elk Grove Village, just west of O’Hare, calls itself the data center capital of the Midwest; its mayor has said about 20 data centers operate there with five more under construction.11 CBRE’s notable activity included Prime Data Centers fully leasing its Elk Grove Village campus, Equinix announcing a hyperscale campus in Minooka and PowerHouse Data Centers partnering with Hillwood on a 1.8 GW campus in Joliet.1 Newer development is pushing past the inner suburbs toward sites that can take 500 MW or more, which in practice means the outer ring and beyond.1
For a site search, the key fact about Illinois is that it is split between two grid operators. The northern part of the state, including Chicago, is served by ComEd and sits in PJM; most of central and southern Illinois is served by Ameren Illinois and sits in MISO.4 Confirm the utility service territory of every parcel first, because tariffs, capacity prices and queue times differ on each side of that line.
02ComEd and PJM: a queue larger than the system
In March 2026 the Illinois Commerce Commission (ICC) approved a ComEd proposal that lets the utility require deposits from large-load developers, sized to each project’s energy needs. The deposits let ComEd recover costs if a customer goes out of business, moves, or leaves facilities built to serve it under-used.2 The commission called the approval an important first step, set aside broader consumer protections as outside the scope of the case, and directed staff to open new proceedings on them.2
Fig. 1ComEd’s large-load pipeline, March 2026
- Large-load projects in the pipeline
- 75+
- Expected demand of those projects
- 28,000+ MW
- ComEd’s highest-ever peak demand
- ~24,000 MW
- Pipeline demand vs. record peak
- ~1.2×
Not all of that pipeline will be built, but the queue drives timing for everyone in it. CBRE reported that projects served by ComEd face power delivery delays until 2032 or later.1 The Illinois Power Agency’s December 2025 resource adequacy study adds a supply problem on top of the delivery problem: it projects shortfalls in ComEd’s northern Illinois territory by about 2029, driven by load growth from data centers, transportation and industry while coal, gas and oil units retire across both regional grids.84
Because ComEd is a PJM utility, capacity costs are set in part by PJM’s regional auction rather than by the state alone. Compare an Illinois site with an Ohio or Indiana site on the same basis, and see our PJM regional guide and PJM capacity prices guide for how the capacity market feeds into bills.
03Ameren Illinois and MISO: the downstate option
Ameren Illinois serves most of downstate Illinois and is in MISO’s Zone 4.47 On its first-quarter 2026 earnings call, Ameren reported 850 MW of signed construction agreements in Illinois and said additional projects are under engineering study.14 State planners have noticed the shift: the Illinois Power Agency’s July 2026 planning materials say updated data center forecasts are higher in the Ameren zone and lower in the ComEd zone, and that the distribution of data center load has moved toward the MISO footprint.3
MISO capacity prices are seasonal and have been volatile. The Citizens Utility Board reported that the Zone 4 summer price fell from a record $666.50/MW-day in 2025 to $424.30/MW-day for summer 2026, still elevated, and named rising forecast load from new and proposed data centers as one of the drivers.7 The resource adequacy study projects shortfalls in the Ameren area by about 2031, a few years after ComEd.84
Fig. 2MISO Zone 4 summer capacity price
- Summer 2025$666.50
- Summer 2026$424.30
$/MW-day
Fig. 3Northern vs. downstate Illinois
Chicago metro
ComEd (PJM)
- Deep fiber and an established market
- Pipeline above 28,000 MW
- Delivery delays to 2032+ reported
- Projected shortfall by about 2029
Downstate
Ameren Illinois (MISO)
- 850 MW of signed construction agreements
- Data center forecasts revised upward
- Seasonal MISO capacity prices
- Projected shortfall by about 2031
MISO’s market rules, queue and resource adequacy constructs are covered in our MISO regional guide; neighboring MISO states include Wisconsin and Missouri.
04The Data Center Investment Program and its pause
Illinois’ incentive is the Data Center Investment Program, run by the Department of Commerce and Economic Opportunity (DCEO). A memorandum of understanding sets the terms under which a qualifying data center may receive state and local sales and use tax exemptions for up to 20 years, issued as renewable five-year certificates, and in some cases tax credits.5
| Requirement | Threshold |
|---|---|
| Capital investment | At least $250 million, owner and tenants combined |
| Jobs | At least 20 full-time or equivalent operations jobs |
| Pay | Total compensation at least 120% of the county median wage |
| Sustainability | Carbon neutral or certified to a green building standard |
| Construction wage credit | 20% of construction wages in underserved areas |
On June 5, 2026, Governor Pritzker directed DCEO to stop taking new applications as of July 1, 2026, after the General Assembly did not act.56 The pause is administrative, not statutory, and how existing agreements are treated is a question for DCEO and counsel.6 For a project still in planning, model the Illinois case without the exemption and treat any restart as upside. Our sales tax exemptions by state and incentives vs. power cost guides put that in context.
05CEJA, CRGA and on-site power
The Climate and Equitable Jobs Act of 2021 (CEJA) targets a zero-emission power sector by 2045, with earlier phase-out dates for private fossil units located within three miles of an environmental justice community.9 That matters for behind-the-meter gas generation, a common workaround for slow grid service elsewhere. The developer of the proposed Lincoln Land Energy Center, a gas plant meant to power a data center campus in Christian County, argued that unless the law changes the plant would have too short a life to attract investors, and the data center developer later abandoned its plans there.10
In January 2026 the governor signed the Clean and Reliable Grid Affordability Act (CRGA), which sets a target of 3 GW of battery storage procurement by 2030 and lifts Illinois’ ban on new large-scale nuclear plants.15 CRGA does not add a data center tariff, but storage and nuclear options change the long-run supply picture.
The next fight is the POWER Act, introduced February 11, 2026, which would require data centers to pay for their own energy, invest in renewable generation, report water use and work with host communities.16 It did not advance before the end of the spring 2026 session, though negotiations may continue; a separate bill, SB 2181, would require energy and water reporting.6 Plan for some form of “bring your own clean capacity” rule, and price it before you option land.
06Local approvals and water
Zoning is local in Illinois, and local positions now vary widely. Elk Grove Village markets itself as the Midwest’s data center capital and keeps adding campuses.11 Downstate, Bloomington council members signaled support for a six-month moratorium in May 2026, citing water and energy.12 Expect hearings to focus on noise, water source, generator emissions and tax revenue.
Water is less of a hard constraint in northern Illinois than in the desert Southwest, but it is a political issue, particularly in areas that draw on aquifers. Reporting bills such as SB 2181 signal where state policy is heading.6 Ask the municipal water utility for a written capacity letter and discuss closed-loop cooling early; our municipal water and sewer capacity guide covers what to request.
07How to screen an Illinois site
- 01Confirm the utility (ComEd, Ameren Illinois, a cooperative or a municipal system) and therefore PJM or MISO.4
- 02Ask the utility where the load would sit in its queue, what deposit or security applies, and what delivery date it will commit to in writing.2
- 03Model energy and capacity costs for the right market, including the projected shortfall years.87
- 04Run the tax case without the Data Center Investment Program and confirm status with DCEO.5
- 05If on-site gas is part of the plan, test its economics against the 2045 zero-emission target and any environmental justice proximity rules.9
- 06Check for local moratoriums, pending zoning text amendments and the water source before signing an option.
Our large-load tariffs guide explains the agreements you will negotiate, and the screening approach is laid out in our methodology. If you want a second opinion on a specific parcel, get a site reviewed.
Common questions
Is Illinois in PJM or MISO?
Both. Northern Illinois, served by ComEd, is in PJM, and most of central and southern Illinois, served by Ameren Illinois, is in MISO.4 Capacity prices, queues and resource adequacy rules differ between the two, so the parcel’s utility matters before anything else.
Does Illinois still offer a data center tax exemption?
The Data Center Investment Program remains in statute, but DCEO stopped taking new applications on July 1, 2026, at the governor’s direction.56 Projects should confirm with DCEO how any existing agreement is treated and should not assume a restart.
How long does it take to get power from ComEd?
It depends on location and size, but CBRE reported power delivery delays to 2032 or later for ComEd-served projects, and ComEd’s large-load pipeline exceeds its record peak demand.12 Get a written estimate of the service date from the utility.
Can a data center build its own gas plant in Illinois?
It is not prohibited outright, but CEJA targets a zero-emission power sector by 2045, with earlier phase-outs for units near environmental justice communities.9 That limits how long a new gas plant can run, which has already deterred at least one proposed project.10 Confirm current rules with environmental counsel.
Notes
- 1.CBRE, “Chicago Data Center Market, North America Data Center Trends H2 2025,” 2026. cbre.com
- 2.Capitol News Illinois, “Regulators OK ComEd’s plan to increase deposit costs for large-load projects like data centers,” 2026. capitolnewsillinois.com
- 3.Illinois Power Agency, “Final IRP and Mitigation Plan Workshop: ELCCs, July 2026,” 2026. ipa.illinois.gov
- 4.WTTW News, “Illinois Electrical Grids Could Face Power Shortages and Price Increases, State Report Warns,” 2025. news.wttw.com
- 5.Illinois Department of Commerce and Economic Opportunity, “Data Centers,” n.d. dceo.illinois.gov
- 6.Venable LLP, “Data Center Tax Incentives Under Pressure as States Reassess Costs and Infrastructure Impacts,” 2026. venable.com
- 7.Citizens Utility Board, “Ameren summer 2026 electricity prices and the MISO capacity auction (CUB blog),” 2026. citizensutilityboard.org
- 8.Illinois Power Agency, “Illinois Resource Adequacy Study 2025: Executive Summary,” 2025. ipa.illinois.gov
- 9.PJM Interconnection, “Update on Illinois Clean Energy Jobs Act,” 2021. ftp.pjm.com
- 10.Springfield Business Journal, “Data center developer abandons plans for Christian County,” n.d. springfieldbusinessjournal.com
- 11.NBC Chicago, “Data center capital of the Midwest expands as Pritzker calls for regulations,” n.d. nbcchicago.com
- 12.WGLT, “Bloomington City Council members signal support for 6-month data center moratorium,” 2026. wglt.org
- 13.CBRE, “Global Data Center Trends 2026,” 2026. cbre.com
- 14.Nasdaq, “Ameren Q1 Earnings Call Highlights,” 2026. nasdaq.com
- 15.WTTW News, “Pritzker Signs Major Energy Reform Bill Amid Projected Shortages,” 2026. news.wttw.com
- 16.Capitol News Illinois, “POWER Act: Lawmakers seek to regulate new data centers’ power, water usage,” 2026. capitolnewsillinois.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Related guides
More in Site selection by state
- Data Center Site Selection in Texas: Grids, SB 6, Water and Incentives
- Data Center Site Selection in Virginia: Power, GS-5, Zoning and Tax Rules
- Data Center Site Selection in Georgia: Georgia Power, PSC Rules, Water and Taxes
- Data Center Site Selection in Arizona: APS, SRP, TEP, Water and Heat
- Data Center Site Selection in Nevada: NV Energy, Reno and Las Vegas, Water Rules and GOED Abatements
- Data Center Site Selection in Oregon
- Data Center Site Selection in Iowa
- Data Center Site Selection in North Carolina
- Data Center Site Selection in South Carolina
- Data Center Site Selection in Pennsylvania
- Data Center Site Selection in Wisconsin
- Data Center Site Selection in Minnesota
- Data Center Site Selection in Nebraska
- Data Center Site Selection in Oklahoma
- Data Center Site Selection in Utah
- Data Center Site Selection in Washington State
- Data Center Site Selection in Louisiana
- Data Center Site Selection in Mississippi
- Data Center Site Selection in Alabama
- Data Center Site Selection in Tennessee
- Data Center Site Selection in Kentucky
- Data Center Site Selection in Missouri
- Data Center Site Selection in Kansas
- Data Center Site Selection in New Mexico
- Data Center Site Selection in Wyoming
- Data Center Site Selection in North Dakota
- Data Center Site Selection in New York: NYISO, Hydropower and the 2026 Permit Pause
- Data Center Site Selection in Michigan: DTE, Consumers, Tax Rules and Water
- Data Center Site Selection in Arkansas: Entergy, SWEPCO, 2025 Laws and Local Rules
- Data Center Site Selection in Colorado: Xcel’s Large-Load Tariff, Water and Local Rules
- Data Center Site Selection in Idaho
- Data Center Site Selection in West Virginia
- Data Center Site Selection in Maryland
- Data Center Site Selection in Montana
- Data Center Site Selection in South Dakota
- Data Center Site Selection in Florida