BlackForge Data Centers

Site selection by state

Data Center Site Selection in Maryland

Maryland’s data center market is concentrated at Quantum Frederick, a 2,100-acre former aluminum smelter site in Adamstown about 25 miles north of Ashburn, Virginia, and Frederick County has drawn a roughly 2,600-acre overlay that keeps new data centers near it.12 Under the 2025 Next Generation Energy Act, loads of 100 MW or more must take service under a utility rate schedule built to cover their grid costs.3 Maryland also imports a large share of its power, so siting comes down to utility capacity, PJM conditions and a tax and zoning picture that is still moving.4

Last reviewed · 8 min read · BlackForge Data Centers

Key takeaways

  • Quantum Frederick occupies the former Eastalco aluminum plant in Adamstown, bought for $100 million and planned as a campus of about 1 GW.15
  • Frederick County’s Critical Digital Infrastructure overlay covers about 2,600 acres north of Adamstown; a referendum petition on it failed in court in 2026.26
  • The Next Generation Energy Act requires utilities to adopt PSC-approved rate schedules for customers of at least 100 MW with a load factor above 80%.3
  • In 2024 Maryland generated about 35.4 million MWh but sold about 59 million MWh at retail, leaving roughly 40% to come from outside the state.4
  • The sales and use tax exemption needs five new jobs and $2 million (Tier 1 areas) or $5 million (elsewhere) of qualified property; a 2026 bill proposed repealing it.78

01Why Maryland is in the conversation

Maryland’s case is proximity. The state sits next to the Northern Virginia data center cluster, and its main campus at Adamstown is about 25 miles due north of Ashburn.1 Developers squeezed by land, power and entitlement limits in Loudoun and Prince William counties have looked across the Potomac for the same fiber reach and labor pool. Our Northern Virginia market guide and Virginia site selection guide cover the other side of the river.

Power is the counterweight. Maryland is a net importer: in 2024 in-state generation was about 35.4 million MWh against retail sales of about 59 million MWh, a gap of roughly 40%.4 In 2023 natural gas overtook nuclear as the largest source of in-state generation for the first time.9 A state that already buys much of its power from the rest of PJM has little slack for gigawatt loads, which is why the Legislature has moved quickly on large-load rules and new generation.

Fig. 1Maryland generation vs. retail sales, 2024

  • In-state net generation35.4
  • Retail electricity sales59

million MWh

The gap between what Maryland generates and what it sells is met with imports from the PJM grid.4

02Quantum Frederick: the anchor campus

Almost all large-scale data center activity in Maryland runs through one site. In a joint venture with TPG Real Estate Partners, Quantum Loophole bought the 2,100-acre former Eastalco Aluminum smelter in Adamstown from an Alcoa subsidiary in a transaction valued at $100 million.1 The developer planned a 1 GW campus built from data center modules of 30–120 MW, with infrastructure for natural gas, energy storage and hydrogen.5 The campus is now known as Quantum Frederick.10

A former industrial site of this kind is the textbook powered land play: a large, flat, already-disturbed parcel with heavy electrical history, outside residential neighborhoods. It also brings legacy environmental questions, which is why a Phase I ESA and any state cleanup records belong early in diligence on similar sites.

Aligned Data Centers bought land on the campus as an early tenant.11 Its Maryland campus is listed at 75 acres, served by FirstEnergy’s Potomac Edison, with construction starting in 2025.12 In 2025 the Maryland Department of the Environment approved an application for 172 diesel backup generators for Aligned at Quantum Frederick, a reminder that air permits for backup generators scale with the campus.10

Fig. 2Quantum Frederick by the numbers

former Eastalco smelter site1
2,100 acres
reported purchase price1
$100M
planned campus capacity5
~1 GW
generators approved for one tenant10
172
Figures as announced by the developer and reported by the trade press and state regulators.

03Frederick County’s overlay zone and the referendum fight

Frederick County chose to concentrate data centers rather than ban or scatter them. In December 2025 the County Council passed a map for a Critical Digital Infrastructure overlay zone of about 2,600 acres, designed to keep the industry in one location north of Adamstown on and around the former Eastalco site and to prevent sprawl.2 The council chose the larger map over a planning commission version about 1,000 acres smaller, and many residents wanted the zone limited to the existing campus.2 Our guide to data center zoning ordinances and overlay districts explains how these tools work.

Opponents then gathered more than 22,000 signatures to put the overlay ordinance to a referendum.6 The courts ruled that the ordinance adopting the overlay map was not a law subject to referendum under the county charter, and the Supreme Court of Maryland agreed with the circuit court.6 In late July 2026 the county executive asked for a pause on a data center land use vote, so the local rules are still being worked out.13

Fig. 3Frederick County overlay, key events

  • Council passes overlay mapAbout 2,600 acres north of Adamstown
  • Referendum petition driveMore than 22,000 signatures submitted
  • Court challengeMap ruled not subject to referendum
  • Executive seeks pauseRequest on a land use vote
02468months from Dec. 2025
Approximate timing from local reporting.613

For a buyer, the practical point is that a Frederick County parcel outside the overlay is very unlikely to be a data center site under current policy, and a parcel inside it still faces site plan, utility and permit scrutiny from an engaged public. See moratoriums and local restrictions for how to screen for this.

04Potomac Edison, BGE and the Next Generation Energy Act

Maryland’s major utilities, including Potomac Edison in Frederick County and western Maryland and BGE in the Baltimore region, all operate in PJM. That means a large load faces two layers: the utility’s rate schedule and interconnection process before the Maryland Public Service Commission, and PJM’s transmission planning and capacity market. See PJM site selection and PJM capacity prices.

The Next Generation Energy Act of 2025 (Chapters 625 and 626) requires each electric utility to adopt a specific rate schedule, approved by the PSC, for a large load customer: a commercial or industrial customer with an aggregate monthly demand of at least 100 MW and a load factor above 80%.3 The schedule must:

  • Make the customer cover the just and reasonable costs of transmission or distribution buildout needed to interconnect or serve it.3
  • Protect residential customers from the financial risks of large loads.3
  • Keep other customers from unreasonably subsidizing large-load costs.3

Reporting on the act says utilities have until January 1, 2027 to file these schedules.14 A 2026 bill, House Bill 1082, proposed extending the large-load definition to every data center regardless of size or load factor, and removing data centers from an exemption for existing customers that expand by no more than 25 MW.3 Confirm the final rules with the utility before modeling a project; our guide to large-load tariffs and electric service agreements covers the usual terms.

The act also set up a procurement of new dispatchable generation, defined as units with an effective load carrying capability of at least 65% that emit less than coal or oil plants, with an expedited path under which the PSC decides on a certificate of public convenience and necessity within 295 days.15 The PSC sought generation proposals under the act in 2025.16 That new supply is aimed at reliability for the whole state, not at any single data center.

05Maryland’s data center sales tax exemption

Maryland exempts qualified data centers from state sales and use tax on qualified data center personal property.7 According to the Department of Commerce, within three years of applying a business must:

Qualification thresholds for the Maryland data center sales and use tax exemption.[^7]
RequirementTier 1 areaRest of state
Minimum investment in qualified property$2 million$5 million
New qualified full-time positions55
Wage floor150% of state minimum wage150% of state minimum wage

Tier 1 areas are Baltimore City, Allegany, Caroline, Dorchester, Garrett, Kent, Somerset, Washington, Wicomico and Worcester counties, plus Opportunity Zones in any county.7 Frederick County is not on that list, so a Quantum Frederick project uses the $5 million threshold unless it sits in an Opportunity Zone. Jobs must be net new to Maryland and filled for 12 months, and the business applies to Commerce first.7

The exemption is under pressure. House Bill 560 of 2026 proposed repealing it, along with local governments’ authority to reduce the assessment of data center personal property, effective July 1, 2026; the fiscal note expected a potentially significant increase in state revenue.8 Legislative listings we found did not show it advancing past committee, but confirm the current law with Commerce or a tax adviser before relying on the exemption. See sales tax exemptions by state and tax incentives vs. power costs.

06How to screen a Maryland site

  1. 01Confirm the county’s rules first; in Frederick County, check whether the parcel is inside the overlay.2
  2. 02Identify the utility (Potomac Edison, BGE or another) and request an indicative capacity and timing answer at your peak MW and ramp.
  3. 03If the load is 100 MW or more with a high load factor, model the large-load rate schedule and its cost-recovery terms.3
  4. 04Plan air permitting for backup generators early, especially at campus scale.10
  5. 05Test the sales tax exemption against the Tier 1 and job thresholds, and confirm it is still in force.78
  6. 06Check environmental history on former industrial land and floodplain near the Potomac and Monocacy rivers.

The site due diligence checklist and our methodology cover the general items. If you hold or are evaluating land in Maryland, you can get a site reviewed.

Common questions

Where are data centers allowed in Frederick County, Maryland?

Mainly within the Critical Digital Infrastructure overlay of about 2,600 acres north of Adamstown, around the former Eastalco site that is now Quantum Frederick.2 A referendum effort against the overlay failed in court in 2026.6

What is Quantum Frederick?

It is the 2,100-acre data center campus on the former Eastalco aluminum smelter in Adamstown, bought by Quantum Loophole and TPG Real Estate Partners for $100 million.1 It was planned for about 1 GW, and Aligned Data Centers is building there.511

Does Maryland have a data center sales tax exemption?

Yes, for qualified data centers that create five jobs and invest at least $2 million in Tier 1 areas or $5 million elsewhere within three years.7 A 2026 bill proposed repealing it, so confirm current status before relying on it.8

What does the Next Generation Energy Act mean for data centers?

Utilities must create PSC-approved rate schedules for customers of 100 MW or more with load factors above 80%, and those schedules must make the customer cover the grid costs it causes.3 The act also launched a procurement of new dispatchable generation.1516

Does Maryland have enough power for large data centers?

Not on its own. In 2024 Maryland sold about 59 million MWh at retail but generated about 35.4 million MWh, relying on PJM imports for the rest.4 New large loads depend on utility upgrades and PJM transmission, so capacity is site-specific.

Notes

  1. 1.Data Center Dynamics, “Quantum Loophole buys 2,100-acre property in Frederick County, Maryland for gigawatt data center campus,” n.d. datacenterdynamics.com
  2. 2.WYPR, “Frederick County Council passes map for data center development,” 2025. wypr.org
  3. 3.Maryland Department of Legislative Services, “Fiscal and Policy Note, House Bill 1082 (2026 Session),” 2026. mgaleg.maryland.gov
  4. 4.U.S. Energy Information Administration, “Maryland Electricity Profile,” n.d. eia.gov
  5. 5.Data Center Frontier, “Quantum Loophole Plans 2,100 Acre Data Center Campus in Maryland,” n.d. datacenterfrontier.com
  6. 6.WYPR, “How Frederick County’s first citizen-led referendum failed in court,” 2026. wypr.org
  7. 7.Maryland Department of Commerce, “Data Center Maryland Sales and Use Tax Exemption Incentive Program,” n.d. commerce.maryland.gov
  8. 8.Maryland Department of Legislative Services, “Fiscal and Policy Note, House Bill 560 (2026 Session),” 2026. mgaleg.maryland.gov
  9. 9.U.S. Energy Information Administration, “Maryland State Profile and Energy Estimates: Profile Analysis,” n.d. eia.gov
  10. 10.Nature Forward, “Quantum Frederick, Frederick County, MD: Maryland Data Center Series, Pt. 3,” n.d. natureforward.org
  11. 11.Data Center Dynamics, “Aligned buys plot of land on Quantum Loophole’s gigawatt campus in Maryland,” n.d. datacenterdynamics.com
  12. 12.Baxtel, “Aligned: Maryland Campus IAD04,” n.d. baxtel.com
  13. 13.WYPR, “Frederick County executive requests pause on data center land use vote,” 2026. wypr.org
  14. 14.Pennsylvania Capital-Star (from Maryland Matters), “In 2026, more data center regulations could be coming in Maryland,” 2026. penncapital-star.com
  15. 15.Maryland Department of Legislative Services, “Fiscal and Policy Note, House Bill 1035 (2025 Session),” 2025. mgaleg.maryland.gov
  16. 16.Maryland Public Service Commission, “PSC Seeks Generation Proposals Under Next Gen Energy Act,” 2025. psc.maryland.gov

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Related guides

More in Site selection by state