Data Center Site Selection in the Southeast

Most of the Southeast is served by vertically integrated utilities outside an RTO, so a data center’s power path runs through one utility’s resource plan, transmission system and state-approved terms. Regulators are now writing large-load rules: Georgia set special terms for loads over 100 MW in 2025 and certified about 9.9 GW of new resources, and TVA created a separate data center rate class effective October 2026.123 Land and water are generally more available than in the West, but heat, storms, karst and interstate water disputes still shape which sites work.4

Last reviewed · 9 min read · BlackForge Data Centers

Key takeaways

  • Outside the parts that sit in PJM or MISO, the Southeast is largely served by vertically integrated utilities without an organized wholesale market.
  • New supply for large loads runs through resource plans and state review: Georgia regulators approved 9,885 MW for Georgia Power in December 2025, and Duke Energy’s 2025 Carolinas plan is before North Carolina regulators.56
  • Large-load terms are tightening: Georgia adopted a 100 MW rule,1 Duke uses a staged letter-agreement process,7 and TVA created new data center rates, each shifting cost and risk to the new load.3
  • Territory rules vary by state; in Georgia, new loads of 900 kW or more outside city limits get a one-time choice of supplier, but most states assign one utility.89
  • Atlanta led North America in data center construction in the first half of 2026, with about 2.9 GW underway.10
Public data · Power trackerLarge-load power tracker39 utilities and their data center power rules, from public filings.

01How power is organized in the Southeast

For this guide, the Southeast means roughly Georgia, Alabama, the Carolinas, Florida, Tennessee and neighboring areas. Most of it is not in an ISO or RTO. Vertically integrated utilities own generation, transmission and distribution, operate as or within balancing authorities, and plan their systems under state commission oversight. Parts of the wider South sit in organized markets: Virginia and some neighboring areas in PJM, and parts of Mississippi, Louisiana and Arkansas in MISO. Our guides to site selection in PJM and MISO cover those areas.

The utility mix is broad. Large investor-owned utilities serve many metro and suburban areas. Electric membership cooperatives cover large rural territories, often buying power from generation and transmission cooperatives. Municipal utilities serve many towns. In the Tennessee Valley, the federal Tennessee Valley Authority generates and transmits power that local power companies distribute, and reporting on TVA’s 2026 rate change notes that nearly all data centers in the Valley connect through those local providers.11 See utility ownership types for how each model makes decisions.

Common utility structures in the Southeast
StructureWho decides on a large loadWhat to ask early
Investor-owned, vertically integratedUtility, with state commission review of contracts and new generationIs new generation needed, and how long will approval take?
Distribution cooperativeCo-op board and its generation and transmission supplierCan the supplier serve a load far larger than the co-op’s current peak?
Municipal utilityCity or public power agency, plus its wholesale supplierWho supplies wholesale power, and can that contract grow?
TVA with local power companiesTVA and the local power company together; TVA can also serve some loads directly11Which data center rate class applies, and what capacity charge?

02Resource planning and new supply for large loads

Without a wholesale market to signal new supply, vertically integrated utilities add generation through integrated resource plans and, in many states, certificates or similar approvals. When data center demand arrives faster than the plan anticipated, the utility may need to file for new generation or contracts before it can commit to serving the load. That review takes time and is public.

Georgia shows the scale. Georgia Power’s pipeline of large-load development projects grew from about 12 GW to 36.5 GW during 2024.12 In December 2025 the Georgia Public Service Commission voted 5–0 to approve a stipulated agreement letting the utility add 9,885 MW of gas, battery storage, solar with storage and purchased power, mostly to serve large customers.52 The agreement says data center service costs are not to be passed to existing customers, and the commission kept room to revisit certification if data center contracts are not signed. Commission staff had raised concerns about stranded assets if demand failed to appear.2

In the Carolinas, Duke Energy filed its 2025 Carolinas Resource Plan with the North Carolina Utilities Commission on October 1, 2025, citing growth and the need to modernize the system.6 Commissioners have said publicly that they want to avoid over-forecasting and overbuilding for load that never arrives, which is a reminder that a utility’s forecast is not a commitment to your project.13 State guides for Georgia and North Carolina cover the local detail.

Fig. 1Large-load growth in the Southeast

Georgia Power large-load pipeline, late 2024
36.5 GW
new Georgia Power resources approved, Dec. 2025
9,885 MW
under construction in Atlanta, H1 2026
2,882 MW
existing Atlanta inventory, H1 2026
~1,803 MW
Georgia figures from regulators and trade press;125 Atlanta figures from CBRE’s H1 2026 report as reported by WSB-TV.14 Pipelines include projects that may never be built.

03Large-load contracts and rates

Large-load terms in the region are meant to protect other customers from stranded costs, and they are getting stricter. Our guide to large-load tariffs and electric service agreements explains the common terms: long minimum terms, minimum monthly demand charges, collateral and exit fees. Three examples show the range:

  • Georgia: in January 2025 the commission unanimously adopted a rule for new Georgia Power customers above 100 MW. It allows billing based on project risk, requires these customers to cover transmission and distribution costs incurred during construction, and sends their contracts to the commission for review.1
  • Carolinas: Duke handles customers over 100 MW in stages, from an initial engagement and transmission study to a letter agreement and then an energy supply agreement, grouping requests into tranches much like a generator interconnection cluster. The letter agreement carries financial commitments before the final contract.7
  • Tennessee Valley: TVA’s board approved a separate data center rate class on August 20, 2026, effective October 1 and phased in over three fiscal years, with an expected average bill impact of about 10%. New or expanding data centers above 5 MW also face a capacity commitment charge of about $1.5 million per MW, paid over three to five years.311

Fig. 2Duke Energy’s large-load path in the Carolinas

  1. 01

    Initial engagement

    Customer submits the load request.

  2. 02

    Transmission study

    Requests are studied in tranches.

  3. 03

    Letter agreement

    Financial commitments before a final contract.

  4. 04

    Energy supply agreement

    Final service contract for the load.

Simplified from Duke’s North Carolina filings for customers over 100 MW; financial obligations begin at the letter agreement.7

These terms vary by utility and change through commission proceedings, so read the current filing for the specific utility, not the region. Clean-energy options in regulated states usually come through utility programs rather than open-market contracts. The Tennessee guide covers TVA’s structure in more depth.

04Territory rules and how interconnection works

Retail service in the Southeast is assigned by utility service territory, and territorial laws differ by state. Georgia is the best-known exception: under its Territorial Electric Service Act, a new load of 900 kW or more at initial full operation, located outside municipal limits, may be served by any supplier.8 Cooperatives describe this as a one-time choice.9 Separately metered loads cannot be aggregated to reach the threshold, according to a Georgia court ruling cited in commission records.15 Most other states assign each location to one utility, and territory lines can split a tract, which can change the power path entirely.

Interconnection is utility-led. The utility studies the load against its transmission system, scopes the substation and line work, and sets the cost and schedule. Larger campuses typically connect at 115 to 230 kV, and sometimes 500 kV, depending on the system. Because one entity owns generation and transmission, the answer can come faster than in a multi-party RTO process, but it depends entirely on that utility’s capacity and priorities.

05Climate and natural hazards

Heat and humidity are the main climate factors. Long, humid summers reduce the hours when outside air can cool a facility directly, which raises cooling energy and favors designs that rely less on economization. See our guide to climate and cooling in site selection for how that plays into design.

  • Hurricanes and storm surge along the Atlantic and Gulf coasts, plus inland flooding from tropical rainfall well away from the coast. See hurricane and storm surge risk.
  • Tornadoes and severe thunderstorms, with frequent lightning.
  • Karst geology and sinkholes in parts of Florida, Tennessee, Alabama and Georgia, which need geotechnical review. See karst and sinkholes.
  • Large areas of mapped floodplain along rivers in the coastal plain and Piedmont.

06Water supply and permits

The Southeast generally has more rainfall and surface water than the West, but water is not simple. States regulate surface and groundwater withdrawals differently, and coastal aquifers can face saltwater intrusion limits. Some river basins carry long interstate disputes. In the Apalachicola-Chattahoochee-Flint basin, the U.S. Army Corps of Engineers adopted water control plan updates in early 2025 that reflect a court-mediated settlement between Georgia and Alabama, protecting metro Atlanta’s supply from Lake Lanier while setting flow objectives downstream.4 Alabama then dropped its appeal, ending a major part of the litigation.16

At the site level, municipal systems may have capacity for a closed-loop design but not for heavy evaporative cooling, and discharge of cooling water blowdown needs a permit or a utility agreement. Reclaimed water from municipal treatment plants is an option in some areas. Our guide to municipal water and sewer capacity covers what to ask the provider.

07Land, entitlement and fiber

Large tracts of timberland and farmland are available in much of the region, and states and local economic development groups often prepare industrial sites in advance. CBRE attributes Atlanta’s construction lead partly to tax incentives, labor availability and rural development opportunities, with gigawatt-scale campuses announced in South Georgia and other rural areas.10 Zoning ranges from detailed ordinances in metro counties to limited zoning in some rural ones, and local opposition over water and electricity rates has grown. Wetlands are common in the coastal plain and along river bottoms, so a Section 404 screen belongs early in the review.

Fiber density centers on a few metro hubs, with Atlanta the most significant interconnection point in the region, and subsea cable landings on the Atlantic coast and in Florida. Long-haul routes follow interstates and rail lines. Rural sites need a realistic path to two diverse long-haul routes; see long-haul and subsea fiber routes.

08A Southeast site checklist

  1. 01Confirm the serving utility and whether state territory rules, such as Georgia’s 900 kW provision, give the load any choice.
  2. 02Ask whether serving the load requires new generation filings and where the utility’s current resource plan stands.
  3. 03Read the utility’s current large-load terms: minimum term, minimum bill, collateral, exit fees and any capacity commitment charge.
  4. 04Screen flood, storm surge, karst and wetlands across the buildable area.
  5. 05Confirm water withdrawal, municipal capacity and discharge options for the cooling design, and any basin-level allocation limits.
  6. 06Map diverse fiber routes and the distance to the nearest metro interconnection point.

If you want an outside screen of a specific tract against these items, you can get a site reviewed.

CalculatorIT load to grid demand →CalculatorCooling water use →

Common questions

Is the Southeast part of an RTO?

Mostly not. Much of the Southeast is served by vertically integrated utilities that own generation, transmission and distribution and plan their systems under state commission oversight. Some parts of the broader South are in organized markets, including areas in PJM and MISO. Check the specific site, because the market structure affects how new supply is added and how power is priced.

How long does it take to get power for a data center in the Southeast?

It depends on the utility and whether the load fits within its existing resource plan. If capacity is available, the timeline is driven by substation and line construction. If the load needs new generation, state approval comes first; Georgia’s 2025 certification, for example, covered resources planned for 2029 through 2031.2 Ask the serving utility directly what the load would trigger and when.

Can a data center choose its electric utility in the Southeast?

Usually not. Retail service is generally assigned by territory under state law. Georgia is an exception: new loads of 900 kW or more outside municipal limits can make a one-time choice of supplier.89 Retail choice of energy supplier, common in parts of the Northeast and Texas, is generally not available in the Southeast.

What changed in TVA’s data center rates?

TVA’s board created a separate data center rate class in August 2026, effective October 1 and phased in over three fiscal years. New or expanding data centers above 5 MW also face a capacity commitment charge of about $1.5 million per MW.3 Confirm the terms with the local power company and TVA for a specific site.

Does humidity in the Southeast affect data center design?

Yes. Hot, humid summers reduce the hours when outside air can be used for cooling, which raises cooling energy and can push designs toward mechanical or liquid cooling. Humidity also affects how much water evaporative systems consume. It rarely rules out a site, but it changes design choices, operating cost and the realistic PUE.

Notes

  1. 1.Data Center Dynamics, “Georgia PSC approves new billing rules for data centers and large load customers,” 2025. datacenterdynamics.com
  2. 2.Bisnow, “Georgia Power Secures PSC Approval For Historic 10 GW Expansion Amid Opposition,” 2025. bisnow.com
  3. 3.256 Today, “TVA board approves higher power rates for data centers,” 2026. 256today.com
  4. 4.Atlanta Regional Commission, “ARC celebrates landmark ACF agreement following U.S. Army Corps of Engineers adoption of water control plan updates,” 2025. atlantaregional.org
  5. 5.T&D World, “Georgia PSC Approves Stipulated Agreement for New Power Generation Capacity,” 2025. tdworld.com
  6. 6.Duke Energy, “Duke Energy files 2025 Carolinas Resource Plan, continues modernizing energy infrastructure to support future growth,” 2025. investors.duke-energy.com
  7. 7.Nelson Mullins, “Developments on How Duke Energy Integrates Data Centers and Other New Large Load Customers in North Carolina,” 2025. nelsonmullins.com
  8. 8.City of Marietta, “Commercial Customers,” n.d. mariettaga.gov
  9. 9.Jackson EMC, “Customer Choice,” n.d. jacksonemc.com
  10. 10.CBRE, “North America Data Center Trends H1 2026,” 2026. cbre.com
  11. 11.Louisville Public Media, “TVA will consider a new electricity rate for data centers this week,” 2026. lpm.org
  12. 12.Data Center Frontier, “Georgia Follows Ohio’s Lead in Moving Energy Costs to Data Centers,” 2025. datacenterfrontier.com
  13. 13.WFAE, “NC energy experts push for transparency in data center development,” 2025. wfae.org
  14. 14.WSB-TV, “Atlanta now leads North America data center construction: report,” 2026. wsbtv.com
  15. 15.Georgia Public Service Commission, “Docket No. 28607,” n.d. services.psc.ga.gov
  16. 16.WABE, “Court dismissal ends major tri-state water wars lawsuit in Apalachicola-Chattahoochee Flint River Basin,” 2025. wabe.org

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.