BlackForge Data Centers

Site selection by state

Data Center Site Selection in Alabama

In Alabama, the serving utility shapes almost everything: Alabama Power, regulated by the Public Service Commission, serves most of the state, while TVA-supplied local power companies serve the north, where loads above 100 MW need TVA board approval.12 Two 2026 laws reset the terms for big projects: one subjects Alabama Power contracts with data centers of 150 MW or more to a new PSC review, and the other trims the state’s data center tax abatements from up to 30 years to 20 and limits them for 100 MW+ loads from 2027.34 Local rezoning and water questions, highlighted by the Bessemer hyperscale fight, are now part of every serious screen.5

Last reviewed · 9 min read · BlackForge Data Centers

Key takeaways

  • Act 2026-610, effective October 1, 2026, defines a large load data center as at least 150 MW of peak demand on one or more contiguous parcels and sends those Alabama Power contracts through a PSC proceeding.3
  • HB399, enacted April 17, 2026, cuts the maximum data center abatement from 30 to 20 years, requires 100 MW+ centers to pay certain purchase taxes from January 1, 2027, and extends applications to July 31, 2032.4
  • Alabama Power bought the 895 MW Lindsay Hill gas plant for $622 million after telling regulators it needed about 1,200 MW of new capacity by decade’s end, partly for data centers.6
  • In north Alabama’s TVA territory, data center loads above 5 MW face a capacity commitment charge from October 1, 2026, with an average bill impact of about 10% phased in over three years.72
  • Bessemer rezoned about 700 acres for a $14.5 billion hyperscale campus on a 5–2 vote, and the follow-on lawsuit was dismissed in June 2026.58
  • Any user able to withdraw 100,000 gallons per day or more must register with the state Office of Water Resources and hold a Certificate of Use.9

01Alabama Power or TVA: start with the territory

Alabama has two very different paths to large-scale power. Most of the state is served by Alabama Power, a vertically integrated utility whose contracts with large customers, including data centers, are regulated by the Alabama Public Service Commission.1 North Alabama is mostly Tennessee Valley Authority country, where TVA sells wholesale power to municipal utilities and cooperatives that serve end customers. Rural cooperatives and municipal systems also serve pockets elsewhere, so a parcel’s utility service territory should be confirmed before land terms are negotiated.

The TVA path has its own approval gates. Decatur Utilities has described the rules plainly: contracts larger than 5 MW are reviewed by TVA, and requests above 100 MW require approval from the TVA board.2 On August 20, 2026, the TVA board approved a wholesale rate class for data centers; from October 1, 2026, new or expanding data center loads above 5 MW pay a capacity commitment charge, with an expected average bill impact of about 10% phased in over three fiscal years.7

Fig. 1Two utility paths for Alabama data centers

Central and south

Alabama Power

  • Investor-owned, regulated by the Alabama PSC
  • Contracts for 150 MW+ data centers get PSC review
  • Adding gas capacity for load growth
  • Single utility counterparty for the load

North

TVA local power companies

  • City utilities and co-ops buy TVA power
  • Contracts above 5 MW reviewed by TVA
  • Requests above 100 MW need TVA board approval
  • Data center rate class from October 2026
General patterns from public filings and reporting; confirm specific terms with the serving utility.237

Neither path is simply faster. Alabama Power offers one regulated counterparty but a new public review for the largest loads. TVA territory adds a federal board step and a new rate design, but sites near retired TVA plants can come with heavy transmission. Our Southeast regional guide compares these utility models across neighboring states.

02Act 2026-610 and PSC review of large data center contracts

The biggest regulatory change of 2026 is Act 2026-610, which took effect October 1, 2026. It defines “large load” data center customers as those expected to require at least 150 MW of peak demand at one or more contiguous parcels, and the PSC has opened a generic proceeding to set procedures and standards for contracts between Alabama Power and those customers, with comments due in August.3 As introduced, the Senate bill would have required the PSC to confirm that the utility recovers the incremental costs of serving such a load and that contracts produce benefits for other customers, such as lower system costs or local economic growth.10

The first contract is already public in part. In late July 2026, a contract for electric service between Alabama Power and Alabama ADC Holdings, LLC, which county property records tie to the proposed Nebius AI factory site in Birmingham’s Oxmoor Valley, was filed with the PSC; the public version withholds the provisions that could affect other customers’ bills.1

For a developer, the practical effects are timing and disclosure. Build PSC review into the schedule for any load at or above 150 MW, expect questions about who pays for new generation, and read our guide to data centers and electricity ratepayers before public hearings. Contract structure is covered in large-load tariffs and electric service agreements.

03Alabama Power’s capacity plan

Alabama Power told the PSC in October 2024 that it would need roughly 1,200 MW of new capacity by the end of the decade, partly because of data center growth, and that it expected surplus capacity only until 2028.6 Its answer, approved in August 2025, was to buy the 895 MW Lindsay Hill gas-fired plant in Autauga County from Tenaska for $622 million to address a projected shortfall by 2029.6

Fig. 2Alabama Power’s load growth response

new capacity needed by 20306
~1,200 MW
Lindsay Hill gas plant purchased6
895 MW
purchase price approved in 20256
$622M
large load threshold under Act 2026-6103
150 MW
Figures from the 2025 Lindsay Hill approval and the 2026 large-load law.63

The scale of the proposed pipeline explains the regulatory attention. A 2026 analysis found that proposed data centers in Alabama could use more electricity than all of the state’s homes combined.11 Proposed load is not built load, and many announced projects will shrink or stall, but the figure tells you how a utility will read a new request: as one more claim on capacity it still has to build. Ask early how your ramp schedule fits the generation plan, and whether a smaller first phase can be served from existing resources.

04The data processing center abatement after HB399

Alabama has offered data center tax abatements since 2012 legislation that lets eligible data processing centers abate certain sales and use taxes and property taxes, with property tax abatement terms of 10 to 30 years depending on the level and timing of investment.12 Before the 2026 changes, projects investing at least $400 million and creating 20 jobs paying at least $40,000 a year could qualify for both sales tax and property tax relief, a combination few states offer.13

HB399, enacted April 17, 2026, changed the program in four ways:4

  • The maximum abatement period falls from 30 years to 20 years.4
  • Data processing centers with total peak demand of 100 MW or more must pay certain taxes on purchases from January 1, 2027, with exceptions for some equipment and infrastructure.4
  • Qualifying centers must make community development investments, such as local utility or education upgrades.4
  • The deadline to apply for an abatement moves from July 31, 2028, to July 31, 2032.4

The 100 MW line matters for hyperscale and AI campuses: their construction purchases may no longer escape state sales and use tax once in service, so model taxes both ways. Abatements are negotiated with local governments, so read our guides to property taxes on data center projects and sales tax exemptions by state, and confirm the current terms with a tax advisor.

05Where projects are landing: Bridgeport, Montgomery, Bessemer

Alabama’s data center map runs from former industrial sites to greenfield land. Google built a $600 million data center in Bridgeport, Jackson County, with up to 100 jobs, on the site of TVA’s retired Widows Creek coal plant, and it began operating in 2019.1415 It is a textbook case of repurposing a power plant site: transmission, water and industrial zoning were already in place. By 2025 Google was the largest contributor to Jackson County’s tax base.15

Meta runs a campus in Huntsville and announced an $800 million data center in Montgomery, later expanded to bring total Montgomery investment above $1.5 billion.1615 In Jefferson County, the Bessemer City Council voted 5–2 in November 2025 to rezone nearly 700 acres from agriculture to light industrial for a hyperscale campus its developers value at $14.5 billion, over objections about power rates, water supply and the number of permanent jobs.5 A lawsuit seeking more disclosure about the council’s decision was dismissed with prejudice on June 22, 2026.8

Fig. 3Announced Alabama data center investments

  • Google, Bridgeport0.6
  • Meta, Montgomery (total)$1.5B+
  • Bessemer hyperscale campus14.5

billion dollars

Headline figures as announced; they mix phases and owners and are not directly comparable.14165

The Bessemer case shows that rezoning can be the critical path even where power is available. See our guide to community engagement for how local concerns tend to surface.

06Water: registration, not a permit system

Alabama manages water use through registration more than allocation. Under the Alabama Water Resources Act of 1993, the Office of Water Resources within ADECA requires public water systems and anyone with the capacity to withdraw 100,000 gallons per day or more to register and obtain a Certificate of Use listing each surface or groundwater withdrawal point.9 That is a lighter process than the permit regimes in some western states, but it is not a capacity commitment: a certificate records a withdrawal, and it does not tell you whether the river, aquifer or municipal system can supply a campus through a drought.

Water also shows up in local politics. Bessemer residents raised water supply as a central objection to the hyperscale rezoning.5 For most Alabama projects the realistic options are a municipal supply contract, an on-site well or river intake registered with OWR, or a cooling design that uses little water. Our guides to water rights and groundwater and municipal water and sewer capacity cover how to test each option.

07How to screen an Alabama site

  1. 01Confirm the serving utility. In TVA territory, model the capacity commitment charge and plan for the 100 MW board step.27
  2. 02If the load will reach 150 MW with Alabama Power, plan for the Act 2026-610 contract review and its disclosure rules.31
  3. 03Model the HB399 tax terms, especially the 100 MW purchase tax rule from 2027 and the new community investment requirement.4
  4. 04Check zoning and the local political temperature; many large sites need a rezoning from agricultural use.5
  5. 05Confirm water supply and the OWR registration path for any withdrawal of 100,000 gallons per day or more.9
  6. 06Run the usual physical screens: floodplain, wetlands, slope and buildable acreage.

Alabama competes most directly with Georgia, Tennessee and Mississippi. If you want an outside read on a specific parcel, you can get a site reviewed.

Common questions

What tax incentives does Alabama offer data centers?

Alabama lets eligible data processing centers abate certain sales and use taxes and property taxes under a program dating to 2012.12 HB399, enacted in April 2026, caps abatements at 20 years, requires 100 MW+ centers to pay certain purchase taxes from 2027, and adds a community development investment requirement.4 Terms are negotiated, so confirm them with the state and local governments involved.

Does the Alabama PSC review data center power contracts?

Yes, for the largest loads. Act 2026-610, effective October 1, 2026, defines large load data centers as at least 150 MW of peak demand, and the PSC has opened a proceeding to set standards for Alabama Power’s contracts with them.3 The first filed contract is public only in part.1

Is north Alabama served by Alabama Power or TVA?

Much of north Alabama is served by local power companies that buy wholesale power from TVA, such as Decatur Utilities. TVA reviews contracts above 5 MW, and requests above 100 MW need TVA board approval.2 Confirm the territory for each parcel, because boundaries do not follow county lines.

Do Alabama data centers need a water permit?

Alabama uses a registration system: users that can withdraw 100,000 gallons per day or more must register with the Office of Water Resources and obtain a Certificate of Use.9 Municipal supply contracts and local approvals may add their own conditions.

Why was the Bessemer data center controversial?

The city council rezoned nearly 700 acres of farmland for a $14.5 billion hyperscale campus on a 5–2 vote, despite concerns about power rates, water supply and permanent jobs.5 A lawsuit seeking more disclosure about the decision was dismissed in June 2026.8

Notes

  1. 1.WBRC, “Public can read Alabama Power’s data center contract, just not parts that could affect bill,” 2026. wbrc.com
  2. 2.Yahoo News, “TVA keeps an eye on data center proposals,” n.d. yahoo.com
  3. 3.NBC 15, “Alabama PSC opens review of data center power contracts, sets August comment deadlines,” 2026. mynbc15.com
  4. 4.LegiScan, “AL HB399, 2026 Regular Session,” 2026. legiscan.com
  5. 5.WBHM, “Bessemer City Council approves rezoning for a massive data center, dividing a community,” 2025. wbhm.org
  6. 6.Inside Climate News, “Alabama Power Gets Approval to Buy $622 Million Natural Gas Plant, Expecting More Data Centers,” 2025. insideclimatenews.org
  7. 7.WSMV, “TVA approves 10% rate spike for data centers to protect household rate payers,” 2026. wsmv.com
  8. 8.WBRC, “Bessemer data center rezoning lawsuit dismissed,” 2026. wbrc.com
  9. 9.Alabama Department of Economic and Community Affairs, “Water Management,” n.d. adeca.alabama.gov
  10. 10.WBRC, “Alabama Senate bills target data center incentives, utility regulation,” 2026. wbrc.com
  11. 11.Route Fifty, “Proposed data centers could use more electricity than all Alabama homes combined, analysis shows. Who will pay?,” 2026. route-fifty.com
  12. 12.Area Development, “Credit & Incentive Trends in Landing a Data Center,” 2017. areadevelopment.com
  13. 13.WBRC, “Alabama weighs cutting data center tax breaks as other states question the return,” 2026. wbrc.com
  14. 14.Trade & Industry Development, “AL: Google Kicks Off Construction on $600M Jackson County Data Center,” n.d. tradeandindustrydev.com
  15. 15.Business Alabama, “As data centers boom, some Alabama cities say, ‘wait a minute’,” 2026. businessalabama.com
  16. 16.Trade & Industry Development, “AL: Meta to Expand Montgomery Data Hub, Pushing Total Investment to More Than $1.5 Billion,” n.d. tradeandindustrydev.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Related guides

More in Site selection by state