A BlackForge Ventures company
BlackForge Data Centers

Grid regions

Data Center Site Selection in MISO

MISO runs the grid and wholesale market for about 45 million people in all or parts of 15 states and Manitoba, from the Upper Midwest to the Gulf Coast,1 and most large loads there are served by state-regulated, vertically integrated utilities. That makes the utility’s resource plan, tariffs and appetite for large loads the center of any site review, while FERC’s June 2026 show-cause order and MISO’s new fast-track studies reshape the regional rules.23 Summer capacity for 2026/27 cleared at $424.30/MW-day in the north and central zones, down from $666.50 the year before.4

Last reviewed · 10 min read · BlackForge Data Centers

Key takeaways

  • MISO spans 15 states and Manitoba, and its north and south differ in climate, hazards and capacity prices.14
  • Most customers are served by vertically integrated utilities under state regulation, so how the utility would supply the load matters as much as the connection.
  • For 2026/27, summer capacity cleared at $424.30/MW-day in zones 1–7 and $384.10 in zones 8 and 10, after $666.50 across all zones in 2025/26.4
  • FERC ordered MISO in June 2026 to justify or reform its large-load rules; MISO sought more time, which could push its filing to mid-November 2026.25
  • Utilities plan about 15 GW a year of new accredited summer capacity, led by natural gas, with about 4 GW a year expected through MISO’s expedited study lane.6
  • Sites near PJM or SPP need extra care about which utility and RTO would serve them, and Great Lakes sites face basin water rules.7
Public data · Power trackerLarge-load power tracker39 utilities and their data center power rules, from public filings.

01The MISO footprint and how it is organized

The Midcontinent Independent System Operator (MISO) runs the transmission system and wholesale market for all or parts of Arkansas, Illinois, Indiana, Iowa, Kentucky, Louisiana, Michigan, Minnesota, Mississippi, Missouri, Montana, North Dakota, South Dakota, Texas and Wisconsin, plus Manitoba in Canada. It serves about 45 million people across about 79,000 miles of transmission lines.1 It is part of the Eastern Interconnection and is regulated by FERC for its U.S. operations.

The footprint is often discussed in two broad parts: a northern and central region across the Upper Midwest and Great Lakes, and a southern region in Arkansas, Louisiana, Mississippi and part of East Texas. They are connected, but they clear at different capacity prices and have different generation mixes, climates and hazards.4 Within both, service comes from investor-owned utilities, cooperatives and municipal utilities. See ISO and RTO markets for the role of RTOs.

Fig. 1MISO’s north and south at a glance

Zones 1–7

North and Central

  • Summer capacity: $424.30/MW-day
  • Cool climate supports efficient cooling
  • Great Lakes Compact bars most out-of-basin diversions
  • 765 kV backbone planned under Tranche 2.1

Zones 8–10

South

  • Arkansas, Louisiana, Mississippi and part of East Texas
  • Summer capacity: $384.10–$412.10/MW-day
  • Hot, humid summers
  • Hurricane, storm surge and river flood exposure
General patterns. Capacity prices are summer 2026/27 auction results by zone;4 the Compact and Tranche 2.1 are covered below.78

02Market structure and retail service

Most of MISO’s states kept vertically integrated utilities. The utility owns or contracts for generation, owns transmission and distribution, and sells bundled service at rates set by the state utility commission. A few states allow limited retail choice. For most data center sites in MISO, the local utility is both the connection provider and the energy supplier. See regulated utility vs. competitive market sites.

That has practical effects. Large-load terms come through the utility’s tariffs and special contracts, approved by state regulators. New generation to serve a large load usually goes through the utility’s resource planning and state review. A utility that wants the load can be an active partner, while one that is cautious can slow everything down. See large-load tariffs and our Wisconsin and Louisiana guides for two MISO examples.

Comparing how large-load service tends to work in MISO, PJM and ERCOT
ElementMISOPJMERCOT
Typical retail modelMostly vertically integrated, state-regulatedMix of retail choice and vertically integratedRetail choice in much of the area; co-ops and municipals often bundled
Resource adequacyUtility planning plus a seasonal MISO auctionCentralized forward capacity market plus state policyEnergy-only design with added reliability services
Who connects the loadLocal utility or transmission ownerLocal utility or transmission ownerTransmission service provider, with ERCOT review
Main regulator for wholesaleFERCFERCState commission (PUCT)

03Resource adequacy and capacity prices

In MISO, utilities and their state regulators carry the main responsibility for having enough generation. MISO sets reserve requirements and runs an annual Planning Resource Auction that lets load-serving entities meet or balance their resource adequacy obligations. The auction now clears each season separately, and many utilities meet most of their needs through their own plants and contracts, using the auction at the margin.

Prices have swung. Summer capacity cleared at $666.50/MW-day across all zones for 2025/26. For the 2026/27 planning year, summer cleared at $424.30 in the north and central zones, $412.10 in zone 9 and $384.10 in zones 8 and 10, while fall, winter and spring prices were far lower.4 Offers rose to about 141 GW from about 136 GW the year before, which helped pull prices down.9 Data centers usually feel these prices through utility rates.

Fig. 2MISO summer capacity prices

  • 2025/26, all zones$666.50
  • 2026/27, zones 1–7$424.30
  • 2026/27, zone 9$412.10
  • 2026/27, zones 8 and 10$384.10

$/MW-day

Summer-season clearing prices in MISO’s Planning Resource Auction; other seasons cleared far lower.4

A large new load changes a utility’s resource plan. The utility may need new generation, longer life for existing plants or new contracts, and those choices often need state approval. That can add time, and it can lead the utility to ask the data center for long-term commitments, minimum bills or help funding new resources. Asking early how the utility would supply the load, not just connect it, is one of the most useful steps in MISO.

04How much new load and supply MISO expects

The annual OMS-MISO survey of load-serving entities found in 2026 that members plan to add about 15 GW of new accredited summer capacity a year, up from as much as 8.6 GW a year in the prior survey, with natural gas the largest share. Members projected five-year load growth of 3.1% to 5.1% a year, based on their forecasts and requests for new load.6

On November load forecasts, the survey showed capacity above the planning reserve requirement growing from 11.5 GW in summer 2028 to 39 GW in summer 2031; on April forecasts the margins were significantly smaller. MISO cautioned that 87 GW of resources with signed interconnection agreements but not yet built may not all materialize, and that reliability risk is shifting from summer toward winter.6

To speed new supply, MISO runs an Expedited Resource Addition Study (ERAS). Its first cycle, in 2025, covered ten projects totaling about 5.3 GW, with in-service dates from January 2027 to August 2028,10 and a third cycle announced in March 2026 covered 15 more projects.11 The survey expects about 4 GW a year of planned additions to come through that lane.6 That can let a utility add generation for a new load faster than the standard queue allows.

05How large-load interconnection works in MISO

A data center applies to the local utility or transmission owner, which studies the connection and coordinates with MISO on transmission effects. MISO’s regional planning process includes forecast loads and can identify upgrades. Loads do not use the generator queue, though any grid-connected on-site generation may.

  • Upgrade costs may fall to the customer, the utility’s ratepayers or a regional allocation, depending on the upgrade and the applicable tariff. See transmission upgrades and cost allocation.
  • Utilities may tie service to an approved resource plan for the new load.
  • Cooperatives often rely on a generation and transmission cooperative for supply, which adds a party to the conversation.

Fig. 3A large load’s path to power in MISO

  1. 01

    Find the utility and RTO

    Serving utility, co-op or city, and the RTO it plans in.

  2. 02

    Load study

    The utility studies the connection with MISO.

  3. 03

    Supply plan

    New generation or contracts, often needing state approval.

  4. 04

    Service agreement

    Large-load tariff or contract, with minimum bills and collateral.

  5. 05

    Build and energize

    Lines, substation and metering, then energization.

Simplified; steps and timing vary by utility, and FERC’s 2026 proceeding may add regional requirements.2

FERC’s 2026 review of large-load rules

On June 18, 2026, FERC issued show-cause orders to all six FERC-jurisdictional RTOs and ISOs, using as a preliminary benchmark new commercial or industrial loads of 50 MW or more connecting above 69 kV.12 The MISO order, in Docket EL26-70, preliminarily found gaps in MISO’s tariff: no adequate large-load definition, unclear application and study procedures, thin ongoing operating requirements and no pro forma service agreement terms.213 MISO asked FERC in August to hold its case in abeyance while it prepares filings; if FERC agrees, MISO’s response would be due in mid-November 2026.5 No ruling on that request had been reported as of early October 2026.

MISO has also asked FERC to approve a faster lane for loads that bring their own supply: a process that studies a large load and the generation serving it together, aiming for an answer in about 120 days. As filed, it is open to loads larger than 200 MW paired with generation in the same resource zone, with a firm offtake contract and control of the generation site, and MISO asked FERC to rule by December 2.3 A separate zero-injection agreement, filed in August 2026, would let generation paired with nearby load connect on the condition that it never exports net energy to the grid.14 See co-locating data centers with power plants.

06Seams with PJM and SPP, and the transmission build-out

MISO borders PJM to the east and SPP to the west, and the borders are irregular. In some states, neighboring counties, or even neighboring tracts, are served by utilities in different RTOs. Transmission flows across these seams, and upgrades on one side can depend on studies on the other.

For a site near a seam, confirm the serving utility and its RTO early. A line visible from the property may belong to a different system than the one that would serve the load. Our guides to PJM and SPP cover the neighboring regions.

MISO’s long-range plan will also change where capacity is available. In December 2024 MISO’s board approved the $21.8 billion Tranche 2.1 portfolio, built around a 765 kV backbone across the Midwest.8 Treat those lines as a future option for a site, not a present one.

07Climate, water, land and other constraints

  • Climate. Northern areas have cool climates that support efficient cooling and lower design PUE. Southern areas are hot and humid for much of the year.
  • Water. The Great Lakes and major rivers provide significant water. Since 2008 the Great Lakes Compact has generally banned diversions outside the basin, with narrow exceptions for straddling communities and counties, and states regulate withdrawals inside it.7 In Wisconsin’s part of the basin, withdrawals above 100,000 gallons a day need a state permit, but a data center that buys city water falls under the utility’s permit rather than its own.15 See water rights and groundwater.
  • Hazards. Southern areas carry hurricane, flood and storm surge exposure. The central footprint has tornado and severe storm risk, and parts of the Mississippi Valley have seismic and river flood exposure.
  • Land. Much of the footprint is agricultural, with large, flat tracts. Converting farmland can raise local concerns and, in some states, specific review. Check any state farmland preservation programs, drainage district obligations and easements that run with the land.
  • Fiber. Metro areas and interstate corridors have good fiber; rural sites may need long laterals for diverse routes.

08What to check for a site in MISO

  1. 01Identify the serving utility, its RTO and whether the site sits near a seam with PJM or SPP.
  2. 02Ask how the utility would supply the load, not just connect it, and whether new generation needs state approval or could use MISO’s expedited study.
  3. 03Learn the utility’s large-load tariff, contract terms and required commitments, and how capacity costs reach the bill.
  4. 04Ask how FERC’s 2026 large-load proceeding could change study steps or service terms.
  5. 05Map nearby transmission and substations, including Tranche 2.1 projects, and ask about pending large loads.
  6. 06Check water supply and any basin or state withdrawal rules.
  7. 07Screen for flood, storm and seismic exposure, especially in the south and along major rivers, and confirm local zoning and fiber options.

When we screen sites in MISO, the utility conversation tends to set the timeline more than the transmission map does. If you have a tract in the footprint, you can get a site reviewed.

CalculatorIT load to grid demand →CalculatorCooling water use →

Common questions

What states are in MISO?

MISO covers all or parts of 15 states, from North Dakota, Minnesota and Michigan south to Louisiana, Mississippi and part of East Texas, plus the Canadian province of Manitoba. Several are split between MISO and neighboring regions such as PJM or SPP, so confirm the serving utility and RTO for any specific site.

How do data centers get power in MISO?

Usually through a vertically integrated utility regulated by the state. The utility studies the connection with MISO, provides the substation and transmission service, and supplies the energy under a large-load tariff or special contract approved by regulators. If the load needs new generation, the utility’s resource planning and state approvals become part of the timeline.

Does MISO have a capacity market?

Yes, in a different form from PJM’s. MISO’s annual Planning Resource Auction sets seasonal prices, but utilities and state regulators carry the main responsibility for resource adequacy. For 2026/27, summer capacity cleared at $384.10 to $424.30/MW-day, depending on the zone.4 For a data center, the utility’s resource plan usually matters more than auction results.

How is FERC changing large-load interconnection in MISO?

In June 2026, FERC ordered MISO and the other FERC-jurisdictional grid operators to justify or reform their rules for large loads, using loads of 50 MW or more connecting above 69 kV as a preliminary benchmark.12 MISO sought more time, so its proposals may not be filed before mid-November 2026 and would then need FERC review.5

Notes

  1. 1.Cass County Electric Cooperative, “Meet MISO,” n.d. casscountyelectric.com
  2. 2.Akin Gump, “FERC Directs Midcontinent Independent System Operator to Revise Tariff to Expedite Data Center Development,” 2026. akingump.com
  3. 3.Utility Dive, “MISO large load and generation study (LARS) filing at FERC,” 2026. utilitydive.com
  4. 4.Midcontinent Independent System Operator, “MISO Status Update (Missouri PSC, May 28, 2026),” 2026. psc.mo.gov
  5. 5.Capacity Media, “Five of six US grid operators seek delay on FERC’s data centre power deadline,” 2026. capacityglobal.com
  6. 6.Utility Dive, “OMS-MISO survey: resource outlook and planned generation,” 2026. utilitydive.com
  7. 7.Wisconsin Department of Natural Resources, “Great Lakes Compact and diversions,” n.d. dnr.wisconsin.gov
  8. 8.American Public Power Association, “MISO Board approves historic transmission plan to strengthen grid reliability,” 2024. publicpower.org
  9. 9.Utility Dive, “MISO capacity auction results, 2026/27 planning year,” 2026. utilitydive.com
  10. 10.S&P Global Commodity Insights, “MISO’s first 10 power projects for expedited queue total 5.3 GW of new capacity,” 2025. spglobal.com
  11. 11.E&E News, “MISO to study 15 projects for accelerated grid connection,” 2026. eenews.net
  12. 12.Akin Gump, “FERC Issues Landmark Show Cause Orders on Large Load Interconnection,” 2026. akingump.com
  13. 13.Federal Energy Regulatory Commission, “Commissioner LaCerte’s Concurrence on Midcontinent Independent System Operator, Inc. (Docket No. EL26-70-000),” 2026. ferc.gov
  14. 14.Utility Dive, “Google, Xcel and MISO zero-injection agreements for large loads at FERC,” 2026. utilitydive.com
  15. 15.WPR, “Microsoft data centers and the Great Lakes Compact,” n.d. wpr.org

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Terms in this guide

Related guides

More in Grid regions

Guide 3 of 9 in Grid regions · all 242 guides · glossary · calculators