A BlackForge Ventures company
BlackForge Data Centers

Decisions and trade-offs

Phased vs. Full Build-Out: How to Stage a Data Center Campus

Most large data center campuses are built in phases, because utility power usually arrives in steps, newer large-load tariffs tie minimum bills to a ramp, and designs change between phases.12 A full build-out can lower unit costs when power, demand and capital are all available up front, but grid connections in the top data center markets now take more than four years.3 The practical answer is often to entitle and size shared infrastructure for the full campus, then build the buildings and IT fit-out in phases.

Last reviewed · 10 min read · BlackForge Data Centers

Key takeaways

  • Power usually sets the phases: AEP Ohio’s approved tariff bills new data centers above 25 MW for at least 85% of contracted capacity for up to 12 years, including a ramp of up to four years.1
  • Phasing spreads capital and lowers demand and technology risk; a full build-out can cut unit cost when power and demand are both firm.
  • Entitle the full campus early and check what vests: North Carolina protects a qualifying multi-phased development for seven years.4
  • Stormwater coverage follows the common plan of development, and generator emissions add up across a campus.56
  • Later phases can adopt newer designs, which matters when one AI rack can draw about 18 times the average rack in Uptime’s survey.78
Public data · Power trackerLarge-load power tracker39 utilities and their data center power rules, from public filings.

01What phasing means on a data center campus

Phasing happens at several layers, and they need not follow the same schedule. Land can be acquired at once or in stages, entitlement can cover the full campus or one building, and the utility can deliver power in steps. Buildings can go up as shells ahead of need, and data halls can be fitted out one at a time as demand arrives.

Fig. 1The layers of a campus that can be phased

  1. 01Land controlBuy, option or lease the whole site, or in stages
  2. 02EntitlementRezoning, master plan or development agreement
  3. 03PowerSubstation, transmission and the utility ramp
  4. 04Site and shared utilitiesGrading, roads, stormwater, water and fiber
  5. 05Building shellsBuilt ahead of need or one at a time
  6. 06Data hall fit-outElectrical, cooling and IT equipment as demand arrives
Simplified. The upper layers are the hardest to change later and are usually secured for the full campus; the lower ones are often built as demand arrives.

A common pattern is to control and entitle the whole site, build the main substation and shared infrastructure for an early phase with room to expand, then add buildings as power and demand allow. At Abilene, Texas, Crusoe began two buildings with more than 200 MW in June 2024 and started six more in March 2025, while the first phase was still being completed, toward a planned eight buildings and about 1.2 GW.9 Meta first planned its Hyperion campus in Louisiana at about 2 GW and in July 2026 raised the target to 5 GW, with investment above $50 billion.10 The real decision is which layers to build ahead and which to build just in time; see campus master planning.

02Phased vs. full build-out, side by side

These are general patterns; which ones matter most depends on how firm the power schedule is and how much demand is contracted.

Comparing build-out strategies
FactorPhased build-outFull build-out
Capital timingSpread over years, matched to demandConcentrated up front
Unit construction costOften higher; repeated mobilizationOften lower; scale and single mobilization
Time to first capacityCan be shorter if phase one is smallLonger before anything is ready
Time to full capacityLonger overallShorter overall, if power is available
Demand riskLower; build as contracts are signedHigher; capacity may sit empty under minimum bills
Technology riskLater phases can adopt newer designs2Design fixed at the start
Power fitMatches stepwise utility deliveryNeeds full capacity available at once
Construction near live operationsYes; needs separation and planningMostly avoided
Entitlement exposureLater phases exposed to rule changes unless vested4Approvals used at once

A full build-out wins most clearly when one user has committed to the whole campus and the utility can deliver all of the power on a firm date. Both are hard to find where grid connections take years.

03Power usually sets the phasing

For large campuses, the utility rarely delivers full capacity on day one. Substations, transmission upgrades and new generation arrive on their own schedules, and JLL’s 2026 outlook puts grid connection times in the top data center markets at more than four years.3 Capacity can arrive in pieces even in established markets: when Dominion Energy resumed new data center connections in eastern Loudoun County, Virginia, in 2022, it did so in smaller increments than customers had planned, with constraints in parts of the area expected to last until new transmission was finished in 2026.11

Utilities increasingly write that schedule into the contract. AEP Ohio’s data center tariff, approved by Ohio regulators in July 2025, requires new data center customers above 25 MW to pay for at least 85% of the capacity they contract for, over terms of up to 12 years that include a ramp of up to four years.1 A build-out that runs ahead of demand then pays for unused capacity, while one that runs behind can strand power. See load ramp schedules, large-load tariffs and power timelines for how ramps are negotiated.

Fig. 2A phased campus following its power steps

Illustrative
  • Rezoning and master plan
  • Substation, first power blockUtility delivers the first block of capacity
  • Phase 1 buildings
  • Transmission upgradeSecond capacity step for later phases
  • Phase 2 buildingsStarts before phase 1 is energized
  • Phase 3 buildings
0204060months
Illustrative example. Building phases follow the utility’s capacity steps and often overlap, as at Abilene, where phase 2 began before phase 1 was complete.9

04Entitle the whole campus, and know what vests

Even when building in phases, it is usually worth entitling the full campus at the start. A master plan approved through a rezoning, planned development or development agreement can set building locations, heights and buffers for every phase. Whether the rules in force at approval also bind later phases depends on state law, and the protection is rarely open-ended:

  • North Carolina vests a qualifying multi-phased development under the rules in effect when the first phase’s site plan is approved, for seven years; later rule changes need the owner’s written consent, with limited exceptions.4
  • Texas reviews the permits a project needs as one series, under the rules in effect when the first application was filed.12 A project with no progress toward completion can be given an expiration date, but not earlier than five years after that application; plat filings, permit applications and spending on roads or utilities count as progress.13
  • Loudoun County, Virginia, ended by-right data center approvals in 2025 but grandfathered projects filed before February 12, 2025, more than 500 feet from homes, if they moved forward without major changes; growth of more than 5% in square footage counts as a substantial modification.14

Without that protection, later phases may face new standards, a moratorium or a more skeptical board, and grandfathering itself can be revisited, as Loudoun supervisors proposed in 2026.15 See moratoriums and local restrictions, and confirm vesting with a land use attorney.

05Size permits and shared infrastructure for the full campus

Several approvals look at the whole site rather than one building, so plan them for full build-out:

  • Stormwater: construction stormwater permits apply to sites that disturb one acre or more, or belong to a larger common plan of development that will; EPA describes a common plan as one contiguous area where separate construction happens at different times, and a zoning request can establish one.5 Size stormwater for full impervious area.
  • Permit cycles: a campus can outlast a permit term. EPA proposed a new construction general permit in August 2026 to replace the 2022 permit, which expires in February 2027.16
  • Air: EPA guidance estimates an emergency generator’s potential emissions at 500 hours a year; one unit rarely makes a site a major source, but EPA cautions that may not hold where many units could run at once.6 Plan the air permit around the full fleet.
  • Noise and corridors: seek noise and setback approvals for all equipment, and secure transmission, fiber, water and sewer routes for full build-out.

The layout must also let construction continue next to operating buildings: substation expansion bays, construction access separate from operations and security perimeters, and laydown areas that stay off future building pads.

06Designs change between phases

A full build-out fixes the design at the start; phasing lets later buildings adopt newer cooling and electrical designs. In January 2025, Microsoft paused early work on the second phase of its Mount Pleasant, Wisconsin, campus to “evaluate scope and recent changes in technology” and how they might affect its facility design.2

Rack power shows the pace of change. Uptime Institute’s 2026 survey of about 800 owners and operators found the most common rack density was 11 kW and the average, excluding purpose-built facilities above 30 kW, 7.8 kW.7 One NVIDIA GB300 NVL72 rack is listed at up to 140 kW,8 and JLL reports that only a sliver of North America’s scarce vacant space can handle racks that dense, which need liquid cooling.17

Fig. 3Rack power: survey figures vs. one AI rack

  • Average rack, Uptime 2026 survey7.8
  • Most common rack, Uptime 202611
  • NVIDIA GB300 NVL72 rackup to 140

kW per rack

Uptime’s average excludes purpose-built facilities above 30 kW; the GB300 value is one vendor’s listed maximum for a single rack, not a typical load.78

For a phased campus, keep shared infrastructure flexible: substation capacity, routes for chilled water or liquid cooling, floor loading and space for heat rejection sized for denser later buildings. See air vs. liquid cooling.

07Where phased campuses run into trouble

Phasing reduces some risks and creates others. Most problems come from treating each phase as a separate project rather than as part of one plan:

  • Shared infrastructure built only for phase one, such as a substation with no room for more transformers or a water line too small for later buildings.
  • Approvals that cover the first building only, leaving later phases to a new hearing under new rules.
  • Phase milestones in a development or incentive agreement that assume power will arrive on time, with no extension if it does not.
  • Generator fleets added building by building until the campus crosses an air permit threshold that triggers a more demanding review.6
  • Changes to a later phase large enough to count as a substantial modification, which can cost a project its grandfathered status.14
  • Neighbors who accepted phase one but were not told how large the full campus would be.
  • Land kept for later phases that is used for laydown or spoil, compacting soils or blocking future pads.

Most of these come from early decisions made under pressure to get the first building online. A short review of the full build-out plan before phase one design is frozen catches many of them.

08How to decide

What tips it toward phasing

  • Power arrives in steps, or the final capacity is uncertain.
  • Demand is contracted over time, or the end users are not yet signed.
  • Cooling and rack density requirements are changing.
  • Capital is easier to raise phase by phase.

What tips it toward a full build-out

  • Full power is available on a firm schedule.
  • A single user has committed to the whole campus.
  • Construction cost savings at scale are significant for that design.
  • The site is constrained, and construction next to live operations would be difficult.

Fig. 4Power certainty vs. demand certainty

Partly or not signed ← Demand under contract → Committed

Phase to the power ramp

Build each phase as a capacity step arrives; pre-build shared infrastructure.

Full build-out candidate

One committed user and firm power; scale savings are real.

Entitle it all, build small

Secure land, approvals and the power request; build phase one only.

Shells ahead, fit-out later

Build substation and shells; fit out data halls as contracts sign.

Stepwise or uncertain ← Full power on a firm date → Firm

A way to frame the choice, not a rule. Wherever power arrives in steps, the left column applies.
  1. 01Map the utility’s delivery schedule and the ramp, minimum-bill and exit terms in the service agreement.1
  2. 02Compare that schedule with contracted and expected demand.
  3. 03Decide which layers to build ahead: land, entitlement, substation, shell, fit-out.
  4. 04Confirm the entitlement path protects later phases, or plan for rule changes.
  5. 05Test the site layout for safe construction next to operating buildings.
  6. 06Price both strategies, including carrying costs and minimum bills, not just construction cost.

The answer usually starts on the power side. If you are weighing a campus plan against what the utility can deliver, you can get a site reviewed before phase one is designed.

CalculatorLand for a load →CalculatorIT load to grid demand →

Common questions

Why are data center campuses built in phases?

Mostly because power arrives in steps. Substations, transmission upgrades and new generation take time, grid connections in the top markets now take more than four years, and utilities often deliver capacity on a contractual ramp.31 Phasing also spreads capital, matches construction to signed demand and lets later buildings adopt newer designs. The trade-off is higher unit cost and construction next to operating buildings.

Should you entitle the full campus even if building in phases?

Usually yes. A master plan approved through a rezoning, planned development or development agreement can fix building locations, heights and buffers for every phase, and some states vest the rules for multi-phase projects; North Carolina does so for seven years.4 Planning stormwater, noise, air permits and easements for the full campus also avoids reopening approvals later.

How many phases does a data center campus have?

There is no standard number. It depends on the campus size, the utility’s delivery schedule, the number of buildings and how demand is contracted. Abilene was planned in two phases of two and six buildings, while Meta’s Hyperion grew from a 2 GW plan to a 5 GW target.910 Fit-out inside each building is often phased separately.

Is a full build-out cheaper than phasing?

Per unit of capacity, it often is, because of scale and a single construction mobilization. But carrying costs, unused capacity, minimum bills that can run at 85% of contracted capacity under newer tariffs,1 and the risk of a design becoming outdated can offset the savings. Compare total cost over the full schedule, not just construction.

Notes

  1. 1.POWER Magazine, “Regulator Approves AEP Ohio’s Landmark Data Center Tariff,” 2025. powermag.com
  2. 2.Data Center Dynamics, “Microsoft pauses construction on part of data center site in Mount Pleasant, Wisconsin,” 2025. datacenterdynamics.com
  3. 3.Latitude Media, “Three major risks slowing the $3T data center boom,” 2026. latitudemedia.com
  4. 4.North Carolina General Assembly, “G.S. 160D-108: Permit choice and vested rights,” n.d. ncleg.gov
  5. 5.U.S. Environmental Protection Agency, “CGP Flowchart: Do I Need a Permit?,” 2022. epa.gov
  6. 6.U.S. Environmental Protection Agency, “Calculating Potential to Emit (PTE) for Emergency Generators,” 1995. epa.gov
  7. 7.Data Center Knowledge, “AI Drives Data Center Uncertainty in Uptime’s 2026 Survey,” 2026. datacenterknowledge.com
  8. 8.GIGABYTE, “NVIDIA GB300 NVL72,” n.d. gigabyte.com
  9. 9.Crusoe, “Crusoe expands AI data center campus in Abilene to 1.2 gigawatts,” 2025. crusoe.ai
  10. 10.Data Center Dynamics, “Meta expands data center campus in Richland Parish, Louisiana, to 5GW, will invest $50bn,” 2026. datacenterdynamics.com
  11. 11.Data Center Frontier, “Dominion Resumes New Connections, But Loudoun Faces Lengthy Power Constraints,” 2022. datacenterfrontier.com
  12. 12.Texas Statutes (Public.Law), “Texas Local Government Code Chapter 245, Issuance of Local Permits,” n.d. texas.public.law
  13. 13.Texas Statutes (Public.Law), “Tex. Local Gov’t Code Section 245.005,” n.d. texas.public.law
  14. 14.McGuireWoods, “Loudoun County Eliminates By-Right Use for Data Centers, Increasing Development Hurdles,” 2025. mcguirewoods.com
  15. 15.Loudoun County, Virginia, “Briskman and TeKrony Seek to End 2025 Data Center Grandfathering Exceptions,” 2026. loudoun.gov
  16. 16.U.S. Environmental Protection Agency, “Proposed 2027 Construction General Permit (CGP) and Related Documents,” 2026. epa.gov
  17. 17.Data Center Knowledge, “For High-Density AI, Available Data Center Space May Not Be Usable,” 2026. datacenterknowledge.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Terms in this guide

Related guides

More in Decisions and trade-offs

Guide 2 of 14 in Decisions and trade-offs · all 242 guides · glossary · calculators