Key takeaways
- The utility whose territory contains the site serves the load; the ISO or RTO does not connect it and owns no transmission lines.2
- Capacity costs differ sharply by market: PJM’s capacity auctions cleared at the price cap for three straight delivery years, through 2028/29.5
- ERCOT runs an energy-only market,6 while SPP and California require load-serving entities to hold enough capacity instead of running a central auction.78
- Regions without an RTO are served by vertically integrated utilities whose plans, approved by state commissions, set the pace of new supply.
- Investor-owned utilities served about 72% of U.S. electricity customers in 2017; cooperatives and public power follow different rules and decision processes.9
- Some states allow retail choice of energy supplier, but wires charges and large-load terms still come from the utility.
01What ISOs and RTOs do
Independent system operators and regional transmission organizations (ISOs and RTOs) operate the high-voltage grid across a region. They do not own transmission or generation, do not sell power to retail customers and do not set retail prices; the wires stay with utilities and transmission companies.2 They dispatch generation, run wholesale energy markets, manage reliability in real time and coordinate regional transmission planning. Their footprints cover about two-thirds of U.S. electricity demand.1
Six of them fall under FERC’s jurisdiction, which is why FERC’s June 2026 large-load orders went to PJM, MISO, SPP, CAISO, NYISO and ISO-NE.4 ERCOT is the exception: because its grid lies wholly within Texas and is largely isolated from neighboring grids, its wholesale market sits outside FERC’s authority, although NERC and FERC reliability rules still apply there.2
Fig. 1Who does what for a large load
- 01FERC and state commissionsFERC: wholesale and transmission rules; states: retail rates, new plants and lines
- 02NERCReliability standards for the bulk grid
- 03ISO or RTOMarkets, dispatch and regional planning; owns no wires
- 04Transmission ownerOwns, builds and maintains the high-voltage lines
- 05Retail utilityStudies the load, signs the service agreement, bills
- 06Data center campusCustomer substation and on-site systems
For a data center, the ISO or RTO matters in three ways: it sets the market that determines wholesale energy and capacity prices, it runs transmission planning that can bring new lines and upgrades, and it runs the generator interconnection queue that adds new supply. Its role in connecting large loads is also growing. FERC’s June 2026 orders preliminarily found that the six operators’ tariffs may be unjust and unreasonable because their rules for large loads, including co-location, behind-the-meter generation and flexible loads, are unclear.4 See power timelines and interconnection queues for what that means for schedules.
02The seven U.S. ISOs and RTOs
| Operator | General footprint | Notable market features |
|---|---|---|
| PJM | Mid-Atlantic and parts of the Midwest and South | Energy market plus a centralized capacity auction10 |
| ERCOT | Most of Texas | Energy-only market with no capacity auction6 |
| MISO | Midwest to the Gulf South, plus Manitoba | Energy market plus a seasonal capacity auction, the Planning Resource Auction11 |
| SPP | Central U.S. from the northern Plains to parts of Texas; parts of the West since April 2026 | Energy market; no centralized capacity auction, but members must carry capacity above forecast peak7 |
| CAISO | Most of California | Energy market; resource adequacy requirements set by the CPUC for load-serving entities8 |
| NYISO | New York State | Energy market plus a capacity market with six-month strip and monthly auctions11 |
| ISO-NE | The six New England states | Energy market plus a capacity market moving from three-year-forward to prompt auctions, the first planned for 202812 |
Footprints follow utility membership, not state lines, so parts of one state can sit in different markets. Market rules also change through stakeholder processes and FERC filings. SPP’s RTO expansion into the Western Interconnection, approved by FERC in 2025, took effect on April 1, 2026, making SPP the first RTO in both the Eastern and Western grids,13 and ISO-NE is replacing its three-year-forward capacity auctions with prompt auctions held about a month before each delivery year.12 Check current rules for any specific site.
03Regions without an ISO or RTO
Roughly a third of U.S. electricity demand sits outside ISO and RTO footprints.1 Most of it is in the Southeast and in the West outside California. There, vertically integrated utilities own generation, transmission and distribution and plan their own systems; new plants and lines are approved by state commissions, and trades with neighboring utilities supplement each utility’s own resources. Some large utilities straddle the line: Duke Energy’s footprint includes territory both inside and outside an RTO.3
For a large load, this often means one utility controls the whole answer: the generation to serve the load, the transmission to deliver it, and the rate it will charge. It also means the utility’s resource plan, and the state commission’s review of it, largely determine how quickly new supply is added for large customers. Advocates argue an RTO would lower wholesale costs in the Southeast, while utilities counter that it would add complexity and reduce state control.3 See our Southeast site selection guide.
The West is changing faster. CAISO’s Extended Day-Ahead Market went live with PacifiCorp on May 1, 2026, the first utility outside California to join, and it now schedules generation and transmission jointly across balancing areas from California to Wyoming.14
Fig. 2Inside an RTO vs. a vertically integrated region
About two-thirds of U.S. demand
Inside an ISO or RTO
- Wholesale market sets energy prices
- Capacity auctions in PJM, MISO, NYISO and ISO-NE
- New supply arrives through generator queues
- Retail utility and transmission owner may differ
Much of the Southeast and West
Vertically integrated region
- One utility plans generation and transmission
- State commission approves rates and new plants
- Supply added through the utility’s own plan
- One company answers most power questions
04Utility territories and who actually serves the load
In most states, retail electric service is assigned by territory. The utility whose service territory contains the site is the one that will study and serve the load, regardless of which transmission line is closest. Territory boundaries can split counties and even individual tracts, and annexation can complicate them further; see annexation and utility service areas.
| Utility type | Ownership and oversight | What it means for a large load |
|---|---|---|
| Investor-owned utility | Shareholder-owned; rates and terms regulated by the state commission | Formal tariffs and processes; large-load terms subject to commission review |
| Electric cooperative | Member-owned; regulation varies by state | Often relies on a generation and transmission cooperative for supply; board and wholesale supplier both involved |
| Municipal utility | Owned by a city or public power agency; local governance | Decisions tied to local government; may buy wholesale power from others |
| Federal or state power entity | Public, with its own governing statutes | Its own rules for serving large loads, often through local distributors |
Fig. 3U.S. electric utilities by ownership, 2017
- Electric utilities in total
- 2,938
- Customers of investor-owned utilities
- 72%
- Electric cooperatives
- 812
- Publicly owned utilities
- 1,958
In ISO and RTO regions, the retail utility and the transmission owner can be different companies. A site may need agreements with both, and the ISO may need to review the load’s effect on the grid. See the large-load interconnection process for those steps.
05Retail choice vs. regulated service
Some states allow customers to buy energy from a competitive retail supplier while the local utility continues to provide delivery over its wires, as in much of the ERCOT region of Texas. Michigan’s regulator counted about 20 jurisdictions with some form of restructured retail market in 2025, but programs vary widely: Michigan itself caps choice at 10% of a utility’s retail sales, and business and industrial customers hold nearly all of it.15 In most other states, the utility provides bundled service at regulated rates.
- In retail-choice areas, the developer can negotiate supply contracts separately, often with more pricing options, but wires charges and interconnection terms still come from the utility.
- In regulated areas, the utility’s tariff sets most of the economics, though large customers may negotiate special contracts subject to commission approval.
- Renewable or clean-energy procurement options also differ, from utility programs to direct power purchase agreements in markets that allow them.
Rules vary by state and sometimes by utility, so check each site rather than assuming one model fits a region; see regulated utility vs. competitive market sites.
06How market structure affects data center siting
No market structure is better for data centers in general. Each one shifts where the cost, risk and decision-making sit.
- Energy prices. Wholesale prices and their volatility differ by region and by location within a market.
- Capacity costs. In markets with capacity auctions, large new loads pay into them, and those costs can move sharply. PJM’s market monitor tied about $6.3 billion, or 38%, of the 2028/29 auction’s $16.4 billion cost to data center demand.16 See PJM capacity prices and data centers.
- Speed of new supply. Organized markets rely on generator queues and market signals; integrated utilities rely on resource plans approved by the state.
- Transmission planning. Regional plans can bring major new lines, but on long cycles; local upgrades are usually faster.
- Co-location and on-site generation. Rules for pairing a load with a generator, and for on-site generation and bridge power, differ by market and utility. FERC ordered PJM in December 2025 to write clear tariff rules and new transmission service options for co-located load,17 and its June 2026 orders extend that review to all six FERC-jurisdictional regions.4
- State policy. Incentives, tariff terms and siting rules are set at the state level and change over time; see our guide to data center tax incentives.
Fig. 4PJM capacity prices by delivery year
- 2025/26$269.92
- 2026/27$329.17
- 2027/28$333.44
- 2028/29about $325
$/MW-day
When we compare sites across regions, we treat the market and utility as part of the site, alongside land, water and fiber. Two otherwise similar tracts in different territories can face very different power costs and timelines.
07What to confirm for a specific site
Market structure is a starting point, not an answer. For any specific tract, confirm these items early with the utility, in writing where possible.
- 01Which retail utility serves the parcel, and whether a territory line crosses it.
- 02Who owns the nearest transmission, and whether the ISO or RTO must review the load.
- 03Which wholesale market the utility belongs to today, and which it has committed to join, especially in the West.
- 04How capacity is procured, and what recent capacity prices or adequacy rules imply for cost.
- 05Whether retail choice is available for a load of your size, and on what terms.
- 06Which large-load tariff, study process and financial security requirements apply.
Early answers from a utility are useful but not binding; our guide to utility will-serve letters explains what they do and do not commit to. If you want a second look at a site’s power path, you can get a site reviewed.
Common questions
What is the difference between an ISO and an RTO?
In practice the terms overlap. Both are independent organizations that operate the high-voltage grid and run wholesale markets across a region. The Department of Energy counts four RTOs (PJM, MISO, SPP and ISO-NE) and three ISOs (CAISO, NYISO and ERCOT), and neither type owns transmission lines, which belong to utilities and transmission companies.2
Does the ISO or RTO connect a data center to the grid?
Usually not directly. The retail utility whose territory contains the site, with the transmission owner if that is a different company, studies and serves the load. The ISO or RTO may review how a large load affects the bulk grid, and FERC’s June 2026 orders asked the six FERC-jurisdictional operators to justify or reform their rules for large loads of about 50 MW and up connecting above 69 kV.4 Start with the utility.
How do I find out which utility serves a property?
Start with the service territory maps that state commissions and many utilities publish, then confirm directly with the utility, because maps are not always current. Cooperative and municipal territories are easy to miss. The serving utility determines the large-load process and rates, so confirming it early avoids building a plan around the wrong company.
Is it better to site a data center inside or outside an RTO?
Neither is better in general. Inside an RTO, wholesale markets set energy and capacity prices, and capacity costs can swing, as PJM’s recent auctions at the price cap show.5 Outside one, a vertically integrated utility plans generation and transmission and sets rates under state oversight. The better choice depends on the specific utility’s capacity, timeline, tariffs and the project’s energy procurement goals, so compare sites individually rather than by region.
Does ERCOT have a capacity market?
No. ERCOT is an energy-only market: prices for energy and ancillary services are the signal for new supply, with no separate capacity auction.6 For a large load, that puts the weight on energy contracts and price exposure rather than on a capacity charge set by auction. Texas also sets its own rules for connecting large loads to the ERCOT grid.
Notes
- 1.Federal Energy Regulatory Commission, “Electric Power Markets: National Overview,” n.d. ferc.gov
- 2.U.S. Department of Energy, “Balancing Authority Backgrounder,” 2023. energy.gov
- 3.Canary Media, “In the Southeast, Where Big Utilities Rule, Calls for a Real Power Market Persist,” 2023. canarymedia.com
- 4.Orrick, “FERC Show Cause Orders Signal Broad Reform to Large Load Interconnection Policies,” 2026. orrick.com
- 5.OPIS, “PJM’s 2028/2029 Capacity Auction Clears at Price Cap for Third Time,” 2026. opis.com
- 6.The Brattle Group, “Brattle Economists Prepare Report That Addresses ERCOT Resource Adequacy Concerns and Provides Recommendations to Improve Long-Term Reliability Through Generation Investment,” n.d. brattle.com
- 7.Customized Energy Solutions, “Part 1 of 3: Resource Adequacy in SPP: The Capacity Gap No One Is Talking About and What Actually Makes a Megawatt Bankable,” 2026. ces-ltd.com
- 8.California Public Utilities Commission, “Resource Adequacy Homepage,” n.d. cpuc.ca.gov
- 9.U.S. Energy Information Administration, “Investor-Owned Utilities Served 72% of U.S. Electricity Customers in 2017,” 2019. eia.gov
- 10.S&P Global Market Intelligence, “PJM Capacity Auction Prices Clear at Record Highs for 2nd Year in a Row,” 2025. spglobal.com
- 11.PJM Interconnection, “Overview of Sub-Annual Market Designs Across Other ISOs/RTOs,” 2025. pjm.com
- 12.Utility Dive, “ISO-NE Proposes Capacity Market Overhaul With Shift to Prompt Auction,” 2025. utilitydive.com
- 13.Southwest Power Pool, “SPP First RTO to Operate in Both Interconnections With Tariff Approval,” 2025. spp.org
- 14.California ISO, “EDAM Is Live: PacifiCorp and CAISO Successfully Launch New Market May 1,” 2026. caiso.com
- 15.Michigan Public Service Commission, “State’s Electric Choice Program Remains Fully Subscribed in 2025,” 2026. michigan.gov
- 16.Maryland Association of Counties (Conduit Street), “Data Center Demand Drives Higher PJM Capacity Costs,” 2026. conduitstreet.mdcounties.org
- 17.Beveridge & Diamond, “FERC Orders PJM to Create Clear Rules for Co-Located Data Centers and Large Loads,” 2025. bdlaw.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Power & interconnection
- How Much Power Does a Data Center Need?
- Transmission Voltage and Data Centers: 69 kV to 765 kV
- Substation Proximity and Capacity for Data Center Sites
- On-Site Generation and Bridge Power for Data Centers
- What Is Powered Land?
- Load Ramp Schedules: How to Phase Power for a Data Center Campus
- Redundant Utility Feeds and Dual Substations for Data Centers
- Large-Load Tariffs and Electric Service Agreements, Explained
- Behind-the-Meter vs. Front-of-the-Meter Power for Data Centers
- Transmission Upgrades for Data Centers: Who Pays for Them?
- Microgrids and Battery Storage at Data Center Sites
- Co-Locating Data Centers With Power Plants
- Nuclear and Small Modular Reactors: Siting Considerations for Data Centers
- Renewable Energy Procurement and How It Affects Data Center Siting
- What Is a Utility Load Study for a Data Center?
- Firm vs. Interruptible Electric Service for Data Centers
- Flexible Data Center Loads and Demand Response
- Texas Senate Bill 6: What It Means for Data Centers and Large Loads
- Contribution in Aid of Construction (CIAC) and Line Extensions for Data Centers
- Transformer and Switchgear Lead Times for Data Centers
- Substation Configurations for Data Center Campuses: Ring Bus, Breaker-and-a-Half and Double Bus
- Power Purchase Agreements for Data Centers: Physical, Virtual and Sleeved
- 24/7 Carbon-Free Energy and Hourly Matching for Data Centers
- Gas Turbines vs. Reciprocating Engines for Data Center On-Site Power
- Fuel Cells for Data Center Power: How They Work and Where They Fit
- NERC Reliability Standards and Large Data Center Loads: Ride-Through, Load Loss and Registration
- From Signed Agreement to Energization: The Data Center Power Timeline
- Hydropower and Data Center Siting: Public Power, Allocations and Drought Risk
- Geothermal Power for Data Centers: Enhanced Geothermal, Clean Tariffs and Siting in the West
- Surplus Interconnection Service and Retired Power Plant Sites: How Existing Grid Rights Get Reused
Guide 6 of 35 in Power & interconnection · all 242 guides · glossary · calculators
