Data Center Site Selection in ERCOT (Texas)

ERCOT runs the grid for more than 27 million customers and about 90% of Texas electric load, on a system not synchronously connected to the rest of the country, so data centers there depend on an intrastate market with its own regulator and large-load rules.1 Requests dwarf the system: ERCOT counted about 474 GW of large-load requests in June 2026, roughly 90% of them data centers, against a record peak of about 91 GW that July.23 Confirm the site is in ERCOT, identify the wires utility and budget for the study fee and security the PUCT adopted in September 2026.4

Last reviewed · 9 min read · BlackForge Data Centers

Key takeaways

  • Not all of Texas is in ERCOT: El Paso, parts of the Panhandle and parts of East Texas sit on other grids served by vertically integrated utilities.5
  • The grid trades with its neighbors only through DC ties, about 820 MW to SPP and 400 MW to Mexico, so it has to cover its own peaks.6
  • ERCOT has no centralized capacity market, so supply contracts and load flexibility shape power costs; real-time co-optimization began in December 2025.7
  • For loads of 75 MW or more, the PUCT’s September 2026 rule requires a $100,000 study fee and $50,000 per MW of security before studies begin.4
  • Large loads are now studied in batches, and Batch Zero deadlines slipped after an August 2026 directive to audit data centers in the queue.89
  • Heat, winter storms, drought and Gulf storms all belong in a Texas review; in February 2021 ERCOT ordered about 20,000 MW of rotating outages.10
Public data · Power trackerLarge-load power tracker39 utilities and their data center power rules, from public filings.

01The ERCOT footprint and how it is organized

The Electric Reliability Council of Texas (ERCOT) operates the grid and wholesale market for more than 27 million customers, about 90% of the state’s electric load, across more than 54,100 miles of transmission lines. Because it is not synchronously tied to grids beyond Texas, most oversight comes from the Public Utility Commission of Texas (PUCT) and the Legislature rather than FERC, although NERC reliability standards still apply.1

ERCOT trades power with its neighbors only through direct-current links, which let power cross between grids that are not in sync: two DC ties to the Southwest Power Pool totaling 820 MW, and a DC tie and a variable frequency transformer to Mexico totaling 400 MW.6 That is small next to ERCOT’s own load, so the system has to cover its own peaks.

Fig. 1ERCOT at a glance

customers served
27 million+
of Texas electric load
~90%
of transmission lines
54,100+ mi
of DC ties to SPP and Mexico
1,220 MW
ERCOT’s published figures as of 2025; DC tie capacity combines the ties to SPP and Mexico.16

Not all of Texas is in ERCOT. El Paso and far West Texas are in the Western Interconnection, while parts of the Panhandle and East Texas counties along the Oklahoma, Arkansas and Louisiana borders are in the Eastern Interconnection, served through SPP or MISO by vertically integrated utilities.5 A site near those edges should be checked against utility service territory maps before any other work. See our Texas, SPP and MISO guides.

02Market structure and retail service

Much of ERCOT has retail competition, which Texas opened with Senate Bill 7 in 1999. In those areas, transmission and distribution utilities own the wires and connect customers, while competitive retail providers sell the energy. Municipal utilities and electric cooperatives can stay out of the competitive market, and where they have, their customers cannot pick a supplier.11 A site in their territory usually buys bundled service from the local provider.

Service models a data center may encounter in ERCOT
Area typeWho connects the siteWho sells the energyWhat to check
Competitive areaTransmission and distribution utilityCompetitive retail provider, or direct wholesale arrangementsWires utility’s large-load process; supply contract structure
Municipal utility territoryCity-owned utilityUsually the municipal utilityLocal policies, capacity and appetite for large loads
Cooperative territoryCooperative and its transmission providerUsually the cooperative or its supplierCo-op board policies, wholesale supply arrangements

This structure gives large buyers more ways to procure energy than in many regulated states, including contracts tied to specific generation. It also means more parties to coordinate. Our comparison of regulated utility vs. competitive market sites explains the trade-offs.

03Resource adequacy in an energy-only market

ERCOT was built as an energy-only market, without a centralized capacity market like PJM’s. Generators earn revenue mainly from selling energy and ancillary services, and scarcity pricing during tight hours is meant to signal the need for new supply. The design keeps changing. On December 5, 2025, ERCOT launched real-time co-optimization plus batteries, which clears energy and ancillary services together every five minutes, with batteries part of the optimization.7

ERCOT set a new hourly record above 91 GW on July 22, 2026, at about 6 p.m. Central, with natural gas supplying about 48% of output and solar about 32%.3 Prices can swing sharply in heat waves, cold snaps and low-renewable hours, so large loads manage exposure through supply contracts, hedges and, in some cases, by agreeing to reduce demand when the grid is stressed. A data center that can curtail part of its load, or switch to on-site generation, has options a fully inflexible load does not. See grid power vs. on-site generation and flexible data center loads.

04How large-load interconnection works in ERCOT

A data center applies to the transmission service provider that serves its location. That provider studies the connection, and ERCOT reviews large loads for their effect on the wider system. Senate Bill 6, a 2025 law, directed the PUCT to set statewide large-load standards, and on September 18, 2026, the commission adopted a rule for loads of 75 MW or more at one site.4 The final rule sets a flat $100,000 study fee, dropping the non-refundable per-MW fee in the March draft, and requires $50,000 per MW of requested capacity to be posted as security before interconnection studies begin.12 For a 300 MW campus, that is $15 million committed before the first study. Our Texas Senate Bill 6 guide covers the statute.

  • Expect studies that look at both the local connection and system-wide effects.
  • Expect questions about load behavior: how fast it ramps, how it rides through faults and whether it can curtail.
  • Rules for loads co-located with generation have changed too; the general steps are in our guide to the large-load interconnection process.

Batch Zero and the 2026 audit

ERCOT told the Texas Senate in July 2026 that its large-load pipeline had reached about 474 GW, roughly 90% of it data centers, and that about 205 GW was eligible for the first batch study.2 The PUCT approved that Batch Zero framework on June 18, 2026, through protocol revisions NPRR 1325 and PGRR 145. Instead of studying requests first come, first served, ERCOT studies eligible loads of 75 MW or more together, so transmission needs can be sized for the group.8

Fig. 2ERCOT large-load requests vs. peak demand

  • Record peak, July 22, 2026~91 GW
  • Eligible for Batch Zero~205 GW
  • All large-load requests, June 2026~474 GW

GW

Requests are not forecasts, and many will never be built. Queue figures from ERCOT’s July 2026 Senate testimony; peak from EIA.23

On August 3, 2026, Governor Abbott directed the PUCT and ERCOT to verify every data center in the interconnection process before more advance, and asked developers to disclose projected annual and peak power use and on-site generation plans.13 On August 20, the PUCT approved ERCOT’s request to push back key Batch Zero deadlines.9 Budget time for that review, and confirm current deadlines with the utility and ERCOT.

Fig. 3A large load’s path to power in ERCOT

  1. 01

    Confirm grid and utility

    Is the site in ERCOT, and which wires utility, co-op or city serves it?

  2. 02

    Request and study fee

    Site control and a $100,000 study fee for loads of 75 MW or more.

  3. 03

    Post security

    $50,000 per MW of requested capacity before studies begin.

  4. 04

    Batch study

    ERCOT studies eligible loads together and allocates capacity.

  5. 05

    Agreement and build

    Interconnection agreement, then lines, substation and metering.

Simplified from the PUCT’s 2026 rule and ERCOT’s batch process.48 Deadlines moved after the August 2026 audit.9

05Typical constraints in Texas

  • Transmission between generation and load. Much wind and solar generation sits in West and South Texas, far from the large metros, and oil and gas demand in the Permian Basin has outgrown the region’s delivery system. In April 2025 the PUCT approved three 765 kV import paths for the Permian Basin, the first lines at that voltage in ERCOT.14 Sites near generation can benefit from that supply but may sit behind export or import constraints until new lines are built.
  • Heat. Long, hot summers raise cooling loads and design PUE, and late-afternoon summer peaks are when the grid is tightest.
  • Cold events. During the February 2021 winter storm, ERCOT ordered about 20,000 MW of rotating outages to avoid a grid collapse, the largest manually controlled load shed in U.S. history.10 Resilience plans, backup fuel and freeze protection should cover both seasons.
  • Water. Much of West and Central Texas is dry. Groundwater follows the rule of capture unless a local groundwater conservation district limits pumping through permits, so the rules differ from place to place.15 A January 2026 HARC study estimated that Texas data centers used about 25 billion gallons in 2025 and could use 29 to 161 billion gallons a year by 2030, with demand clustered in already stressed watersheds.16 See water rights and groundwater.
  • Coastal storms and flooding. The Gulf Coast carries hurricane and storm surge exposure, and flat terrain can mean broad floodplains inland too.
  • Oil and gas activity. Parts of the state have active or abandoned wells, pipelines and severed mineral rights that affect layout and title.

Fig. 4Two common Texas site profiles

Power-rich

West Texas, near generation

  • Close to wind and solar generation and gas supply
  • Planned 765 kV import paths, approved in 2025
  • Dry climate; groundwater rules vary by district
  • Long fiber laterals to reach diverse routes

Network-rich

Metro edge

  • Dense fiber around Dallas–Fort Worth, Houston, Austin and San Antonio
  • More competing load on each substation
  • City limits, annexation and utility service areas to check
  • Gulf Coast sites add hurricane and flood exposure
General patterns, not rules; individual sites vary widely.14

06Land, fiber and entitlement tendencies

Texas has large tracts of land and, outside cities, many counties have limited land-use regulation compared with other states. That can shorten approvals, but it also means fewer predictable rules, and city annexation or extraterritorial jurisdiction can change what applies. Check which jurisdiction controls the site and whether it might change, since annexation can also shift which utility provides water and sewer. Our guide to annexation and utility service areas explains what to ask.

Fiber is strongest in and between the major metros, such as Dallas–Fort Worth, Houston, Austin and San Antonio, and along interstate corridors. Rural sites, including those near West Texas generation, may need long laterals to reach diverse routes.

Light county rules do not mean light scrutiny. Large projects still need road access agreements, floodplain and stormwater approvals and, for on-site generation, air permits. Ask the county, any nearby city and the groundwater district early.

07What to check for a site in ERCOT

  1. 01Confirm the site is inside ERCOT and identify the serving utility, co-op or municipal provider.
  2. 02Ask the transmission provider for the current large-load requirements, including the study fee, security and site-control evidence.
  3. 03Find out which batch window the project would fall in and how the 2026 audit affects its timeline.
  4. 04Map nearby transmission, known export or import constraints and planned 765 kV lines.
  5. 05Decide how energy will be procured and whether the load can offer any flexibility.
  6. 06Check water supply and the local groundwater district’s rules.
  7. 07Screen for flood exposure, storm risk, oil and gas features and mineral rights, and confirm the land-use jurisdiction and fiber options.

Rules are still settling in 2026, so confirm current terms with the utility, ERCOT and Texas regulatory counsel before committing security. If you have a tract in Texas, you can get a site reviewed.

CalculatorIT load to grid demand →CalculatorCooling water use →

Common questions

Is all of Texas on the ERCOT grid?

No. ERCOT covers most of the state, but El Paso is in the Western Interconnection, and parts of the Panhandle and East Texas are in the Eastern Interconnection through SPP or MISO, served by vertically integrated utilities.5 For any Texas site, confirm the serving utility and its grid region before evaluating power availability.

Why is ERCOT attractive for data centers?

ERCOT offers large land tracts, a fast-growing generation fleet and a competitive market with many ways to procure energy, and many areas have light land-use regulation. The trade-offs include a crowded queue, wholesale price volatility, extreme weather at both ends of the year and water limits in drier areas. About 474 GW of large-load requests in mid-2026 shows how many developers reached the same conclusion.2

Does ERCOT have a capacity market?

No. ERCOT was designed as an energy-only market, so generators rely mainly on energy and ancillary service revenue, with scarcity pricing during tight periods. Since December 2025, energy and ancillary services have been co-optimized in real time.7 For data centers, power cost and risk depend heavily on supply contracts and the ability to manage price swings.

How much does it cost to request a large-load connection in ERCOT?

Under the PUCT’s September 2026 rule, a load of 75 MW or more pays a flat $100,000 study fee and posts $50,000 per MW of requested capacity as security before studies begin.12 Utility facility costs and any required contribution to the connection come on top, so ask the transmission provider for a full estimate.

Can a data center in ERCOT reduce load to help the grid?

Often, yes. Large loads in ERCOT can take part in programs that pay them to reduce demand during grid stress, and large-load rules may require some curtailment capability. Facilities running interruptible batch or training work have more room to curtail than those serving real-time customers.

Notes

  1. 1.Electric Reliability Council of Texas, “ERCOT Fact Sheet,” 2025. ercot.com
  2. 2.Electric Reliability Council of Texas, “ERCOT Senate July 29 Panel 1: Assessing the Grid,” 2026. ercot.com
  3. 3.U.S. Energy Information Administration, “Hourly peak load in ERCOT set a new record exceeding 91 GW on July 22,” 2026. eia.gov
  4. 4.White & Case, “PUCT sets financial commitments for data center interconnection as governor pauses permit approvals,” 2026. whitecase.com
  5. 5.Texas Comptroller of Public Accounts, “Electric Reliability Council of Texas (ERCOT),” 2023. comptroller.texas.gov
  6. 6.Electric Reliability Council of Texas, “ERCOT Grid Insights: Electricity Connection and Transfer,” 2025. ercot.com
  7. 7.American Public Power Association, “Texas grid operator goes live with real-time co-optimization plus batteries,” 2025. publicpower.org
  8. 8.Sheppard Mullin, “PUCT Approves Batch Zero Framework That Will Provide a Pathway for Large Load to Connect to the Grid and Receive Electricity,” 2026. sheppard.com
  9. 9.Octus, “Public Utility Commission of Texas Approves ERCOT’s Batch Zero Deadline Extensions,” 2026. octus.com
  10. 10.Federal Energy Regulatory Commission, “Final Report on February 2021 Freeze Underscores Winterization Recommendations,” 2021. ferc.gov
  11. 11.Electric Reliability Council of Texas, “ERCOT Grid Insights: Retail Market,” 2025. ercot.com
  12. 12.Utility Dive, “Texas PUC adopts data center interconnection rules,” 2026. utilitydive.com
  13. 13.Office of the Texas Governor, “Governor Abbott Directs Comprehensive Data Center Audit,” 2026. gov.texas.gov
  14. 14.T&D World, “PUCT Approves Development of First Extra High Voltage Transmission Lines in ERCOT Region,” 2025. tdworld.com
  15. 15.The Texas Tribune, “The one thing Texas won’t do to save its water supply,” 2025. www2.texastribune.org
  16. 16.Houston Advanced Research Center, “Texas Data Center Boom Could Consume Up to 161 Billion Gallons of Water Annually by 2030,” 2026. harcresearch.org

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.