Key takeaways
- MISO spans 15 states and Manitoba, and its north and south differ in climate, hazards and capacity prices.14
- Most customers are served by vertically integrated utilities under state regulation, so how the utility would supply the load matters as much as the connection.
- For 2026/27, summer capacity cleared at $424.30/MW-day in zones 1–7 and $384.10 in zones 8 and 10, after $666.50 across all zones in 2025/26.4
- FERC ordered MISO in June 2026 to justify or reform its large-load rules; MISO sought more time, which could push its filing to mid-November 2026.25
- Utilities plan about 15 GW a year of new accredited summer capacity, led by natural gas, with about 4 GW a year expected through MISO’s expedited study lane.6
- Sites near PJM or SPP need extra care about which utility and RTO would serve them, and Great Lakes sites face basin water rules.7
01The MISO footprint and how it is organized
The Midcontinent Independent System Operator (MISO) runs the transmission system and wholesale market for all or parts of Arkansas, Illinois, Indiana, Iowa, Kentucky, Louisiana, Michigan, Minnesota, Mississippi, Missouri, Montana, North Dakota, South Dakota, Texas and Wisconsin, plus Manitoba in Canada. It serves about 45 million people across about 79,000 miles of transmission lines.1 It is part of the Eastern Interconnection and is regulated by FERC for its U.S. operations.
The footprint is often discussed in two broad parts: a northern and central region across the Upper Midwest and Great Lakes, and a southern region in Arkansas, Louisiana, Mississippi and part of East Texas. They are connected, but they clear at different capacity prices and have different generation mixes, climates and hazards.4 Within both, service comes from investor-owned utilities, cooperatives and municipal utilities. See ISO and RTO markets for the role of RTOs.
Fig. 1MISO’s north and south at a glance
Zones 1–7
North and Central
- Summer capacity: $424.30/MW-day
- Cool climate supports efficient cooling
- Great Lakes Compact bars most out-of-basin diversions
- 765 kV backbone planned under Tranche 2.1
Zones 8–10
South
- Arkansas, Louisiana, Mississippi and part of East Texas
- Summer capacity: $384.10–$412.10/MW-day
- Hot, humid summers
- Hurricane, storm surge and river flood exposure
02Market structure and retail service
Most of MISO’s states kept vertically integrated utilities. The utility owns or contracts for generation, owns transmission and distribution, and sells bundled service at rates set by the state utility commission. A few states allow limited retail choice. For most data center sites in MISO, the local utility is both the connection provider and the energy supplier. See regulated utility vs. competitive market sites.
That has practical effects. Large-load terms come through the utility’s tariffs and special contracts, approved by state regulators. New generation to serve a large load usually goes through the utility’s resource planning and state review. A utility that wants the load can be an active partner, while one that is cautious can slow everything down. See large-load tariffs and our Wisconsin and Louisiana guides for two MISO examples.
| Element | MISO | PJM | ERCOT |
|---|---|---|---|
| Typical retail model | Mostly vertically integrated, state-regulated | Mix of retail choice and vertically integrated | Retail choice in much of the area; co-ops and municipals often bundled |
| Resource adequacy | Utility planning plus a seasonal MISO auction | Centralized forward capacity market plus state policy | Energy-only design with added reliability services |
| Who connects the load | Local utility or transmission owner | Local utility or transmission owner | Transmission service provider, with ERCOT review |
| Main regulator for wholesale | FERC | FERC | State commission (PUCT) |
03Resource adequacy and capacity prices
In MISO, utilities and their state regulators carry the main responsibility for having enough generation. MISO sets reserve requirements and runs an annual Planning Resource Auction that lets load-serving entities meet or balance their resource adequacy obligations. The auction now clears each season separately, and many utilities meet most of their needs through their own plants and contracts, using the auction at the margin.
Prices have swung. Summer capacity cleared at $666.50/MW-day across all zones for 2025/26. For the 2026/27 planning year, summer cleared at $424.30 in the north and central zones, $412.10 in zone 9 and $384.10 in zones 8 and 10, while fall, winter and spring prices were far lower.4 Offers rose to about 141 GW from about 136 GW the year before, which helped pull prices down.9 Data centers usually feel these prices through utility rates.
Fig. 2MISO summer capacity prices
- 2025/26, all zones$666.50
- 2026/27, zones 1–7$424.30
- 2026/27, zone 9$412.10
- 2026/27, zones 8 and 10$384.10
$/MW-day
A large new load changes a utility’s resource plan. The utility may need new generation, longer life for existing plants or new contracts, and those choices often need state approval. That can add time, and it can lead the utility to ask the data center for long-term commitments, minimum bills or help funding new resources. Asking early how the utility would supply the load, not just connect it, is one of the most useful steps in MISO.
04How much new load and supply MISO expects
The annual OMS-MISO survey of load-serving entities found in 2026 that members plan to add about 15 GW of new accredited summer capacity a year, up from as much as 8.6 GW a year in the prior survey, with natural gas the largest share. Members projected five-year load growth of 3.1% to 5.1% a year, based on their forecasts and requests for new load.6
On November load forecasts, the survey showed capacity above the planning reserve requirement growing from 11.5 GW in summer 2028 to 39 GW in summer 2031; on April forecasts the margins were significantly smaller. MISO cautioned that 87 GW of resources with signed interconnection agreements but not yet built may not all materialize, and that reliability risk is shifting from summer toward winter.6
To speed new supply, MISO runs an Expedited Resource Addition Study (ERAS). Its first cycle, in 2025, covered ten projects totaling about 5.3 GW, with in-service dates from January 2027 to August 2028,10 and a third cycle announced in March 2026 covered 15 more projects.11 The survey expects about 4 GW a year of planned additions to come through that lane.6 That can let a utility add generation for a new load faster than the standard queue allows.
05How large-load interconnection works in MISO
A data center applies to the local utility or transmission owner, which studies the connection and coordinates with MISO on transmission effects. MISO’s regional planning process includes forecast loads and can identify upgrades. Loads do not use the generator queue, though any grid-connected on-site generation may.
- Upgrade costs may fall to the customer, the utility’s ratepayers or a regional allocation, depending on the upgrade and the applicable tariff. See transmission upgrades and cost allocation.
- Utilities may tie service to an approved resource plan for the new load.
- Cooperatives often rely on a generation and transmission cooperative for supply, which adds a party to the conversation.
Fig. 3A large load’s path to power in MISO
- 01
Find the utility and RTO
Serving utility, co-op or city, and the RTO it plans in.
- 02
Load study
The utility studies the connection with MISO.
- 03
Supply plan
New generation or contracts, often needing state approval.
- 04
Service agreement
Large-load tariff or contract, with minimum bills and collateral.
- 05
Build and energize
Lines, substation and metering, then energization.
FERC’s 2026 review of large-load rules
On June 18, 2026, FERC issued show-cause orders to all six FERC-jurisdictional RTOs and ISOs, using as a preliminary benchmark new commercial or industrial loads of 50 MW or more connecting above 69 kV.12 The MISO order, in Docket EL26-70, preliminarily found gaps in MISO’s tariff: no adequate large-load definition, unclear application and study procedures, thin ongoing operating requirements and no pro forma service agreement terms.213 MISO asked FERC in August to hold its case in abeyance while it prepares filings; if FERC agrees, MISO’s response would be due in mid-November 2026.5 No ruling on that request had been reported as of early October 2026.
MISO has also asked FERC to approve a faster lane for loads that bring their own supply: a process that studies a large load and the generation serving it together, aiming for an answer in about 120 days. As filed, it is open to loads larger than 200 MW paired with generation in the same resource zone, with a firm offtake contract and control of the generation site, and MISO asked FERC to rule by December 2.3 A separate zero-injection agreement, filed in August 2026, would let generation paired with nearby load connect on the condition that it never exports net energy to the grid.14 See co-locating data centers with power plants.
06Seams with PJM and SPP, and the transmission build-out
MISO borders PJM to the east and SPP to the west, and the borders are irregular. In some states, neighboring counties, or even neighboring tracts, are served by utilities in different RTOs. Transmission flows across these seams, and upgrades on one side can depend on studies on the other.
For a site near a seam, confirm the serving utility and its RTO early. A line visible from the property may belong to a different system than the one that would serve the load. Our guides to PJM and SPP cover the neighboring regions.
MISO’s long-range plan will also change where capacity is available. In December 2024 MISO’s board approved the $21.8 billion Tranche 2.1 portfolio, built around a 765 kV backbone across the Midwest.8 Treat those lines as a future option for a site, not a present one.
07Climate, water, land and other constraints
- Climate. Northern areas have cool climates that support efficient cooling and lower design PUE. Southern areas are hot and humid for much of the year.
- Water. The Great Lakes and major rivers provide significant water. Since 2008 the Great Lakes Compact has generally banned diversions outside the basin, with narrow exceptions for straddling communities and counties, and states regulate withdrawals inside it.7 In Wisconsin’s part of the basin, withdrawals above 100,000 gallons a day need a state permit, but a data center that buys city water falls under the utility’s permit rather than its own.15 See water rights and groundwater.
- Hazards. Southern areas carry hurricane, flood and storm surge exposure. The central footprint has tornado and severe storm risk, and parts of the Mississippi Valley have seismic and river flood exposure.
- Land. Much of the footprint is agricultural, with large, flat tracts. Converting farmland can raise local concerns and, in some states, specific review. Check any state farmland preservation programs, drainage district obligations and easements that run with the land.
- Fiber. Metro areas and interstate corridors have good fiber; rural sites may need long laterals for diverse routes.
08What to check for a site in MISO
- 01Identify the serving utility, its RTO and whether the site sits near a seam with PJM or SPP.
- 02Ask how the utility would supply the load, not just connect it, and whether new generation needs state approval or could use MISO’s expedited study.
- 03Learn the utility’s large-load tariff, contract terms and required commitments, and how capacity costs reach the bill.
- 04Ask how FERC’s 2026 large-load proceeding could change study steps or service terms.
- 05Map nearby transmission and substations, including Tranche 2.1 projects, and ask about pending large loads.
- 06Check water supply and any basin or state withdrawal rules.
- 07Screen for flood, storm and seismic exposure, especially in the south and along major rivers, and confirm local zoning and fiber options.
When we screen sites in MISO, the utility conversation tends to set the timeline more than the transmission map does. If you have a tract in the footprint, you can get a site reviewed.
Common questions
What states are in MISO?
MISO covers all or parts of 15 states, from North Dakota, Minnesota and Michigan south to Louisiana, Mississippi and part of East Texas, plus the Canadian province of Manitoba. Several are split between MISO and neighboring regions such as PJM or SPP, so confirm the serving utility and RTO for any specific site.
How do data centers get power in MISO?
Usually through a vertically integrated utility regulated by the state. The utility studies the connection with MISO, provides the substation and transmission service, and supplies the energy under a large-load tariff or special contract approved by regulators. If the load needs new generation, the utility’s resource planning and state approvals become part of the timeline.
Does MISO have a capacity market?
Yes, in a different form from PJM’s. MISO’s annual Planning Resource Auction sets seasonal prices, but utilities and state regulators carry the main responsibility for resource adequacy. For 2026/27, summer capacity cleared at $384.10 to $424.30/MW-day, depending on the zone.4 For a data center, the utility’s resource plan usually matters more than auction results.
How is FERC changing large-load interconnection in MISO?
In June 2026, FERC ordered MISO and the other FERC-jurisdictional grid operators to justify or reform their rules for large loads, using loads of 50 MW or more connecting above 69 kV as a preliminary benchmark.12 MISO sought more time, so its proposals may not be filed before mid-November 2026 and would then need FERC review.5
Notes
- 1.Cass County Electric Cooperative, “Meet MISO,” n.d. casscountyelectric.com
- 2.Akin Gump, “FERC Directs Midcontinent Independent System Operator to Revise Tariff to Expedite Data Center Development,” 2026. akingump.com
- 3.Utility Dive, “MISO large load and generation study (LARS) filing at FERC,” 2026. utilitydive.com
- 4.Midcontinent Independent System Operator, “MISO Status Update (Missouri PSC, May 28, 2026),” 2026. psc.mo.gov
- 5.Capacity Media, “Five of six US grid operators seek delay on FERC’s data centre power deadline,” 2026. capacityglobal.com
- 6.Utility Dive, “OMS-MISO survey: resource outlook and planned generation,” 2026. utilitydive.com
- 7.Wisconsin Department of Natural Resources, “Great Lakes Compact and diversions,” n.d. dnr.wisconsin.gov
- 8.American Public Power Association, “MISO Board approves historic transmission plan to strengthen grid reliability,” 2024. publicpower.org
- 9.Utility Dive, “MISO capacity auction results, 2026/27 planning year,” 2026. utilitydive.com
- 10.S&P Global Commodity Insights, “MISO’s first 10 power projects for expedited queue total 5.3 GW of new capacity,” 2025. spglobal.com
- 11.E&E News, “MISO to study 15 projects for accelerated grid connection,” 2026. eenews.net
- 12.Akin Gump, “FERC Issues Landmark Show Cause Orders on Large Load Interconnection,” 2026. akingump.com
- 13.Federal Energy Regulatory Commission, “Commissioner LaCerte’s Concurrence on Midcontinent Independent System Operator, Inc. (Docket No. EL26-70-000),” 2026. ferc.gov
- 14.Utility Dive, “Google, Xcel and MISO zero-injection agreements for large loads at FERC,” 2026. utilitydive.com
- 15.WPR, “Microsoft data centers and the Great Lakes Compact,” n.d. wpr.org
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Grid regions
Guide 3 of 9 in Grid regions · all 242 guides · glossary · calculators
