Key takeaways
- Blowdown is the minimum flow bled from a recirculating cooling system to remove built-up dissolved solids, so it is saltier than the water that went in.1
- Any nondomestic user of a public sewer is bound by federal prohibitions on discharges that pass through or interfere with the treatment plant, permit or not.7
- Direct discharge to surface water needs NPDES coverage; many states offer general permits for cooling tower blowdown, with eligibility limits.189
- In Goodyear, Arizona, Microsoft agreed in 2023 to pay $36 million toward a roughly $90 million wastewater plant expansion and to air-cool later buildings.4
- Utilities are pausing or studying data center sewer service: Ypsilanti’s authority adopted a 12-month moratorium in April 2026.6
01Where data center wastewater comes from
A data center produces two very different wastewater streams. The first is sanitary flow from restrooms and kitchens, which is small because staffing is light. In one recent Texas case, a planned data center complex estimated about 30,200 gallons per day of sanitary sewer use and told the city that was less than the housing previously planned for the tract.10 The second is process wastewater from cooling, and for a campus using evaporative cooling it can be far larger.
Cooling towers reject heat by evaporating water. Evaporation leaves minerals behind, so the recirculating water grows more concentrated over time. To keep scale and corrosion in check, operators continuously bleed off part of that water and replace it with fresh make-up water. The bleed is called blowdown, which state permits define (following the federal definition at 40 CFR 401.11) as the minimum discharge of recirculating water needed to remove the buildup of dissolved materials.1 Other process streams can include reject water from reverse osmosis or softening systems and periodic drain-downs for maintenance.
Blowdown volume depends on the cooling design, the climate and the quality of the make-up water, so it should come from the mechanical engineer, not a rule of thumb. Our guide to data center water requirements covers the demand side. The point for siting is that every gallon of make-up water that is not evaporated becomes wastewater, and it is more mineralized than what the utility delivered. Black & Veatch, describing a data center blowdown project, notes that sampling the actual blowdown was part of deciding whether it could go to the local plant without added treatment.3
Fig. 1Three paths for cooling blowdown
Most common
Sewer to a POTW
- Governed by the local sewer use ordinance
- Industrial user permit and local limits
- Needs pipe and plant capacity
- Utility may charge for capacity and flow
NPDES permit
Direct discharge
- Outfall to a stream or storm drain
- State general or individual permit
- Limits tied to the receiving water
- Monitoring and reporting duties
Treat and reuse on site
- Blowdown treated and returned to the towers
- Leaves a smaller concentrated reject
- More equipment, power and operations
02Sewer discharge and industrial pretreatment
Most data centers send blowdown to a publicly owned treatment works, or POTW, through the city sewer. That discharge falls under the National Pretreatment Program, a component of the NPDES program run cooperatively by EPA, states and local utilities.2 As of the EPA program page cited here, 37 states were approved to oversee POTW pretreatment programs, with EPA regions handling the rest.2 Where a POTW has an approved local program, it issues the industrial user permit; where it does not, the state typically does.11
Rules that apply to every user
Federal general and specific prohibitions apply to all nondomestic dischargers, whether or not the POTW has an approved program and whether or not the user holds a permit.7 The core test is whether a discharge causes pass through (pollutants that exit the plant and cause a violation of its NPDES permit) or interference (disruption of treatment or sludge handling).12 Specific limits a POTW develops for its own plant, called local limits, are treated as federal pretreatment standards for enforcement purposes.12
Will the data center be a significant industrial user?
EPA’s definition of a significant industrial user (SIU) includes a user that discharges an average of 25,000 gallons per day or more of process wastewater, a user whose process flow is 5% or more of the plant’s average dry-weather hydraulic or organic capacity, and any user the POTW designates because it could harm the plant or cause violations.13 The 25,000-gallon count excludes sanitary, noncontact cooling and boiler blowdown flows.13 Whether cooling tower blowdown counts toward the threshold is therefore a question for the control authority, but a large campus can be designated on the capacity or harm tests regardless. SIU status brings a permit, sampling, reporting and inspections.13
The parameters that matter most for blowdown are usually not the ones that concern a food plant. Dissolved solids, temperature, pH and residual treatment chemicals (biocides, scale and corrosion inhibitors) are the typical discussion points. The plant’s biology can matter too: a Nevada permit fact sheet records a facility that proposed sending blowdown to a storm drain outfall instead of the nearby treatment plant, because the plant works best with nutrient-rich influent and the blowdown lacked nutrients.14
03Direct discharge under an NPDES permit
Where no sewer is available, or the POTW cannot take the flow, a site may discharge blowdown to surface water. That requires NPDES coverage from the state (or EPA in non-delegated states). Many states issue general permits that cover noncontact cooling water and cooling tower blowdown, which is faster than an individual permit when the facility fits the eligibility terms.
- North Carolina’s NCG500000 covers noncontact cooling water and cooling tower and boiler blowdown, excludes major dischargers and Outstanding Resource Waters, and notes that open recirculating cooling discharges to water supply waters may need an individual permit.1
- Oregon’s 100-J general permit covers recycled noncontact cooling water and cooling tower blowdown, which it describes as the bleed-off that prevents solids buildup.8
- Ohio’s general permit OHN000006 is limited to discharges under 5% of the receiving stream’s seven-day, ten-year low flow.9
That last condition illustrates the real siting issue. A small creek that runs low in late summer may not be able to take a continuous discharge without an individual permit and tighter limits, and the summer is when cooling loads peak. A larger river or an existing permitted outfall on a former industrial site can be a meaningful asset. Our guides to stormwater management and greenfield vs. brownfield sites cover related permits and legacy outfalls.
Black & Veatch describes one data center project where the work included designing a 2.5-mile pipeline to carry blowdown to a local treatment plant and modifying an NPDES permit, which shows that the two paths are often evaluated together.3
04Sewer and treatment plant capacity
Pretreatment rules address what is in the wastewater. Capacity addresses how much of it the system can carry and treat. A plant may have headroom on paper while the gravity sewer between the site and the plant is full, or a lift station is undersized. Our guide to municipal water and sewer capacity covers how utilities measure headroom; recent cases show how it plays out for data centers.
Fig. 2Recent data center wastewater commitments
In Goodyear, Arizona, the city lacked sewer line and plant capacity for more data center wastewater. Under an updated development agreement approved in March 2023, Microsoft agreed to pay $36 million toward a roughly $90 million expansion of the 157th Avenue treatment plant, in place of wastewater impact fees, securing 1.2 million gallons per day of capacity; to post more than $5 million in assurance for a dedicated discharge line; and to air-cool data centers built later on the site.4
In Shreveport, Louisiana, a council packet estimated that a proposed facility would send about 2.5 million gallons per day of wastewater and blowdown back to the city system. Under the draft agreement the developer would build the needed improvements, and the sewer charge was set at 35% of metered water use.5
Peaks matter as much as averages. Santa Clara, California, hired a consultant to study “extreme discharge events” from data center cooling during heat waves, when many facilities could raise discharges at once, and the study could lead to restrictions on how data centers dispose of wastewater.15
05Moratoriums, tax incentives and public scrutiny
Sewer service has become a lever in local data center debates. In April 2026 the Ypsilanti Community Utilities Authority in Michigan approved a 12-month moratorium on new water and sewer service for large data centers while it studies capacity.6 Bridge Michigan reported that local officials tied the dispute to the state’s data center tax incentives, which require hookup to municipal water, arguing that system capacity had not been assessed when the incentives passed.16
For a site, that means a sewer connection should be treated like an entitlement, with council or board approval, public hearings and conditions. Our guide to community engagement covers how water and sewer concerns surface, and the tax incentives guide covers where incentives carry utility conditions.
06How to screen a site for wastewater
Fig. 3Settling the discharge path for a site
- 01
Estimate flows
Average and peak blowdown for each cooling option.
- 02
Find the receiver
Nearest sewer, lift stations, POTW and its permit.
- 03
Ask the control authority
SIU status, local limits and sampling duties.
- 04
Test the fallback
NPDES general permit eligibility for nearby waters.
- 05
Put it in writing
Sewer service agreement, permit and cost sharing.
- 01Get blowdown estimates from the cooling engineer for each design under consideration, including summer peaks.
- 02Identify the POTW, the route from the site, and any lift stations or interceptors along it.
- 03Ask the utility whether it has an approved pretreatment program, what its local limits are and whether it would designate the facility an SIU.
- 04Ask whether the plant and the conveyance system have capacity, whether any moratorium or study is pending, and who pays for upgrades (see impact fees and connection fees).
- 05If the sewer is uncertain, check the state’s cooling water general permit and the low flow of nearby streams.
- 06Make wastewater acceptance a condition in the due diligence period, alongside the will-serve letter for water.
Confirm conclusions with the utility’s pretreatment coordinator, the state permitting agency and a wastewater engineer. If you want water, wastewater, power and land looked at together, you can get a site reviewed.
Common questions
What is cooling tower blowdown?
It is water deliberately drained from a recirculating cooling system to keep dissolved minerals from building up as water evaporates. Permits define it as the minimum discharge needed to remove that buildup.1 It is replaced with fresh make-up water.
Can a data center discharge blowdown to the city sewer?
Usually, if the utility has capacity and the discharge meets its sewer use ordinance and local limits. All nondomestic users must avoid pass through and interference at the plant.712 Large users may need an industrial user permit.13
Does a data center need an NPDES permit?
Only for discharges to surface water, such as a blowdown outfall to a stream, plus construction and industrial stormwater where applicable. Many states cover cooling water and blowdown under general permits with eligibility limits.19 Sewer discharges are handled by the POTW’s pretreatment program instead.2
Who pays for sewer upgrades for a data center?
Increasingly, the developer. Microsoft agreed to fund $36 million of a Goodyear plant expansion, and a Shreveport draft agreement had the developer build the needed improvements.45
Can a city refuse sewer service to a data center?
Yes. Utilities can decline service, attach conditions or pause new connections. Ypsilanti’s utility authority approved a 12-month moratorium on new water and sewer service for large data centers in 2026.6
Notes
- 1.North Carolina Department of Environmental Quality, “NCG500000 Fact Sheet 2025,” 2025. deq.nc.gov
- 2.U.S. Environmental Protection Agency, “National Pretreatment Program,” n.d. 19january2017snapshot.epa.gov
- 3.Black & Veatch, “Data Center Owner Overcomes Complex Water Challenges and Achieves Sustainability Goals,” n.d. bv.com
- 4.Arizona Technology Council (reprinting Phoenix Business Journal), “Microsoft agrees to make data centers air cooled amid water infrastructure challenges in Goodyear,” 2023. aztechcouncil.org
- 5.KSLA News 12, “Documents show proposed Shreveport data center would use 7.5 million gallons of water daily,” 2025. ksla.com
- 6.WNDU 16 (Associated Press), “Michigan utility OKs 12-month ban on supplying water for data centers,” 2026. wndu.com
- 7.U.S. Environmental Protection Agency, “Pretreatment Standards and Requirements: General and Specific Prohibitions,” n.d. epa.gov
- 8.Oregon Department of Environmental Quality, “NPDES General Permit 100-J (Cooling Water) Fact Sheet,” n.d. oregon.gov
- 9.Ohio Environmental Protection Agency, “General Permit OHN000006 for Noncontact Cooling Water,” n.d. dam.assets.ohio.gov
- 10.Community Impact, “Proposed data center seeks wastewater services from Hutto,” n.d. communityimpact.com
- 11.Kansas Department of Health and Environment, “NPDES Pretreatment Program,” n.d. kdhe.ks.gov
- 12.Legal Information Institute, Cornell Law School, “40 CFR § 403.5: National pretreatment standards: Prohibited discharges,” n.d. law.cornell.edu
- 13.U.S. Environmental Protection Agency, “Pretreatment Roles and Responsibilities: Industrial Users,” n.d. 19january2025snapshot.epa.gov
- 14.Nevada Division of Environmental Protection, “NV0024262 Fact Sheet Draft 2,” n.d. ndep.nv.gov
- 15.Data Center Dynamics, “City of Santa Clara to study impact of data center discharge on sewage system,” n.d. datacenterdynamics.com
- 16.Bridge Michigan, “In Ypsilanti, battle lines draw over data centers and sewage,” n.d. bridgemi.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Related guides
More in Water, gas & fiber
- Natural Gas Pipeline Access for Data Center Sites
- Fiber Connectivity for Data Center Sites
- Climate, Cooling and Data Center Site Selection
- Air vs. Liquid Cooling: What Each Needs From a Site
- Dark Fiber vs. Lit Services: Which Does a Data Center Site Need?
- How Long-Haul and Subsea Fiber Routes Affect Data Center Site Selection
- Water Stress and Drought Risk in Data Center Siting
- Fiber Route Diversity and Latency for Data Center Sites
- Internet Exchange Points and Carrier Hotels: Why They Shape Data Center Markets
- Latency Requirements by Workload: Where Data Center Proximity Matters
- Firm Natural Gas Transportation for Data Center On-Site Power
- Data Center Heat Reuse and District Heating: EU Rules, Nordic Examples and U.S. Site Implications
