A BlackForge Ventures company
BlackForge Data Centers

Water, gas & fiber

Air vs. Liquid Cooling: What Each Needs From a Site

Air cooling still serves most data center racks, which average under 10 kW, but AI racks such as Nvidia’s GB200 NVL72 draw around 120 kW and need liquid cooling.12 Liquid cooling concentrates more megawatts on each acre, so power becomes the constraint sooner, and warm-water designs let dry coolers take over more of the work from chillers.3 Both approaches still reject heat outdoors, so water, mechanical yard space and noise remain site questions either way, and most new campuses plan for a mix.

Last reviewed · 9 min read · BlackForge Data Centers

Key takeaways

  • Most racks are still air-cooled: Uptime Institute’s 2026 survey put average density at about 7.8 kW, excluding purpose-built high-density sites.1
  • AI racks around 120 kW are far past the roughly 50 kW where air cooling is reported to stop being practical, so liquid-cooled campuses need much more power per acre.24
  • Warm facility water lets dry coolers replace chillers for more of the year; Nvidia says its Vera Rubin systems can run on 45°C water with no water chillers.3
  • Removing evaporation trades water for energy: Microsoft’s zero-water design avoids more than 125 million liters a year per data center at a nominal rise in energy use.5
  • Dense AI loads change how a campus behaves on the grid, and NERC issued a rare Level 3 alert on large computational loads in May 2026.6
  • Liquid-cooled buildings need more structure, piping and CDU space; one immersion tank reference design specifies a floor loading capacity of 1,200 kg per square meter.7

01How air and liquid cooling differ

Air cooling moves heat from servers into air, then from that air into a chilled water loop or directly outdoors. Computer room air handlers, fan walls and containment aisles do the work inside the data hall. It has been the standard for decades, suits traditional rack densities well and is still what most operators rely on.8

Liquid cooling brings a fluid much closer to the heat source. The main forms are:

  • Rear-door heat exchangers, which cool the air leaving a rack with a water coil. A bridge between air and liquid.
  • Direct-to-chip cooling, where cold plates on processors carry heat into a liquid loop. In Nvidia’s GB200 NVL72 rack, the liquid loop serves the CPUs, GPUs and NVLink switches, while networking and storage stay on air.9
  • Immersion cooling, where servers sit in tanks of dielectric fluid in single-phase or two-phase designs. Two-phase systems have relied on PFAS fluorochemicals, and 3M’s decision to exit PFAS manufacturing by the end of 2025 has clouded their outlook.10

In liquid systems, coolant distribution units (CDUs) separate the rack-side coolant loop from the facility water loop. The facility loop then rejects heat outdoors through dry coolers, cooling towers or chillers, just as in an air-cooled building. ASHRAE’s guidelines classify facility water by its maximum supply temperature, now labeled W17, W27, W32, W40, W45 and W+, and the W40 class was added because many manufacturers design for water at about 40°C.11

Fig. 1How heat leaves a liquid-cooled rack

  1. 01Chips and cold platesProcessors pass heat into coolant at the rack.
  2. 02Rack coolant loopTreated fluid kept separate from building water.
  3. 03Coolant distribution unitHeat exchanger and pumps between the two loops.
  4. 04Facility water systemBuilding loop rated by supply temperature, W17 to W+.
  5. 05Outdoor heat rejectionDry coolers, cooling towers or chillers in the yard.
Simplified direct-to-chip path. Networking and storage parts often stay on air, and ASHRAE classes facility water by its supply temperature.911

02Density changes how much power a site needs per acre

The biggest site effect of liquid cooling is density. Most racks in service still draw modest power: Uptime Institute’s 2026 survey put the average at about 7.8 kW, excluding purpose-built sites above 30 kW, only 0.3 kW higher than a year earlier.1 Its 2025 survey found growth concentrated in racks of 10 to 30 kW, with only a small share of sites running higher.12 Air cooling stops being practical somewhere above that range; Data Center Knowledge reports Uptime’s view that the limit is around 50 kW per rack.4

AI hardware sits far beyond it. A GB200 NVL72 rack draws on the order of 120 kW, and SemiAnalysis expected many buyers to choose a two-rack version of the system because their facilities could not deliver 120 kW to a single rack.2 Our guides to AI data center site requirements, high-density GPU racks and rack density trends cover the hardware and its demands in depth.

Fig. 2Power per rack: typical vs. AI

  • Average rack (Uptime, 2026)7.8
  • Reported air-cooling limitabout 50
  • GB200 NVL72 rackabout 120

kW per rack

The average excludes purpose-built sites above 30 kW.1 The air-cooling limit is Uptime’s view as reported by Data Center Knowledge, and real limits depend on design.4 The GB200 figure is SemiAnalysis’s estimate.2

Higher density means the same building footprint can draw much more power. A tract that would hold a modest air-cooled campus could hold a campus several times larger in megawatts if it is liquid-cooled. That moves the binding constraint even further toward power delivery: substation capacity, transmission voltage and the utility’s ability to serve the ramp. Our guide to data center power requirements explains how IT load and PUE translate into the request.

Density also changes how the load behaves. AI training can swing a campus’s demand by hundreds of megawatts almost instantly, a risk a NERC white paper rated “high likelihood, high impact,”13 and in May 2026 NERC issued a rare Level 3 alert asking transmission owners, balancing authorities and other registered entities to act on risks from large computational loads.6 Expect utilities to ask about ramp rates, load swings and ride-through, not only peak demand.

03What each approach needs from a site

Site implications of air and liquid cooling
Site factorAir-cooled campusLiquid-cooled campus
Power per acreLower; more land per MWHigher; AI racks draw around 120 kW each
Building formLarger halls and air handling volumeSmaller halls per MW; more space for piping, CDUs and electrical rooms
StructureStandard data center floor loadsHeavier loads, especially for immersion tanks and dense racks
Heat rejectionChillers, towers or economizers; climate-sensitiveWarm water allows more dry cooling hours; still needs outdoor equipment
Water useRanges from minimal to high, depending on heat rejectionOften lower with dry or closed-loop heat rejection, but depends on design
Mechanical yardLarge, often on roofs or ground yardsConcentrated around fewer, denser buildings
Electrical yardSized to lower MW per buildingMore transformers and switchgear per building
NoiseFans on chillers, dry coolers and air handlersSimilar sources, concentrated in a smaller area

These are tendencies, and many buildings combine air and liquid systems, since even liquid-cooled racks shed some heat to air. In Uptime’s 2025 cooling survey, about a fifth of operators reported using direct liquid cooling somewhere, against three quarters using perimeter air cooling, so mixed buildings are the norm.8

04Water and climate sensitivity

Liquid cooling can often run with warmer facility water than chilled-water air systems. Warmer water means outdoor air can reject the heat through dry coolers for more hours of the year, without evaporation or compressors. At CES in January 2026, Nvidia’s chief executive said its Vera Rubin systems can be cooled with 45°C water and that at that temperature no water chillers are necessary.3 In effect, liquid cooling widens the range of climates where a low-water design works. Our guide to climate and cooling in site selection covers economizer hours and design days.

Climate still sets limits. A dry cooler can only bring water to a few degrees above the outdoor air temperature, and Network World noted that 45°C is only about a degree above Las Vegas’s 2025 summer peak.14 In the hottest markets, some supplemental cooling may still be needed on peak days, and those days size the heat rejection plant.

Removing evaporation trades water for energy. Since August 2024, Microsoft’s new data center designs use chip-level cooling in a closed loop, which it says avoids more than 125 million liters of water a year per data center; replacing evaporative cooling with mechanical cooling raises PUE, but Microsoft says warmer-water chips keep the increase in annual energy use nominal.5 The water need comes from the heat rejection choice, not the label on the data hall, as our guide to closed-loop and waterless cooling explains.

Fig. 3The water and energy trade-off in heat rejection

Low ← Cooling energy → High

Mechanical cooling

Air-cooled chillers: little water, more power on hot days.

Water-cooled chillers

Towers plus compressors: water and power both rise in hot weather.

Warm-water dry cooling

Liquid loops near 40–45°C with dry coolers in mild climates.

Evaporative cooling

Towers or direct evaporative: least power, most water.

Low ← Water use → High

A way to frame the trade-off, not a rule; climate moves every cell. Cutting water use tends to raise energy use.5

05Building, structure and campus layout

Liquid cooling changes the building as much as the site. Floors may need to carry heavier racks or fluid-filled tanks: Intel’s reference design for a 12U single-phase immersion tank weighs 236 kg before coolant and specifies a floor loading capacity of 1,200 kg per square meter, roughly 245 pounds per square foot, for the tank and its CDU.7 Piping runs to every rack, with leak detection and isolation valves. CDUs need floor space, and the facility water loop needs pumps, storage and room for redundancy, often designed to N+1 or 2N like the electrical systems.

  • Single-story buildings on slab handle heavy loads more easily; multistory designs need more structural investment.
  • Denser buildings can mean fewer buildings per campus, but each needs more electrical and mechanical yard nearby.
  • Heat rejection equipment may move from roofs to ground yards for weight and access reasons, which uses land.
  • Truck access and laydown areas matter for large CDUs, tanks and coolant deliveries.

For land planning, the result is that a liquid-cooled campus does not simply shrink in proportion to its density. Setbacks, substations, stormwater, roads and mechanical yards still take space, so buildable acreage and layout still matter. Our guides to cooling plant and equipment yard space and slope, soils and geotechnical review cover those pieces, and warmer return water can also make heat reuse more practical.

06Planning a site for both

Most new campuses expect a mix: air-cooled space for general computing and networking, and liquid-cooled halls for high-density workloads. The proportions may change over a campus’s life, sometimes within a single building. Adoption is still uneven: Uptime found direct liquid cooling spreading slowly, with cost, a lack of industry standards and the risk of failure among the barriers operators cite.8 A site plan that supports both keeps more buyers interested and adapts better as technology changes.

  1. 01Size the power request for the higher-density case, or confirm a path to expand.
  2. 02Ask the utility how it will study fast load swings and what ride-through or ramp limits apply to AI loads.
  3. 03Screen water across a range from dry to evaporative heat rejection.
  4. 04Reserve mechanical and electrical yard space next to each building pad.
  5. 05Check geotechnical conditions for heavier floor and equipment loads.
  6. 06Review noise limits at the property line for the full set of outdoor equipment, as covered in our guide to noise, setbacks and buffers.

When we screen a site, we do not assume a cooling design unless the buyer has chosen one. We test whether the site works across the plausible range, and we note where it does not. If you are weighing a site for AI workloads, you can get a site reviewed.

CalculatorWhite space to IT load →CalculatorCooling water use →CalculatorFiber latency & distance →

Common questions

Does liquid cooling use less water than air cooling?

Often, but not always. Warmer facility water lets dry coolers reject heat for more of the year without evaporation, and Microsoft says its closed-loop, chip-level design avoids more than 125 million liters of water a year per data center.5 But some liquid-cooled campuses still use cooling towers, and some air-cooled campuses use almost no water. Water use depends mainly on how heat is rejected outdoors.

Does a liquid-cooled data center need less land?

It needs less building area per megawatt, because racks are much denser. But the campus does not shrink in proportion. Substations, electrical and mechanical yards, roads, setbacks and stormwater still need space, and denser buildings need more equipment around each one. The bigger effect is that a liquid-cooled campus needs more power per acre, so power usually becomes the limit sooner.

What is direct-to-chip liquid cooling?

Direct-to-chip cooling attaches cold plates to processors and other hot components, and a liquid loop carries the heat away. Coolant distribution units separate that loop from the facility water system, which rejects the heat outdoors. Other parts still shed heat to air; in a GB200 NVL72 rack, networking and storage stay air-cooled.9 It is one of the main approaches for high-density AI racks.

Do liquid-cooled data centers still need chillers?

Not always. With warm facility water, dry coolers can reject heat for much or all of the year, and Nvidia says its Vera Rubin systems can run on 45°C water without water chillers.3 Peak summer temperatures in the hottest markets come close to that level,14 so some designs keep supplemental cooling, and air-cooled equipment in the same building may still need chilled water.

Should a data center site be planned for air or liquid cooling?

In most cases, both. Many campuses mix air-cooled and liquid-cooled space, and the balance can shift over the life of the campus. A site that can deliver power for the high-density case, supply water across a range of designs, and fit mechanical and electrical yards next to each building will suit more buyers and adapt better to changes in cooling technology.

Notes

  1. 1.Data Center Knowledge, “AI Drives Data Center Uncertainty in Uptime’s 2026 Survey,” 2026. datacenterknowledge.com
  2. 2.SemiAnalysis, “GB200 Hardware Architecture and Component,” 2024. newsletter.semianalysis.com
  3. 3.Facilities Dive, “No chillers needed for Vera Rubin server racks: Nvidia CEO,” 2026. facilitiesdive.com
  4. 4.Data Center Knowledge, “AI Rack Density’s Real Limits: Power, Cooling, Failure Risk,” 2026. datacenterknowledge.com
  5. 5.Microsoft, “Sustainable by design: Next-generation datacenters consume zero water for cooling,” 2024. microsoft.com
  6. 6.Davis Wright Tremaine, “NERC Signals Rare Level 3 Alert on Large Loads and Data Centers,” 2026. dwt.com
  7. 7.Intel, “Intel Open IP Immersion Cooling Reference Solutions, Single Phase, Product Brief (12U),” n.d. cdrdv2-public.intel.com
  8. 8.Uptime Institute, “DLC adoption remains slow and steady,” 2025. intelligence.uptimeinstitute.com
  9. 9.CUDO Compute, “NVIDIA GB200 NVL72,” n.d. cudocompute.com
  10. 10.HPCwire, “PFAS Regulations, 3M Exit to Impact Two-Phase Cooling in HPC,” 2023. hpcwire.com
  11. 11.Upsite Technologies, “Major Changes to ASHRAE’s Fifth Edition of Thermal Guidelines, Part 3: Liquid Cooling Chapter Updates,” n.d. upsite.com
  12. 12.Uptime Institute, “Uptime Institute Global Data Center Survey 2025,” 2025. intelligence.uptimeinstitute.com
  13. 13.E&E News, “AI power demand creates ‘high likelihood, high impact’ grid risks,” n.d. eenews.net
  14. 14.Network World, “Raising the temp on liquid cooling,” 2026. networkworld.com

Have a site in mind?

Get a straight answer on your land.

Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.

Start a conversation →

This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.

Terms in this guide

Related guides

More in Water, gas & fiber

Guide 6 of 18 in Water, gas & fiber · all 242 guides · glossary · calculators