Key takeaways
- Proximity to a pipeline says little about whether it has capacity to spare at the delivery point you need.
- Interstate pipelines are regulated by FERC, while intrastate pipelines and local gas utilities answer to state commissions, and each serves a different role.5
- A tap, lateral and meter station are separate pieces of infrastructure. Under FERC’s blanket certificate program, as of 2026, small interstate projects up to $14.5 million can proceed automatically and, under a temporary waiver, larger ones up to $61.65 million with prior notice; higher limits are proposed.6
- Firm transportation is what makes gas-fired power reliable; interruptible service can be curtailed when the system is tight.3 Even firm service failed some generators in Winter Storm Elliott when supply froze off, so backup fuel still matters.7
- A pipeline easement on the site reduces buildable area, and a large occupied building near a line can change its federal class location.4
01When does a data center site need natural gas?
A grid-served data center with diesel backup needs little or no gas. Gas becomes a siting criterion when the project plans to generate power on site, whether as bridge power while waiting for the utility, as a permanent behind-the-meter plant, or as gas-fired backup. Our guide to on-site generation and bridge power explains those roles.
The trend is toward more gas at the site, not less. Kinder Morgan has argued that grid operators who cannot deliver capacity quickly enough are pushing data centers toward dedicated gas-fired plants beside the load.8 Williams has reported an agreement, Project Atlas, to deliver up to 164 million cubic feet of gas a day to a data center in the Northeast.2
The gas volumes involved can be large. In February 2025, Energy Transfer agreed to supply up to 450,000 MMBtu a day of firm gas to a planned campus near San Marcos, Texas, which the companies said could support roughly 1.2 GW, subject to the developer reaching a final investment decision.1 That puts a large campus in the same category as a power plant, which is why many sites near small distribution lines cannot support it.
Fig. 1Forecasts of 2030 U.S. data center gas demand
- Tudor Pickering Holt1.3–8.5
- Kinder Morgan3–6
- Enverus (all-gas ceiling)up to 4.1
- EQT (power burn, mostly data centers)10–18
For site selection, the point is not which forecast is right. It is that many projects are competing for the same pipeline capacity, and Goldman Sachs has cited an average of about four years from the announcement of a gas transmission project to its in-service date.9
02Types of gas pipelines and who regulates them
| System | Regulation | Typical role | What to check |
|---|---|---|---|
| Interstate transmission | FERC for rates and certificates; PHMSA for safety5 | High-pressure, long-distance transport across state lines | Available firm capacity, tap policy, delivery pressure, whether a lateral fits blanket authority or needs its own certificate |
| Intrastate transmission | State commissions or agencies; PHMSA safety standards, often administered by the state5 | High-pressure transport within one state | Capacity, tariff terms, the operator’s willingness to serve a new large delivery |
| Local distribution company (LDC) | State public utility commission | Delivery to homes and businesses through smaller, lower-pressure lines5 | Main size and pressure, firm or interruptible service options, required system upgrades |
| Gathering lines | Lighter regulation that varies by state | Moving raw gas from wells to processing | Gas quality; raw gas may need processing before it suits generating equipment |
Large generation loads are usually best served directly from a transmission pipeline, either interstate or intrastate. Some local gas utilities can serve them through dedicated facilities, but it depends on the utility’s system and its state tariff. LDCs often give large customers a choice of service: CenterPoint Energy in Minnesota, for example, offers commercial and industrial customers firm, interruptible or combined firm and interruptible service, and customers with backup fuel can more easily accept interruption.11
Fig. 2From transmission pipeline to on-site plant
- 01Transmission pipelineInterstate (FERC) or intrastate (state); high pressure
- 02TapConnection on the existing line, often made while it stays in service
- 03LateralNew pipe on its own right-of-way to the site
- 04Meter and regulation stationMeasures gas and sets delivery pressure
- 05On-site generationTurbines, engines or fuel cells serving the campus
03Proximity is not capacity
A pipeline can run along the edge of a property and still have nothing to offer. Transmission pipelines sell capacity under contract, and firm service, which is not subject to prior claim by another customer, is the highest-priority service they offer.3 A fully subscribed line has no firm capacity left for a new customer. What remains may be interruptible service, which can be curtailed whenever it would interfere with higher-priority deliveries, often on the same cold or hot days when power demand is high too.3
Fig. 3Firm vs. interruptible gas transportation
For primary power
Firm
- Highest-priority service up to a contract maximum
- Reservation charge paid whether or not gas flows
- Long terms and credit support are typical
- Still exposed if supply itself fails in extreme cold
Interruptible
- Lower priority, curtailed when capacity is short
- Usually a commodity-only charge
- Workable when backup fuel is on site
- Curtailment risk peaks during extreme weather
Firm transportation is necessary but not always sufficient. In Winter Storm Elliott in December 2022, freeze-related production drops in the Marcellus and Utica shales pushed pipeline pressures down, and the FERC-NERC report counted 63 gas-fired generator outages or derates, about 10,038 MW, tied to curtailments of firm gas transportation.7 A data center that depends on gas for primary power should plan for that tail risk with dual fuel, storage or grid backup.
Key questions for any pipeline near a site:
- Is firm capacity available at or near the proposed delivery point, and in what volume?
- What delivery pressure can the pipeline hold at that point, and does it suit the turbines or engines without on-site compression?
- If capacity is short, would an expansion be required, and how does the pipeline solicit interest, such as through an open season?
- Are there other large new loads competing for the same capacity?
- Is there more than one pipeline within reach, which adds supply diversity?
04Taps, laterals and meter stations
Connecting a site to a transmission pipeline usually involves three pieces of infrastructure:
- The tap: a connection on the existing pipeline, often made while the line stays in service.
- The lateral: a new pipeline from the tap to the site, which needs its own right-of-way, crossings and permits. Its length and route drive much of the cost and schedule.
- The meter and regulation station: equipment that measures the gas and controls pressure, usually on its own small parcel or a defined area of the site.
Laterals for large loads can be substantial projects. To serve Entergy Louisiana’s plants supporting Meta’s Richland Parish campus, Energy Transfer is building a 12-mile lateral off its Tiger Pipeline with capacity of up to 1 Bcf a day, under a 20-year agreement announced in November 2025 for firm transportation of 250,000 MMBtu a day starting in February 2028.12
Depending on the pipeline and its size, the pipeline company may build and own the lateral, or the customer may build it and reimburse or transfer it. For interstate pipelines, smaller facilities can proceed under FERC’s blanket certificate program: as of 2026, up to $14.5 million per project automatically and, under a temporary waiver for projects in service by May 31, 2028, up to $61.65 million with prior notice.6 FERC proposed in May 2026 to raise the prior-notice limit to $86 million, though that is a proposal, not a final rule.613 Larger laterals need a full certificate. A lateral route crosses the same constraints as any linear project: wetlands, streams, roads, railroads and private land.
05Gas supply and transportation contracts
Gas service has two parts that are often contracted separately: the gas itself (the commodity) and the right to move it through the pipeline (transportation). A data center or its power provider might buy gas from a marketer or producer and hold a firm transportation agreement with the pipeline. Firm pipeline service typically carries a two-part rate: a reservation charge for the capacity and a commodity charge for the gas actually moved.3 When an LDC serves the site, the arrangement follows that utility’s tariff.
Firm transportation agreements typically run for long terms and require credit support, which matters for who signs them. The Energy Transfer and Entergy agreement that supports Meta’s Louisiana campus, for example, runs 20 years, from February 2028 through January 2048.12 For a bridge plan, the contract term has to match how long the equipment will run, and the exit has to be planned. For a permanent plant, gas contracting is a core part of the project’s financing. Our guide to firm transportation for data centers covers the terms in more detail.
06Pipelines crossing the site: easements and safety rules
A pipeline running through a property is both an asset and a constraint. The easement area generally cannot hold buildings, and roads, utilities and grading across it usually need the operator’s approval through a crossing or encroachment agreement. Easement width and terms vary by the original grant, so read the recorded document rather than assuming. Our guide to mineral rights and easements covers the title work.
Federal pipeline safety rules also matter. Under 49 CFR 192.5, PHMSA classifies gas pipeline by the number of buildings intended for human occupancy within 220 yards of the centerline along any continuous mile: Class 1 for 10 or fewer, Class 2 for 11 to 45, Class 3 for 46 or more, and Class 4 where buildings of four or more stories are prevalent. A segment also becomes Class 3 if it lies within 100 yards of a building or small outdoor area occupied by 20 or more people at least five days a week for ten weeks in any 12-month period.4 A staffed data center beside a line can meet that test, and a change in class location can require the operator to lower pressure or replace pipe, so raise it with the operator early.
Easements reduce usable acreage and can split a site in ways that make a campus layout harder. Our guide to gross vs. buildable acreage covers how to account for them.
07How to screen a site for gas access
When we screen a site where gas matters, we work from the map to the operator:
- 01Map transmission pipelines within a practical lateral distance, along with their operators and whether each is interstate or intrastate.
- 02Identify any pipeline easements on the site, pull the recorded documents and note the class location of nearby segments.
- 03Sketch a lateral route, note crossings and constraints along it, and estimate whether it fits under blanket authority.
- 04Contact the pipeline operator about firm capacity, pressure and tap policy at a specific delivery point.
- 05Check whether the local gas utility has rights or tariffs that affect service to the site.
- 06Plan for supply disruptions with backup fuel or grid service.
- 07Confirm the air permitting path, since gas without an air permit does not produce power (see air permits for generators).
Gas is one item in a broader site due diligence checklist, and it carries the most weight on projects that cannot wait for the grid. If you are weighing a site where gas is the path to power, you can get a site reviewed.
Common questions
How close does a data center need to be to a gas pipeline?
There is no fixed distance. What matters is whether a lateral from a pipeline with available capacity can be built at a reasonable cost and schedule. A short lateral across open land can be simple, while a longer one through wetlands, rail crossings or many private parcels can be hard. For scale, the lateral being built to serve the power plants behind Meta’s Louisiana campus is about 12 miles long.12
Can a local gas utility serve a data center power plant?
Sometimes. A local distribution company may serve a large generation load through a dedicated line or upgraded facilities, under its state-approved tariff.11 Many distribution systems, though, operate at pressures and volumes too low for large turbines or engine plants without major upgrades. In those cases a direct connection to a transmission pipeline is usually more practical.
What is firm gas transportation?
Firm transportation is a contracted right to move a set daily volume of gas through a pipeline, with the highest priority the pipeline offers, usually paid through a reservation charge. Interruptible transportation is cheaper but can be cut when the pipeline is full, often during extreme weather. A data center that relies on gas for its main power supply generally needs firm transportation and a backup fuel, since even firm service was curtailed for some generators in Winter Storm Elliott.7
Can you build a data center over a pipeline easement?
Generally not on the easement itself. Pipeline easements usually prohibit buildings and restrict grading, and roads or utilities crossing them typically need the operator’s written approval. Buildings can sit near the easement within the setbacks the operator and local rules require, but an occupied building within 100 yards of a line can affect its federal class location.4 The recorded easement document defines the specific width and restrictions, so review it during diligence.
Does a new gas lateral need FERC approval?
It depends on who builds and owns it. A lateral that an interstate pipeline builds as part of its system needs FERC authorization: as of 2026, many smaller projects proceed under the blanket certificate program within set cost limits, while larger ones need a case-specific certificate.6 Laterals owned by intrastate pipelines or local utilities follow state rules, and customer-owned lines raise their own jurisdictional questions, so confirm the path with counsel early.
Notes
- 1.Business Wire, “Energy Transfer and CloudBurst Sign Agreement for Natural Gas Supply to Data Center Project in Central Texas,” 2025. businesswire.com
- 2.Inspenet, “Williams sets quarterly record driven by natural gas demand,” 2026. inspenet.com
- 3.Eastern Shore Natural Gas, “Our Services,” n.d. esng.com
- 4.Legal Information Institute, Cornell Law School, “49 CFR § 192.5 - Class locations,” n.d. law.cornell.edu
- 5.U.S. Energy Information Administration, “Natural gas pipelines,” n.d. eia.gov
- 6.Troutman Pepper Locke, “FERC Proposes Increased Cost Limits and Other Changes to Natural Gas Blanket Certificate Program,” 2026. troutmanenergyreport.com
- 7.Power Engineering, “FERC-NERC final report: Natural gas struggled the most during Winter Storm Elliott,” 2023. power-eng.com
- 8.S&P Global Commodity Insights, “Grid challenges make dedicated gas generation best option for data centers: Kinder Morgan,” 2024. spglobal.com
- 9.Argus Media, “US gas industry pins hopes on AI power demand,” 2024. argusmedia.com
- 10.Enverus, “EIR forecasts modest impact on U.S. natural gas demand from data center expansion,” 2025. enverus.com
- 11.CenterPoint Energy, “Information for end-use customers in Minnesota,” n.d. centerpointenergy.com
- 12.Pipeline & Gas Journal, “Energy Transfer, Entergy Louisiana ink 20-year gas deal to power North Louisiana growth,” 2025. pgjonline.com
- 13.Willkie Farr & Gallagher, “FERC Proposes to Double Blanket Certificate Thresholds,” 2026. willkie.com
Have a site in mind?
Get a straight answer on your land.
Send a parcel number, an address, a map pin or a target load. We’ll tell you what it can support and what it would take.
This guide is general information about data center site selection. It is not engineering, legal, tax or investment advice. Requirements vary by state, utility and county, so confirm the specifics for any site with the relevant authorities and advisors.
Terms in this guide
Related guides
More in Water, gas & fiber
- Data Center Water Requirements and Cooling Choices
- Fiber Connectivity for Data Center Sites
- Climate, Cooling and Data Center Site Selection
- Reclaimed Water for Data Center Cooling
- Air vs. Liquid Cooling: What Each Needs From a Site
- Dark Fiber vs. Lit Services: Which Does a Data Center Site Need?
- How Long-Haul and Subsea Fiber Routes Affect Data Center Site Selection
- Water Rights and Groundwater Permits for Data Centers
- Wastewater and Cooling Water Discharge for Data Centers
- Water Stress and Drought Risk in Data Center Siting
- Closed-Loop and Waterless Data Center Cooling: What It Means for a Site
- Fiber Route Diversity and Latency for Data Center Sites
- Internet Exchange Points and Carrier Hotels: Why They Shape Data Center Markets
- Latency Requirements by Workload: Where Data Center Proximity Matters
- Municipal Water and Sewer Capacity for Data Center Sites: Treatment Plants, Extensions and Will-Serve Letters
- Data Center Heat Reuse and District Heating: EU Rules, Nordic Examples and U.S. Site Implications
Guide 2 of 18 in Water, gas & fiber · all 242 guides · glossary · calculators
