Key takeaways
- U.S. transmission lines in the federal HIFLD dataset run from 69 kV up to 765 kV; distribution feeders typically operate far lower, often at 4–16 kV in California’s system and up to about 35 kV elsewhere.14
- NERC’s Bulk Electric System generally starts at 100 kV, so 69 kV lines are usually treated as sub-transmission, and radial lines serving only load can be excluded.5
- A line’s usable capacity depends on its thermal rating, existing flows and single-contingency limits, not voltage alone.36
- Large campuses usually need a new substation and often a loop-in or two sources; Dominion has served a 100 MW-plus data center by looping a 230 kV line into a new four-breaker ring.78
- Public transmission maps are approximate: some HIFLD voltages were inferred from imagery, so the utility’s own data is what counts.9
01Why voltage matters for data center sites
Electrical power is the product of voltage and current. For a given conductor, raising the voltage lets a line carry more power with lower losses over longer distances. That is why utilities move bulk power at high voltage and step it down near the customer. A common engineering yardstick, surge impedance loading, rises with the square of line voltage, so doubling voltage roughly quadruples a line’s natural loading.2
For site selection, voltage is a quick proxy for scale. A site next to a 12.47 kV distribution feeder and a site next to a 345 kV line are in different categories before anything else is considered. Voltage tells you what class of load the nearby system was built to move. It does not tell you how much spare room it has.
Fig. 1How power reaches a data center campus
- 01GenerationPower plants step voltage up for transport
- 02Bulk transmission230, 345, 500 and 765 kV backbone
- 03Regional transmission69, 115, 138 and 161 kV networks
- 04Customer substationSteps transmission down to medium voltage
- 05Campus distributionMedium voltage, such as 34.5 or 13.8 kV, to each building
02Distribution vs. transmission service
Distribution systems operate at much lower voltages than transmission. In California, the CPUC notes that distribution lines are typically energized at 16 kV, 12 kV or 4 kV and cover much shorter distances than transmission lines.4 Elsewhere, common distribution voltages include 12.47 kV, 13.2 kV, 13.8 kV, 25 kV and 34.5 kV. These feeders serve homes, businesses and smaller industrial customers out of a distribution substation.
Transmission starts above that. The federal HIFLD transmission dataset covers lines operated from 69 kV up to 765 kV.1 The reliability rules that apply depend on voltage and configuration. NERC’s Bulk Electric System definition uses 100 kV as its bright line, excludes facilities used in local distribution, and excludes radial systems that start from a single point of connection at 100 kV or higher and serve only load.5 That is why many utilities treat 69 kV, and sometimes 115 kV, as sub-transmission.
Edge facilities can often be served from distribution. Above that, the size of the load usually pushes the project to transmission service with its own substation. Once a project takes transmission service, the developer typically pays for, and sometimes owns, the substation that steps power down to a medium voltage such as 34.5 kV or 13.8 kV for distribution across the campus. Our guide to utility-owned vs. customer-owned substations covers that choice.
03Matching transmission voltage to data center size
The table below gives rough planning roles for each voltage class. Treat the load ranges as indicative only. Line loadability falls as lines get longer, a relationship engineers have used since H.P. St. Clair’s 1953 curve, so a short, lightly loaded 138 kV line between two strong substations can outperform a long, heavily loaded 230 kV line.10
| Voltage | Typical system role | Data center fit (indicative) |
|---|---|---|
| Below ~35 kV | Distribution feeders | Edge sites, from a few MW up to roughly 10 MW depending on the feeder |
| 69 kV | Sub-transmission, local networks; usually below the BES threshold | Smaller enterprise and colocation, tens of MW |
| 115 / 138 kV | Regional transmission workhorse | Colocation and early hyperscale phases, tens to low hundreds of MW |
| 161 kV | Regional transmission in parts of the Midwest and Southeast | Similar to 138 kV, somewhat more headroom |
| 230 kV | Regional backbone | Hyperscale campuses, low to mid hundreds of MW |
| 345 kV | Bulk transmission backbone in many regions | Large hyperscale and AI campuses, hundreds of MW and up |
| 500 kV | Extra-high-voltage bulk transfer | Gigawatt-scale campuses |
| 765 kV | Extra-high-voltage network in parts of the eastern U.S., now planned in Texas11 | Gigawatt-scale campuses and regional load growth; connections are rare and studied closely |
Texas shows how load growth is pushing voltages up. In April 2025 the Public Utility Commission of Texas adopted a 765 kV plan for the Permian Basin, including three new 765 kV lines from Central Texas, to serve load growth projected through 2038; one policy analysis expects the added capacity to serve mainly data center growth in West Texas.11 ERCOT’s study used Permian load levels of 23,659 MW in 2030 and 26,400 MW in 2038.12 For the load side of this comparison, see our guide on how much power a data center needs.
Fig. 2Texas Permian Basin 765 kV plan
- New 765 kV lines approved from Central Texas
- 3
- Study load for the Permian region, 2030
- 23,659 MW
- Study load for the Permian region, 2038
- 26,400 MW
04Why line capacity depends on more than voltage
Two lines at the same voltage can have very different capacity to serve a new load. Utilities and grid operators look at several factors.
- Thermal rating. Conductor size and type, and how hot the line is allowed to run, set how much current it can carry. Since FERC Order No. 881, transmission providers must use ambient-adjusted ratings that reflect an up-to-date temperature forecast for periods of an hour or less, with implementation required by July 12, 2025.613
- Existing flows. A line already carrying power across a region has less room for a new load tapped off it.
- Contingency limits. Under NERC TPL-001-5.1, planners test the system with no contingency (P0) and after the loss of a single element (P1), in both steady-state and stability studies.3 A new load often hits these limits before it hits a line’s normal rating.
- System strength and voltage support. A large load at the end of a long line can cause voltage problems even when thermal capacity looks adequate, and long lines heavily loaded relative to their natural loading need added reactive support.
- Upstream constraints. The binding limit may be a transformer or line miles away, not the one next to the site.
This is why utilities run load studies before committing to serve a large customer, and why a site next to a high-voltage line can still face major network upgrades. CenterPoint’s load data request notes that data centers are significantly large loads that planners must understand to model adequately.14 Our guides to the utility load study and transmission upgrade cost allocation explain what follows.
05How a data center campus connects to a transmission line
There are a few common ways to bring transmission service to a site. The utility decides which it will accept, based on reliability and its own planning rules.
- Radial tap. A single line is extended from an existing line to the customer substation. It is cheaper and quicker to build and needs less land, but it gives the site only one path and exposes it to upstream faults and outages.8 Many utilities limit how much load they will serve this way.
- Loop-in (or “loop-in, loop-out”). The existing line is cut and routed into a new station, so the site is fed from two directions. It costs more, takes longer and needs more space, and the new segments must carry the line’s full through-flow.8
- New switching station. A new utility-owned station with breakers is built on or near the site, often designed for future expansion. In one PJM filing, Dominion served a data center above 100 MW by cutting and looping a 230 kV line into a new substation with a four-breaker ring.7
- Two independent sources. Lines from two different substations or two separate circuits feed the campus, which improves resilience to a single outage.
Fig. 3Radial tap vs. loop-in connection
Faster, cheaper
Radial tap
- One new corridor from the existing line
- Less land and construction
- Single path to the site
- Exposed to upstream line or substation outages
More resilient
Loop-in, loop-out
- Existing line split into the site station
- Fed from two directions
- Higher cost and longer design time
- Larger footprint; must carry through-flow
Each option has a land footprint, and each needs easements if the line crosses other property; see eminent domain and transmission easements. Our guides to substation proximity and capacity, substation configurations and redundant utility feeds cover the substation side in more detail.
06Reading transmission maps with care
Public and commercial transmission maps are a useful starting point for screening. They are also approximate. Metadata for the widely used HIFLD transmission layer notes that voltage information for some records was inferred from indirect sources, such as substation connectivity seen in imagery, and that no formal attribute accuracy test was conducted.9 Line routes can be misplaced, voltages mislabeled, and recently built or retired facilities missing. Maps rarely show circuit count, ratings or how heavily a line is used. Our guide to public data sources for power capacity lists what else is available.
- Confirm the voltage and number of circuits on the structures in the field when you can.
- Identify which substations each line runs between.
- Check who owns and operates the line; it may not be the local retail utility.
- Treat any capacity estimate drawn from maps alone as a hypothesis for the utility to confirm through the large-load interconnection process.
Common questions
What voltage does a data center need?
It depends on the size of the load. Edge sites can often be served from distribution below about 35 kV. Colocation and enterprise campuses commonly take service at 69, 115 or 138 kV. Hyperscale and AI campuses usually connect at 230 kV, 345 kV or 500 kV, and in a few regions 765 kV.11 On site, a customer substation steps the power down to a medium voltage such as 34.5 kV or 13.8 kV for distribution across the campus.
Can a 138 kV line serve a hyperscale data center?
Sometimes, especially for early phases. A 138 kV line can serve loads from tens to low hundreds of megawatts, depending on its rating, length, how loaded it already is, and the strength of the substations at each end.10 A full hyperscale build of several hundred megawatts usually needs more, either multiple 138 kV sources or a connection at 230 kV or higher. Only a utility load study answers this for a specific line.
Is being next to a high-voltage line enough to build a data center?
No. Proximity to a high-voltage line is a strong starting point, but the line may already be heavily loaded, the utility may not permit a tap at that location, or upstream constraints may require major upgrades. Usable capacity depends on thermal ratings, single-contingency limits and system conditions.3 Treat proximity as a reason to ask the utility, not as an answer.
What is the difference between transmission and distribution voltage?
Distribution systems operate at lower voltages, often 4–16 kV in California and up to about 35 kV elsewhere, and deliver power to homes, businesses and smaller industrial users.4 Transmission lines run from 69 kV to 765 kV and move bulk power between plants and substations; NERC’s Bulk Electric System rules generally apply at 100 kV and above.5 Most data centers above a few tens of megawatts need transmission service and a dedicated substation.
How accurate are public transmission line maps?
Good enough for screening, not for decisions. HIFLD metadata notes that some voltage values were inferred and that no formal attribute accuracy test was conducted.9 Confirm voltage, circuits and ownership with the utility before relying on a line.
Notes
- 1.U.S. Department of Homeland Security (HIFLD), via Data.gov, “Electric Power Transmission Lines,” n.d. catalog.data.gov
- 2.Texas A&M University (ECEN 460), “ECEN 460 Spring 2026, Class 8,” 2026. birchfield.engr.tamu.edu
- 3.PJM Interconnection, “TPL-001-5 M14B Changes,” 2023. pjm.com
- 4.California Public Utilities Commission, “Electric Transmission Fact Sheet,” n.d. files.cpuc.ca.gov
- 5.North American Electric Reliability Corporation, “Project 2010-17 Definition of Bulk Electric System (Phase 2),” 2014. nerc.com
- 6.Federal Energy Regulatory Commission, “Managing Transmission Line Ratings, Docket No. RM20-16 (Order No. 881),” 2021. ferc.gov
- 7.PJM Interconnection (Dominion Energy), “Dominion Supplemental Projects, TEAC, January 7, 2025,” 2025. pjm.com
- 8.Burns & McDonnell, “Underground Transmission Considerations for Powering Modern Data Centers,” n.d. info.burnsmcd.com
- 9.University of Florida GeoPlan Center, “Florida Geographic Data Library Documentation: Electric Power Transmission Lines,” n.d. geoplan.ufl.edu
- 10.Grid Controller of India (POSOCO), Western Regional Load Despatch Centre, “Line Loadability in Indian Perspective,” 2012. posoco.in
- 11.Texas Public Policy Foundation, “765 kV Transmission,” 2026. texaspolicy.com
- 12.Electric Reliability Council of Texas, “Response to Rep. Geren, August 12, 2026,” 2026. ercot.com
- 13.ISO New England, “Order 881: Managing Transmission Line Ratings (NEPOOL Council presentation),” 2022. iso-ne.com
- 14.CenterPoint Energy Houston Electric, “CEHE Load Interconnection Data Request Form,” n.d. assets.centerpointenergy.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Power & interconnection
- Power Timelines: Why “When” Matters as Much as “Where”
- ISOs, RTOs and Utility Territories in Data Center Siting
- On-Site Generation and Bridge Power for Data Centers
- Load Ramp Schedules: How to Phase Power for a Data Center Campus
- Redundant Utility Feeds and Dual Substations for Data Centers
- Large-Load Tariffs and Electric Service Agreements, Explained
- Behind-the-Meter vs. Front-of-the-Meter Power for Data Centers
- Transmission Upgrades for Data Centers: Who Pays for Them?
- Microgrids and Battery Storage at Data Center Sites
- Co-Locating Data Centers With Power Plants
- Nuclear and Small Modular Reactors: Siting Considerations for Data Centers
- Renewable Energy Procurement and How It Affects Data Center Siting
- What Is a Utility Load Study for a Data Center?
- Firm vs. Interruptible Electric Service for Data Centers
- Flexible Data Center Loads and Demand Response
- Texas Senate Bill 6: What It Means for Data Centers and Large Loads
- PJM Capacity Prices and Data Center Load Growth
- Contribution in Aid of Construction (CIAC) and Line Extensions for Data Centers
- Transformer and Switchgear Lead Times for Data Centers
- Electricity Rates and Power Costs for Data Center Sites
- Power Purchase Agreements for Data Centers: Physical, Virtual and Sleeved
- 24/7 Carbon-Free Energy and Hourly Matching for Data Centers
- Gas Turbines vs. Reciprocating Engines for Data Center On-Site Power
- Fuel Cells for Data Center Power: How They Work and Where They Fit
- NERC Reliability Standards and Large Data Center Loads: Ride-Through, Load Loss and Registration
- From Signed Agreement to Energization: The Data Center Power Timeline
- Hydropower and Data Center Siting: Public Power, Allocations and Drought Risk
- Geothermal Power for Data Centers: Enhanced Geothermal, Clean Tariffs and Siting in the West
- Surplus Interconnection Service and Retired Power Plant Sites: How Existing Grid Rights Get Reused
Guide 2 of 35 in Power & interconnection · all 242 guides · glossary · calculators
