Key takeaways
- Ownership is a utility and tariff question first. Some utilities offer customer ownership as standard practice for very large loads; others build everything themselves or use a build-and-transfer model.45
- Tariffs often pay for customer ownership: Entergy Arkansas cuts demand charges by $2.18 per kW where the customer owns all transformation,1 and Green Mountain Power lists a 21.65% subtransmission discount.2
- Regulators are moving costs for dedicated substations onto the large loads that trigger them, which narrows the cost gap between the two models.67
- Equipment, not engineering, sets the schedule. Wood Mackenzie expected a 30% U.S. supply deficit for power transformers in 2025,8 whoever places the order.
- An owner takes on a written maintenance program under NFPA 70B, now a mandatory standard,9 and may face new NERC registration rules for large computational loads being finalized in 2026.1011
01What “owning the substation” actually means
Every large data center needs a substation that steps transmission voltage down to the medium voltage that feeds the campus. The ownership question is about where the utility’s system ends and the customer’s begins. That point, the point of delivery, sets the voltage at which power is metered, which tariff applies, and who owns, operates and repairs each piece of equipment.
In the utility-owned model, the utility builds and owns the high-voltage yard, the main power transformers and usually the medium-voltage breakers, and delivers power to the customer at distribution voltage. In the customer-owned model, the utility brings a transmission line to a switching point and the customer owns everything downstream. Black & Veatch describes the second model as building substations that the client will own, allowing the local utility to connect directly with its transmission lines.3
Fig. 1Where ownership can change hands
- 01Transmission lineUtility-owned in almost every case
- 02Switching stationBreakers and metering at transmission voltage
- 03Main power transformersThe key ownership decision
- 04Medium-voltage switchgearOften customer-owned in either model
- 05Campus distributionCustomer-owned feeders to data halls
A third, hybrid model is common: the customer designs and builds the station to utility standards, then transfers it to the utility, which owns and maintains it afterward. The configuration of the yard (ring bus, breaker-and-a-half) is a separate decision from who owns it, although the utility will usually dictate the configuration of anything it is going to own.
02Cost: who pays up front and who pays every month
With a utility-owned substation, the customer historically paid for the station over time through rates, sometimes with a contribution in aid of construction for facilities built only for that customer. With a customer-owned substation, the customer pays the full capital cost up front and then pays a lower monthly rate, because the utility is not carrying the transformation equipment or its losses.
Utility tariffs show the size of that monthly credit. Entergy Arkansas’s voltage adjustment rider reduces the monthly demand charge by $2.18 per kW, and reduces demand and energy losses by 1.0%, where service is delivered at primary voltage and the customer owns and maintains all transformation facilities.1 Green Mountain Power’s 2026 commercial and industrial schedule lists a 21.65% subtransmission voltage discount, a 23.04% discount for loads above 20 MW and a separate transformer ownership credit.2 Discounts vary widely by utility and change with each rate case, so confirm the current tariff sheet.
The other side of the ledger is shifting. Virginia regulators ordered Dominion Energy to directly assign certain transmission costs, such as a new substation or dedicated line, to the data center customers that trigger them,6 and in August 2026 the State Corporation Commission proposed a process for working out those mechanisms in a separate docket.12 Pennsylvania’s May 2026 model tariff for loads above 50 MW (or 100 MW in aggregate) calls for upgrades to be paid up front through contribution in aid of construction, though the order is guidance utilities may or may not adopt.7 Where those rules apply, a data center pays for its dedicated station either way, and the real question becomes who owns and runs it afterward. Our guides to large-load tariffs and transmission cost allocation cover those rules.
Fig. 2Three ways to own the campus substation
Most common
Utility-owned
- Utility designs, builds, owns and maintains
- Cost through rates and any CIAC
- Delivery at distribution voltage
- Utility’s standards and schedule
Build and transfer
- Customer builds to utility standards
- Utility owns and maintains after handover
- Refunds or credits set by agreement
- Customer controls early procurement
Customer-owned
- Utility delivers at transmission voltage
- Customer pays full capital cost
- Lower demand charges or voltage discounts
- Customer maintains, spares and staffs
03Schedule and control
The strongest argument for customer ownership is time. Black & Veatch reports that utilities often say it will be five years or more before they can provide the circuits and substations for a proposed campus, and that customer ownership lets the owner better control schedule and cost.3 In its own account, a sponsored industry article, the firm says building and running your own station can accelerate development when the interconnecting utility has resource or capital constraints, if regional regulations and the utility allow it.13 Those are a contractor’s claims, not independent data, but they match the logic: an owner can hire its own engineer, order equipment before the utility’s budget cycle, and run substation work in parallel with the building.
Early procurement is where most of the time is won or lost. On a 300 MW hyperscale project, Black & Veatch used progressive design-build to buy long-lead items early and reported that quoted lead times for circuit breakers averaged about 85 weeks.14 Wood Mackenzie projected 2025 supply deficits of about 30% for power transformers and 10% for distribution transformers, with roughly 80% of U.S. power transformers expected to be imported.8 Ownership does not create equipment that does not exist; it only decides whose purchase order is in the queue. See transformer and switchgear lead times for current procurement patterns.
Control also covers design. An owner can choose its own protection philosophy, metering, spare transformer strategy and expansion bays, and can match the station to the campus ramp schedule. A utility will build to its system standards, which are proven but may not anticipate a second phase.
Fig. 3Build-and-transfer sequence
- 01
Agreement
Scope, standards, cost estimate and refund terms.
- 02
Design review
Utility approves drawings and protection.
- 03
Procurement
Customer orders long-lead equipment early.
- 04
Construction
Built to utility specifications and inspected.
- 05
Transfer
Utility accepts ownership and operation.
04How utilities actually handle it
Practice varies by utility, and the utility’s answer usually decides the question before the customer’s preference does. Rocky Mountain Power told Utah regulators that hyperscale data centers take service at 46 kV or higher through a customer-owned substation, which it described as the most cost-effective way to serve large contracted loads, and noted load requests above 100 MW.4 Other utilities insist on owning any station connected to their transmission system.
Build-and-transfer is a middle path. A PG&E advice letter describes an agreement under which Google builds certain facilities and transfers ownership to PG&E once they are completed and approved; to protect other customers, the refund is the lower of a binding cost estimate or actual cost.5 In practice this lets the customer drive the schedule while the utility ends up with an asset it is willing to maintain.
| Item | Utility-owned | Customer-owned |
|---|---|---|
| Capital cost | Rates, CIAC or direct assignment | Customer, up front |
| Point of delivery | Distribution voltage | Transmission voltage |
| Demand charge | Standard rate | Discount or credit where offered |
| Maintenance and testing | Utility | Customer, under NFPA 70B |
| Spare transformer | Utility’s fleet | Customer must stock or contract |
| Outage response | Utility crews | Customer staff or contractor |
05Maintenance, operations and compliance
Ownership is permanent work. NFPA 70B, which for decades was a recommended practice, became a standard in 2023, changing its language from what practices “should” be to what they “shall” be.9 It requires the equipment owner to implement and document an electrical maintenance program, with intervals set by an equipment condition assessment.15 Whether it is enforceable at a given site depends on adoption by the local authority having jurisdiction.9
An owner also needs spares, relay settings management, switching procedures and qualified people on call. A utility can roll a mobile transformer or pull a spare from its fleet; a single customer usually cannot, so customer-owned stations often carry a spare main transformer or a second transformer sized to carry the load. Our guide to redundant utility feeds covers how dual sources change that calculation.
Reliability regulation is the newest factor. NERC posted draft registry criteria for computational loads in April 2026 using 20 MW at 60 kV or above,10 and a revised proposal circulated in August 2026 used at least 50 MW served through equipment connected at 100 kV or above.16 In July 2026, FERC directed NERC to file reliability standards and registration criteria for large computational loads by December 31, 2026.11 Final rules were not in place as of October 2026, but a customer that owns its transmission-voltage station also owns its protection and ride-through settings, which is where those standards are likely to focus. See NERC reliability and large loads.
06How to decide, and what to ask the utility
Customer ownership tends to make sense when the load is large and long-lived, the utility allows it and offers a meaningful transmission-voltage rate, and the owner has (or will contract for) a substation operations team. Utility ownership tends to fit smaller or uncertain loads, utilities that will not accept customer-owned stations, and owners who want the utility to carry restoration risk. Build-and-transfer fits when schedule matters but the owner does not want a permanent high-voltage operation.
- 01Does the utility permit customer-owned substations at this voltage, and under which tariff or rider?
- 02What is the transmission-voltage rate or credit, and how has it changed in recent rate cases?
- 03Will dedicated facilities be directly assigned or billed as contribution in aid of construction regardless of ownership?
- 04Is a build-and-transfer option available, and what are the refund and cost-cap terms?
- 05Who orders the transformers and breakers, and when?
- 06What maintenance, spares and compliance obligations follow ownership?
Raise these at the first meeting in the large-load interconnection process, before the parcel is under contract, since the answer changes how much land the yard needs and how the budget is built. BlackForge screens sites for power path and substation options; you can get a site reviewed.
Common questions
Is it cheaper for a data center to own its substation?
It usually costs more up front and less every month. Tariffs such as Entergy Arkansas’s voltage adjustment rider reduce demand charges for customers that own their transformation,1 but the customer pays the full capital cost and carries maintenance and spares. Whether it pays off depends on the discount, the load factor and the term.
Can any data center build its own substation?
Only where the utility and state rules allow it. Some utilities treat customer-owned stations as the normal way to serve hyperscale loads,4 while others require utility ownership or a build-and-transfer arrangement.5 Ask the utility early.
Does owning the substation make power arrive faster?
It can, because the owner controls design and procurement and does not wait for the utility’s construction program.3 It does not shorten transmission upgrades on the utility’s side or create transformers that are not available.
Who maintains a customer-owned substation?
The customer, either with its own staff or a contractor. NFPA 70B puts the duty to run a documented maintenance program on the equipment owner.15
Will NERC rules apply to a data center that owns its substation?
Possibly. NERC’s 2026 proposals would register large computational loads based on size and connection voltage, and FERC set a December 31, 2026 deadline for standards.11 Confirm the final criteria with counsel.
Notes
- 1.Entergy Arkansas, “Voltage Adjustment Rider (VAR),” 2024. entergyarkansas.com
- 2.Green Mountain Power, “Rate 63/65 Commercial and Industrial, Effective October 1, 2026,” 2026. gmpsnapshot.greenmountainpower.com
- 3.Black & Veatch, “Leading Data Center Provider Turns to Substations to Solve Fast Expansion Needs,” n.d. bv.com
- 4.Rocky Mountain Power (Utah Public Service Commission filing), “Tariff filing, Docket No. 24-035-T01,” 2024. pscdocs.utah.gov
- 5.Pacific Gas and Electric Company, “Advice Letter 7785-E,” n.d. pge.com
- 6.Data Center Dynamics, “Virginia regulators order Dominion Energy to directly assign transmission costs to data centers,” n.d. datacenterdynamics.com
- 7.National Law Review, “Pennsylvania Public Utility Commission Adopts Model Interconnection Tariff for Large Load Customers,” 2026. natlawreview.com
- 8.Wood Mackenzie, “Power transformers and distribution transformers will face supply deficits of 30% and 10% in 2025,” 2025. woodmac.com
- 9.Electrical Safety Foundation, “NFPA 70B,” n.d. esfi.org
- 10.Steptoe, “NERC Releases Proposed Registration Requirements for Computational Load Customers, Signaling Major Shift in Data Center Regulatory Risk,” 2026. steptoe.com
- 11.Willkie Farr & Gallagher, “FERC Orders New Reliability Standards for Data Centers and Other Computational Loads,” 2026. willkie.com
- 12.Sierra Club, “Virginia SCC Proposes Process for Data Center Customers to Cover Transmission Update Costs,” 2026. sierraclub.org
- 13.Data Center Frontier (sponsored, Black & Veatch), “The Benefits of Implementing Substations for Data Centers,” 2024. datacenterfrontier.com
- 14.Black & Veatch, “Powering Hyperscale Data Centers,” n.d. bv.com
- 15.EC&M, “A New Standard for Electrical Equipment Maintenance,” n.d. ecmweb.com
- 16.Texas Reliability Entity, “NERC CLE Proposal,” 2026. texasre.org
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Related guides
More in Decisions and trade-offs
- Buy, Option or Lease: How Developers Secure Data Center Land
- Phased vs. Full Build-Out: How to Stage a Data Center Campus
- New Site or Expand an Existing Campus? How to Decide
- Grid Power vs. On-Site Generation: How to Decide
- One Large Data Center Campus vs. Several Smaller Sites
- Near the Metro or Near the Power? Choosing a Data Center Location
- Build, Lease or Colocate? How to Source Data Center Capacity
- Regulated Utility vs. Competitive Market Sites for Data Centers
- Rural vs. Suburban Data Center Sites: Land, Power, Labor and Local Politics
- Tax Incentives vs. Power Costs: Which Matters More for a Data Center Site?
- Converting a Warehouse or Factory to a Data Center vs. Building New
